Title: IAEA Procedure for International Collaborative Standard Problem ICSP


1
IAEA Procedurefor International
Collaborative Standard Problem (ICSP)
  • Jong-Ho CHOI
  • Division of Nuclear Power
  • IAEA

2
IAEA Procedure for ICSP
  • Draft was developed through the consultancy with
    CSIs of CRP on natural circulation based on the
    OECD document (CSNI Report No. 17 Rev. 4, March
    2004, CSNI International Standard Problem
    Procedures)
  • IAEA Draft Safety Guide DS349 Application of the
    Management System for Nuclear Facilities
    (Appendix II Management System for Research and
    Development Activities) was quoted for quality
    management

3
IAEA Procedure for ICSP
  • General Objectives of ICSPs
  • Provide a comparison of BE computer code
    calculations to experimental data
  • Evaluate the capability of computer codes
  • Proposals for ICSPs
  • Objective
  • Description of experimental facility
  • Description of experimental data
  • Initial and boundary conditions and brief
    description of test procedure

4
IAEA Procedure for ICSP
  • Specification of ICSP
  • Specific objective
  • Detailed description of experimental facility
  • Parameters to be measured
  • QA procedure for planning and conducting the
    experiment
  • Format of calculated results
  • Experimental data to be collected
  • Initial and boundary conditions
  • Schedule

5
IAEA Procedure for ICSP
  • Reporting of Analytical Predictions
  • Computer codes used for the ICSP
  • Analytical models, equations, assumptions and
    numerical method
  • Inherent limitations of the codes
  • Changes made in the codes to perform the ICSP and
    justification for changes
  • Availability of codes and users manual, computer
    requirements to run the codes
  • Description of simulation model
  • Sensitivity analyses to establish simulation
    model
  • Results of calculations

6
IAEA Procedure for ICSP
  • Comparison of Analytical Predictions versus
    Experimental Data
  • Facility description, and description of the
    points for which results are calculated by the
    codes
  • Comparison of calculated results with
    experimental data
  • Discussion of results, and through analysis of
    experience gained
  • Publication of Results of an ICSP
  • IAEA Nuclear Energy Series Report
  • Encouraged to present papers at relevant
    international conferences