B180, gantry cranes for EC (2t), EMEC (4t), HEC (4t) clean-rooms (all installed ... 21 cranes to be installed for the 4 LHC experiments ... – PowerPoint PPT presentation

Number of Views:56
Avg rating:3.0/5.0
Slides: 13
Provided by: ijoa4
Category:

less

Transcript and Presenter's Notes

Title: Cranes ATLAS, ALICE, CMS and LHC-b Experiments and Machine


1
Cranes ATLAS, ALICE, CMS and LHC-b Experiments
and Machine
  • Update situation
  • at 11 March 2003
  • C. Bertone ST-HM

2
Contents
  • Cranes for ATLAS (Experiences and Machine)
  • Planning problems and solutions
  • Cranes for ALICE (Experience and Machine)
  • Cranes for CMS (Experience and Machine)
  • Cranes for LHCb (Machine)

3
Cranes for ATLAS
  • 12 cranes for ATLAS, 4 contracts in place
  • F280 contractor Italkrane (I)
  • cranes SF1 (3,2t), SUX1 (8t), SH1 (10t)
  • F420 contractor Brunnhuber (D)
  • cranes SX1 (280t et 20t), UX15 (65t et 65t), SDX1
    (16t)
  • CA1180208 contractor Stahl (D)
  • B180, crane cleanroom Barrel (6,3t installed in
    2001)
  • CA1187451 contractor Quentin Levage (F)
  • B180, gantry cranes for EC (2t), EMEC (4t), HEC
    (4t) clean-rooms (all installed and commissioned
    in 2002)

4
ATLAS Cranes status
  • F280 contractor Italkrane (I)
  • SF1 3,2t. Installation completed in February
    2001. Commissioned.
  • SUX1 8t. Installation completed in September
    2000. Commissioned.
  • SH1 10t. Installation completed in September
    2002. Commissioned.

5
ATLAS Cranes status
  • F420 contractor Brunnhuber (D)
  • FC done June 2001.
  • SDX1 16t. Commissioned in October 2002
  • SX1 280t. Commissioning foreseen the 2nd June
    2003
  • SX1 20t. Commissioning foreseen in September
    2003
  • UX15 2x65t. Commissioning foreseen in June 2003

6
Crane SX1 tambours
7
Cranes for ALICE
  • F420 contractor Brunnhuber (D)
  • One crane UX25 (40t), installed and commissioned
    in November 2002.

8
Cranes for CMS
  • 7 cranes for CMS, 2 contracts in place
  • F280 contractor Italkrane (I)
  • cranes SF5 (3,2t), SUX5 (8t), SH5 (10t), USC55
    (10t)
  • F276 contractor TAIM (ES)
  • SX5 (80t and 80t), UXC55 (20t)
  • New crane SDX5 (10t) to be studied and integrated
    in one of the contract

9
CMS cranes status
  • F280 contractor Italkrane (I)
  • SF5 3,2t. Installation completed in 2001.
    Commissioned.
  • SUX5 8t. Installation completed in 2001.
    Commissioned.
  • SH5 10t. Installation completed in 2002.
    Commissioned.
  • USC55 10t. Installation foreseen in July 2003.

10
CMS crane status
  • F27610 contractor TAIM (ES)
  • FC done September 1998.
  • SX5 2x80t on feet. Commissioned in year 2000.
  • UXC55 20t. Commissioning foreseen for June-July
    June 2003 (according to CE schedule)
  • New crane to be installed in SX5 (or SDX5?) under
    discussion with both contractors

11
Cranes for LHCb
  • 1 crane LHCb,
  • F280 contractor Italkrane (I)
  • cranes SDH8 (5t). Installed and commissioned in
    2001.

12
Conclusions
  • 21 cranes to be installed for the 4 LHC
    experiments
  • 6 cranes still to be installed (4 for ATLAS, 2
    for CMS)
  • 1 under discussion (CMS)
  • Satisfactory results and delays
  • Simultaneous worksites
  • plannings continuously changing up to the
    delivery (penalties almost inapplicable)
  • Difficulties to manage the restricted spaces
    (caverns)
  • Clients continuously changing technical
    parameters up to the delivery