Development in Practice: A Case Study - PowerPoint PPT Presentation

1 / 38
About This Presentation
Title:

Development in Practice: A Case Study

Description:

We are a multi discipline planning practice, involved in a range of development ... 22 unit scheme relates to the Roebuck Rise and Durant Rise area, now implemented. ... – PowerPoint PPT presentation

Number of Views:33
Avg rating:3.0/5.0
Slides: 39
Provided by: sbr98
Category:

less

Transcript and Presenter's Notes

Title: Development in Practice: A Case Study


1
Development in Practice A Case Study
  • Steven Brown (Bsc Hons DipTP MRTPI)
  • Associate
  • Woolf Bond Planning

2
Introduction Presentation Format
  • The Practice
  • The Case Study
  • Planning History Background
  • Planning Policy Position
  • Constraints to Development
  • Planning Policy
  • The Planning Application
  • The Councils Decision
  • Tactical Approach
  • The Appeal
  • Observations
  • Client Cost Implications

3
Preamble
  • The Practice
  • We are a multi discipline planning practice,
    involved in a range of development schemes across
    England.
  • Projects vary from strategic site promotion,
    major urban expansion proposals to medium and
    small-scale development projects.
  • We offer specialist advice on housing land supply
    issues and advise on the form, content and layout
    of development schemes.
  • Accordingly, we promote often difficult and
    controversial schemes at the application and
    appeal stages.

4
Purpose
  • The aim of the presentation is to give LPA
    officers an insight into how the development
    industry approaches development opportunities and
    the complications that often arise

5
Linkages
  • No development brief
  • Earlier planning permissions now time expired
  • Windfall site
  • A number of problems have arisen before, during
    and after the application stage
  • Key issue is whether the problems (dealt with
    below) could have been avoided had such a brief
    been prepared for the site

6
The Case Study
  • Client TA Fisher (house builder)
  • The site
  • Rectangular, situated within the settlement
    boundary of Tilehurst, to the west of Reading
    (see Handout Figs. 1, 2 3).
  • Occupied by three detached dwellings (No.s 1053,
    1055 and 1057 Oxford Road) with long curtilage
    depths to the road frontage (See Handout Figs 4
    5)
  • Adjoins built development
  • Tree belts.
  • Change in levels of 15 metres
  • Site extends in total to approx 1.58 hectares.
  • Densities of surrounding area
  • Represents a housing development opportunity,
    brownfield site, urban area,
  • A PPG3 compliant scheme

7
(No Transcript)
8
(No Transcript)
9
Planning History Background
  • Outline planning applications were submitted in
    1989 proposing the erection of 24 and 46
    dwellings on land at 1063 1069 Oxford Road and
    1053 to 1069 respectively
  • Both applications were refused by the Council but
    subsequently allowed on appeal
  • In allowing the appeals the number of dwellings
    was reduced by the Inspector from 24 to 17 and 46
    to 43 respectively.
  • The 1989 appeal decision established the
    principle of residential development on the site.

10
  • Both permissions were overtaken by events in that
    subsequent consents were granted and implemented
    in the 1990s for development in two phases on the
    western part of the site. Phases I and II have
    been completed, resulting in a total of 22
    dwellings. This leaves the potential for some 21
    dwellings on the remaining part of the site.
  • The 22 unit scheme relates to the Roebuck Rise
    and Durant Rise area, now implemented. (See
    Handout Figs. 3, 6 7)
  • If the terms of the Inspector's decision on the
    46 (amended to 43) unit application are to be
    followed this would allow for the construction of
    a further 21 dwellings on the case study site
    (Handout Fig.3 edged red)

11
Construction and Ownership
  • Our clients acquired and built land parcels A and
    B as phases I and II of the development (22
    houses).
  • They own No. 1053 Oxford Road but have no control
    over the in-between properties (No.s 1055 and
    1057 Oxford Road).
  • Ransom issue concerning delivery of comprehensive
    scheme. However, only feasible access is via
    Durant Way. Not possible to provide a new access
    from Oxford Road (a classified Road).
  • Therefore, only means of developing the site is
    via an extension to the existing cul-de sac
    through land not controlled by our developer
    client
  • Issue of deliverability and land valuation
    concerning the middle parts

