Title: Alexandria University Hospitals PPP Project
1Alexandria University Hospitals PPP Project
Investor Conference June 18, 2008
2Discussion Overview
- PPP Objectives and Strategy
- Key Principles of the PFI Contract
- Transaction Structure Two Lots
- Allocation of Risk and Responsibility
- Service Provider - Profile Structure
- Key Issues for Discussion During Q A
- Project Time-line
3PPP Objectives and StrategyAlexandria University
Hospital Project
- General objectives of the University Hospitals
Project - Improve quality of facilities to international
standards - Increase cost-effectiveness of construction,
design, operation and management - Increase access to specialized hospital care
- Gynecology Hospital Blood Bank PPP aims to
- Rebuild a new Gynecology/Obstetrics University
Hospital at Smouha to provide patient care,
teaching and research for gynecological and
obstetric services - Rebuild a new blood bank
- New Mowassat Hospital PPP aims to
- Build a Center of Excellence for Neurology and
Urology that will provide a number of highly
specialized care services on an inpatient and
outpatient basis
4Key Principles of the PFI Contract
- The Government transfers responsibility and risk
for hospital assets, non-clinical and some
diagnostic services to the Service Provider. - Service Provider takes on obligations for 20 or
more years. - Service Provider designs, builds, maintains
hospital assets and provides non-clinical and
some diagnostic services. - Lenders fund Service Provider on limited recourse
basis. - Government pays an Availability Payment for
available and acceptable hospital service for
duration of long-term PFI contract - Detailed PFI contracts specifying performance
obligations
5Transaction Structure - Two Lots
? Consortia will be able to bid on one of two
lots, or on both
Lot 1
Lot 2
Mowassat Center of Excellence
Gynecology Hospital Blood Bank
- Finance, design, construct, equip and operate all
non-clinical services of a new OB/GYN hospital
and a Blood Bank - Part of a 3-part hospital complex incl. Emergency
Pediatrics - Gynecology Hospital 200 beds emphasis on
out-patient / short-stay - Blood Bank Estimated 100,000 - 120,000 donors
and 200,000 blood products per year
- Finance, design, construct, equip and operate all
non-clinical and some diagnostic services of
Alexandrias 1st high-quality hospital of
international standards as two Centers of
Excellence - Nephrology/Urology
- Neurosurgery
- Around 230 beds
6Allocation of Risk and Responsibility
Private sector
Public sector
Public / Private sector
Allocation of Risk and Responsibility
Capital Funding
Equipment
Facility Maintenance
Non-Clinical Services
Clinical Services
Hospital Management
Clinical Support Services
Construction
7Service Provider - Profile
- The PPP Contract will be signed by the University
of Alexandria and a Special Purpose Vehicle
(SPV) to be legally incorporated prior to
bidding. - The Government is providing investors with
considerable flexibility in forming their SPV
consortium to best suit their needs, strengths
and interests. - A typical SPV structure within the PPP
contractual arrangement is shown in the following
slide however, the SPV could take many different
forms.
8Service Provider - Structure
- The following schematic illustrates the private
and public sector roles in the PFI model and how
we envisage the SPV to be structured
MoF/MoHE
CLINICAL SERVICES
Availability Payment
Budget
NON-CLINICAL SERVICES
Alexandria University
SPV
9Key Issues for discussion during Q A
- Contract term Is there investor interest to
lengthen the contract for 20 years? - Medical equipment How should replacement of
equipment in technology over the course of the
project be determined? - Design How specific should design
specifications - be?
- Diagnostic services Is there investor interest
to take on more of the clinical specialty areas? - Availability Payment How will the payment
mechanism be set? (frequency, inflation
adjustment, etc.)
10Project Timetable
May
Apr
Mar
Feb
Jan 2009
Dec
Nov
Oct
Sept
Aug
July
June
Draft Tender Docs
Due Diligence
Bidder Conference
Bid submission deadline
Sign PPP Contract
Data Room
Pre-Bid Meeting Site Visits
Technical Evaluation
QA
Finalize Tender Docs
Prequalification
Commercial Bid Opening
Winning Bidder Selected
Issue final RFP Tender Docs
11(No Transcript)