Title: Process Engineers Role in Project Management
1Process Engineers Role in Project Management
2Management of Engineering Project
- Preparation
- Developing The Team
- Project Duty Specification
- The Process Specification
- General Design Criteria
- Level of Detail
- Execution of Engineering and Installation
- Project Management
- Project Initiation
31. Preparation
- In order to appoint an EC it is necessary to
complete the following - Compile Project Duty Specification
- Develop contractors scope of work
- Develop contractual terms and contract itself
- Assemble the document inviting contractor bid
- Decide on the selection procedure for the
contractor appointment - Forms the basis of selected ECs scope of work
42. The Team Involved
- Company Middle management
- Senior personnel from engineering, purchasing and
legal department
53. Project Duty Specification
- The process specification
- General design criteria
- Any preliminary flow sheets
- Utilities specification
- Basis for economic evaluation
- Material of construction
- Equipment standards
- Instrument standards
64. The Process Specification
- Developed entirely by senior process engineer
- Gives precise terms of the plant required
- The number of units
- Its throughput
- The product yields and quality
- The required test standards
- Any salient process requirements
75. General Design Criteria
- Main input from project engineers with technical
check by process engineer supplies general data
associated with plant site The main topics
covered are - Scope
- Climatic data
- General design considerations
- Units of measurements
- Engineering Line Diagram/PID/PFD
- Utilities specification
- Basis of economic evaluations
- Material of construction
- Equipment standards to be used for sizing and
design - Instrument standards required
86. Level of Detail
- Request for contractor's quotes
- Less detail is supplied depending on contractor's
standards and criteria - More detail required to ensure good competitive
quotation - Complete project duty specification would also
contain details and criteria for other
disciplines, which have very little process input
which includes civil, structural, electrical and
piping
97. Execution of Engineering and Installation
- With limitless funds and time and no specific
quality anyone with little technical knowledge
can build a process plant - However in the real world constraints the art and
management skills are required for a successful
product i.e. project management and control
techniques.
108. Project Management
- Begins with forming a team of engineers necessary
to design, procure and erect the facility - Led by a project manager and supplemented by
project schedulers and cost estimators - All are senior members of respective disciplines
- Have the authority to direct the work for
quality, timeliness and cost
11 The project team organisation
- Project Manager
- Procurement Co-ordinators
- Area Project Engineers
- Project control team cost engineers, estimators
and schedulers - An engineering Manager
12 Typical project team organisation
Project Manager
Engineering Manager
Lead Piping Engineer
Lead Process Engineer
Lead EI Engineer
Lead Civil Engineer
Lead Mechanical Engineer
Design Coordinator
13The project team organisation
- Reporting directly to engineering manager are
lead engineers of the following disciplines - Process engineering
- Instrument engineering
- Electrical engineering
- Mechanical engineering
- Vessel, civil, piping and structural engineering
149. Project Initiation The Kick off meeting
- Formally releases the contractor to begin work
and describes clients requirements - Following above a less formal meeting of
contractors project team process engineer draw
from experience to high-light any pitfalls to
other disciplines e.g. coke formation in furnace
piping design to mechanical engineers - Project management aspect of the project are
discussed i.e.. Completion dates with major
milestones with indication of when cost estimates
are to be updated and when critical project
decisions would be made
15Lead Engineers Responsibility
- Maintain quality
- Keep with in the project schedule
- Cost in terms of person hours expended
- Prepare execution plan for approval by project
manager - Develop person hour budget and schedule to meet
the master plan implementation - Have the authority to direct work within their
discipline to meet the project objectives
16Design Coordinator's Role
- Maintain precise management control and interface
during the development of PID and Equipment data
sheets - Have similar authority as any lead engineer
- Act as single source between engineering and the
respective design functions ie flow of design
drawings, material take-off data etc into the
project - This project organization brings order into the
execution of the project.
17 The Project Procedure Manual
- Conferences and meetings
- Filing index
- Individual engineering, procurement and design
interface procedures - Drawing index
- Field organisation and directory
- Hand-over procedure and close-out reports
- Introduction
- Project Organisation and directory
- The master schedule
- Person hour budgets
- The cost code of accounts
- Project control procedures
- Correspondence and communication
The basic requirement of PM is compiled at this
early stage. An ideal time For key people to
contribute to this.
18 Preliminary schedules and budgets
- Project manager must establish execution plan and
measure the cost and preliminary schedules to
implement he plan. - This is followed by master plan budget and
schedule by input supplied by various lead
engineers and coordinators - First six months mainly for front end activities
bulk of process engineering is completed
followed by advising role and this concludes with
input to preparing operating manuals and
compiling data for process guarantees
19 Preliminary schedules and budgets
- Based on the scope of work process engineer
prepares an execution plan - Once approved by project manager lead process
engineer prepare a bar chart for front end with
person hour spread - This then followed by other disciplines with
their plan - Project manager then develops the initial overall
plan, master schedule and budget for the project
20Typical Process Engineering Schedule
21PID Conference and Approval
- In order to provide to other disciplines to
commence effective work, a major milestone in
achieving this objective is to conference the PID
and have it approved by the client - Although development of equipment data sheets
already allowed the mechanical engineering and
the procurement functions to start work but it is
the release of approved PID puts the project into
top gear.
22PID Conference Basic Guidelines
- Preparing for the conference
- Location and Attendees
- Conducting the conference
- The flow sheet conference is a necessary
activity but is nevertheless a high consumer of
time.
23Subsequent Process Activities
- Participation in equipment activities ensuring
safety, capacity and economy - Participation in plot layout development help
in locating various plant items, also
participation in plot layout conference for
clients approval. - Subsequent development of PID maintaining
control of technical content. Once per week
checking for addition and actions - Developing the operating and plant commissioning
manual - Process guarantees and Guarantee Test Run final
process engineers activity during the project
execution
24Typical Operating Manual
- Pre-startup conditioning of the plant
- Plant start up
- Normal operation and trouble shooting
- Emergency action and shut-down
- Normal shut-down
- Catalyst regeneration
25Typical Commissioning Instructions
- Pre-energising activities
- Energising the plant
- Conditioning equipment, calibrating instruments
and setting relief valves - Final check-out and closing up all vessels
- Preparation of start-up
- Start-up
- Lining out
- Performance test runs and guarantee test run
- Much of this done by the future operators of the
plant
26Concluding Remarks
- A process engineer plays a key role in both
development and execution of the project. - It is a very demanding/responsible role where he
needs to satisfy the clients requirements in
terms of design, plant performance through to
achieving guaranteed plant production.