12
Constraints to Development
  • Character of the surrounding area
  • Density
  • TPOs
  • S.106 requirements (Inc. affordable housing
    provision)
  • Land ownership, Site Assembly
  • No development brief to guide comprehensive
    development of the site
  • Local opposition
  • The above factors, allied to the development plan
    policy position, were taken into account in the
    preparation of the application proposal

13
Planning Policy
  • Section 38(6) Planning and Compulsory Purchase
    Act
  • Adopted Berkshire Structure Plan to 2006
  • West Berkshire District Local Plan to 2006
  • Emerging Replacement Structure Plan

14
  • Structure Plan Policy seeks to ensure that
    development is sustainable in its location and
    form.
  • Local Plan Policy implements Structure Plan
    Policy at the District level and seeks to locate
    development within the existing settlement
    pattern
  • However, Structure Plan Policy EN1 seeks to
    protect and enhance the environment of built up
    areas only permitting development which is
    appropriate in scale, form, impact, character and
    siting to its location
  • Local Plan Policy adds a further constraint to
    allowing development in urban areas, only
    allowing development where it would not give rise
    to an unacceptable impact on the character or
    appearance of an area or the amenities of
    neighboring land uses
  • Structure Plan Policy seeks to ensure that
    development is sustainable in its location and
    form.

15
PPG3 Housing
  • Paragraphs 57 and 58 refer to the need to make
    the best use of land, and encourage local
    planning authorities to avoid developments which
    make inefficient use of land (those of less than
    30 dwellings per hectare net).
  • The appeal scheme represents a density of 30.4
    dwellings per hectare. It accords with PPG3
    density advice and also reflects the character of
    the surrounding area and is a direct response to
    the need to protect existing tree belts and TPOd
    trees.

16
  • This PPG also gives consideration to issues of
    design. Paragraph
  • 56 states
  • New housing development of whatever scale
    should not be viewed in isolation. Consideration
    of design and layout must be informed by the
    wider context, having regard to any immediate
    neighbouring properties but the townscape and
    landscape of the wider locality
  • (Our emphasis).

17
Circular 01/05
  • Circular 1/05 which requires schemes in the South
    East of England to
  • achieve PPG3 compliant development on sites in
    excess of 1 hectare.
  • The appeal proposals in this respect are fully
    compliant in the sense
  • that the site extends, gross, to 1.58 hectares
    and some 48 dwellings
  • are proposed, yielding a density of
    30.4 dwellings per hectare.
  • This is the minimum requirement to meet PPG3
    Annex C based on
  • gross site calculation

18
The Planning Application
  • The application followed a detailed and
    comprehensive assessment of the planning policy
    position, a site and local area appraisal and
    discussions with the Local Planning Authority.
  • The process can be summarised as follows
  • Site appraisal
  • Planning report prepared for client advising on
    merits or otherwise of development potential
    having regard to, inter alia, policy position
  • Draft scheme prepared
  • Discussions between architects, planners,
    landscape architect, arboricultutist, highway
    consultants and client
  • Preferred scheme drawn up
  • Details submitted to the LPA
  • Meeting held and scheme discussed/ negotiations
    (S.106 etc.)
  • Revisions to scheme
  • Application submitted

19
  • The principal constraint to development of the
    site was identified as being the character of the
    surrounding area
  • However, schemes required to accord with PPG3
    requirements
  • The application was submitted in outline in
    January 2003 with all matters other than means of
    access reserved for subsequent approval.
  • At the request of the Council, details of siting
    and landscaping were added for approval, leaving
    only design and external appearance as reserved
    matters
  • The scheme proposed the demolition of 3 existing
    detached dwellings and the redevelopment of the
    site to provide 33 houses and 15 apartments (30
    affordable housing)
  • At that stage the affordable housing provision
    was to be paid for off site (LPA request)
  • The proposals are shown on Fig.6 attached with
    the handouts.

20
(No Transcript)
21
  • The site plan layout demonstrates the range and
    type of dwellings to be provided as part of the
    appeal proposal including a mix of terraced, link
    detached and flatted development
  • Overall the site comprises 1.58ha, of which 0.41
    would be taken up by open space. The density of
    the scheme is 30.4ha
  • The application represents a density at the
    bottom end of the range encouraged by Government
    guidance towards making efficient use of housing
    land, respecting also character of area.
  • In designing the 48 unit scheme our clients have
    also sought to respect the concerns of local
    residents and to respond to
  • their perceptions of the character of the area.
  • It was considered that the scheme satisfied all
    necessary requirements of the Development Plan

22
During Consideration
  • During 2003, and because of the ransom issue
    relating to access between Durant Way and No.
    1053 Oxford Road, the owners of properties 1055
    and 1057 Oxford Road submitted a scheme to the
    LPA for housing development on their plots only,
    with access from Oxford Road.
  • The company objected to these proposals on the
    grounds that the scheme was not economical and
    also on the grounds that it would result in
    piecemeal development
  • The scheme was subsequently withdrawn on the
    advice of the LPA.

23
The Councils Decision
  • The Officers of West Berkshire Council
    recommended approval of the 48 unit application.
  • The report to committee supported the scheme and
    identified site will have to be developed at a
    higher density. In officers opinion, no
    material harm will result on the character of the
    area or amenities of adjoining development.
  • Further stated that overall, the proposal is
    considered an acceptable form of development,
    which complies fully with both national
    objectives and local plan policies.
  • Officer report requested a number of developer
    contributions, including
  • Commuted maintenance sum for transfer of the open
    space (26,840)
  • Financial contribution toward education provision
  • Contribution to highway works
  • Affordable housing provision

24
Reason For Refusal
  • Notwithstanding the officer recommendation to
    approve the scheme, the application was refused
    for the following reason
  • The proposed development of 48 units would
    result in an
  • unacceptable overdevelopment of the site which,
    by failing to take
  • account of and reflect the nature and density of
    surrounding
  • development, would produce a built form out of
    sympathy with the
  • established character of the surrounding area
    which would result in
  • significant and unacceptable detriment to its
    existing amenities. If
  • allowed the proposal would set a precedent which
    would make
  • further applications on similar sites in the
    locality harder to resist.
  • The proposal is therefore contrary to provisions
    of policies

25
Our View
  • Council decisions are frequently contrary to
    officer recommendation.
  • Frustrating for development industry, leading to
    significant delays in
  • project delivery
  • In order for higher density development to be
    accommodated within
  • the urban area it is inevitable that changes of
    this nature will be
  • necessary and will have to be accepted and
    accommodated. The
  • implication otherwise is that the requirements of
    PPG3 cannot be
  • achieved. There will inevitably be change
    brought about by sustainable
  • development opportunities in built up areas.
  • An appeal against the decision was subsequently
    lodged with the
  • Inspectorate.

26
Tactical Approach
  • Following the refusal of the 48 unit application
    a subsequent application was submitted by our
    clients for the erection of 39 dwellings only.
    Details of the form and layout of the proposed
    development are shown on Handout Fig.7 attached.
  • The scheme was submitted as a direct response to
    the refusal of the 48 unit scheme by reducing the
    density of deleting the flatted block.
  • The 39 unit scheme has a density based on PPG3
    Annex C of just in excess of 25 dwellings per
    hectare
  • The 39 unit application was based on an
    interpretation of PPG3, Annex C, to the effect
    that trees and landscaped area on the northern
    and southern parts of the site could be defined
    as significant buffer strips and excluded from
    the site area for the purposes of density
    calculation.

27
(No Transcript)
28
  • This derives a reduced site area of 1.28ha,
    yielding a density of 30.46ha
  • As a practice our view is that this approach did
    not accord with our interpretation of PPG3 Annex
    C
  • Following negotiations with the LA Officers, the
    scheme was recommended for approval.
  • At this stage the LPA then requested affordable
    provision on site
  • Again, notwithstanding officer support, the
    scheme was refused.

29
Barker Report
  • Published for the ODPM in March 2004
  • The Barker Report identifies that political
    decisions often reflect negative local attitude
    to development.
  • Referred to in the context of setting housing
    numbers but equally relevant to the consideration
    of planning applications at the local level.

30
The Appeal
  • The appeal was lodged against the Councils
    decision to refuse the 48 unit scheme.
  • We did not appeal the 39 unit scheme
  • The grounds of appeal and subsequent Rule 6
    statement cited PPG3 grounds for the
    acceptability of the scheme.
  • A statement of common ground and a core documents
    list was prepared by the appellant parties.
  • In preparing the appeal, further detailed work
    was carried out by the appellant company, to
    include a contextual appraisal and preparation of
    an illustrative diagram to show the impact of the
    proposed flatted block on the street scene.
  • Clearly, there are cost implications (for the
    client) in taking matters to appeal

31
Developer Contributions
  • Prepared in accordance with S.106 TCP Act 1990,
    S.278 Highways Act
  • Because our appellant client does not have a
    legal interest in the whole of the site, the
    contributions are triggered by the commencement
    of development on any part of the site.
  • Unilateral undertaking to cover
  • Educational facilities (300,000)
  • Highway Improvements (115,000)
  • Omitted open space requirements as based on draft
    SPG
  • In addition, requirement for 30 affordable
    housing (14 units)
  • Because our appellant client does not have a
    legal interest in the whole of the site, the
    contributions are triggered by the commencement
    of development on any part of the site. Scheme
    for affordable housing required at RM stage.
  • Inspector satisfied that, given our clients
    control over the point of connection to Durant
    Way which is required to provide access to the
    development, there is sufficient interest in the
    land to provide reasonable assurance that the
    obligations would be delivered.

32
Inspectors Decision
  • The Inspector considered the main issue in the
    determination of the appeal as the effect the
    proposal would have on the character, appearance
    and amenity of the locality having regard to
    local and national policies on sustainable
    development
  • Character
  • Appearance
  • Amenity

33
Decision
  • The Inspector concluded
  • Although the proposal would contrast with nearby
    development in terms of density,
  • such contrasts, together with an increased
    perception of built form, are to be expected
  • as a result of pursuing a greater intensity of
    development ion sustainable locations which
  • such low existing densities
  • On the main issue that there would be serious
    harm would not be caused to the
  • character, appearance, and amenity of the
    locality, and that the proposal accords both
  • with the development plan on these matters and
    sustainable development objectives
  • The appeal was allowed. Affordable housing
    provided on site through Grampian
  • conditions

34
General Observations
  • LPA support for scheme
  • Developers willing to enter into S.106 agreement
    provided there is a justification for the
    commuted sum
  • PPG3 density advice provides for higher density
    schemes.
  • Change in character not necessarily a bad thing
  • Supported by Inspectorate
  • Officers open to proposals, whilst seeking to
    ensure that schemes accord with development plan
  • Councillors protect local voter interest. NIMBY.

35
Client Cost Implications
  • Our client has developed Phases I and II for a
    total of 22 dwellings. The remainder of the site
    remains undeveloped, albeit with the benefit of
    an extant (? delivery) planning permission for 48
    units.
  • Significant costs in promoting development,
    including
  • Purchase No. 1053 Oxford Road (750,000)
  • Application Fee (3,520)
  • Consultants Fees/Counsel (100,000)
  • Education Contributions (300,000)
  • Highway Contributions (115,000)
  • No Open Space contribution
  • Build costs (_at_35 value) 5m
  • TOTAL 6.26M

36
Summary
  • The case study is an illustration of where you
    have significant land assembly issues.
  • Represents an example of where you have a single
    land owner preventing development from coming
    forward.
  • Phases I and II have been built. Phase III now
    permitted (48 units) but no certainty as to
    deliverability
  • Our clients have been involved with this site for
    in excess of ten years and it is still yet to
    come forward despite having a scheme and S.106 in
    place.
  • Each property is worth IRO 750,000 as a private
    market dwelling house
  • However, how do you value the different interests
    in this example?

37
  • TA Fisher have a ransom issue
  • How do you value No. 1055 Oxford Road in terms of
    implementing the planning permission
  • How, in turn, do you value No. 1057 Oxford Road.
  • Value of end plot (No. 1053)
  • Is there a mathematical answer or is it simply a
    matter for negotiation?

38
End Result
  • Planning Permission granted, with necessary S.106
    contributions.
  • Expensive exercise for developer client in
    pursuing scheme to appeal
  • No certainty that scheme can be delivered
  • Worked example of how local resident objections
    have delayed the planning process but ultimately
    worked against them.
  • They could have had a 39 unit scheme and off site
    provision of affordable housing
  • By forcing the developers to appeal the PPG3
    compliant scheme (48 units) the result is
    (subject to implementation and delivery!) a
    higher density scheme with on site affordable
    housing provision.
Write a Comment
User Comments (0)
About PowerShow.com