Task%20C%20Activities%20in%20the%20CMS%20Experiment - PowerPoint PPT Presentation

About This Presentation
Title:

Task%20C%20Activities%20in%20the%20CMS%20Experiment

Description:

The NSF CAREER Award won by GL in June 2003 allowed us to expand in the new ... uncovered and fixed many trigger simulation bugs and cleaned up ORCA code and ... – PowerPoint PPT presentation

Number of Views:47
Avg rating:3.0/5.0
Slides: 27
Provided by: gregl167
Learn more at: http://physics.bu.edu
Category:

less

Transcript and Presenter's Notes

Title: Task%20C%20Activities%20in%20the%20CMS%20Experiment


1
Task C Activities in the CMS Experiment
  • Greg Landsberg
  • DOE Site Visit
  • September 28, 2006

2
Brown and CMS
  • Next energy frontier and a natural way for our
    group to evolve is LHC
  • While have realized this a while ago, it would
    have been a hard decision to move part of our
    DOE-supported group away from DØ w/o stretching
    thin our major responsibilities there
  • The NSF CAREER Award won by GL in June 2003
    allowed us to expand in the new direction w/o
    compromising our DØ strength
  • Why CMS?
  • Better detector
  • Strong Fermilab presence allowing for an
    adiabatic transition
  • December 2003 formal application to join CMS
  • March 2004 presentation of our application at
    the CMS Week
  • June 2004 Brown was voted in and became a full
    member of CMS
  • At the same time, Ryan Hooper, a new RA to work
    on DØ and CMS has been hired using the NSF Grant
  • Based on our strong ties with Fermilabs SiDet,
    we have joined Tracker Outer Barrel construction
    project
  • Where do we stand now, two years since weve
    joined?

3
CMS Soon to be Lowered!
September 2006 CMS Week
4
CMS Explained
Jos Engelen, SLAC 2006 Summer School
5
CMS All-Silicon Tracker
Brown group involvement
Outer Barrel (TOB)
Pixels
End Caps (TEC 12)
Inner Barrel Disks (TIB TID)
2,4 m
5.4 m
volume 24.4 m3 running temperature 20 0C
6
TOB Construction
  • Major hardware project accomplished via joint
    effort of Brown, Fermilab, KU, Rochester, UCSB,
    UIC, and UCR
  • Two mirror production facilities Fermilab and
    UCSB
  • Some TOB statistics
  • Total number of modules 5208 5 spares
  • Total number of rods 688 5 spares
  • Total silicon area 1000 ft2
  • Total silicon weight 100 lbs
  • Brown involvement QA, rod assembly, single-rod
    test stand
  • People GL, Ryan Hooper, Hai Duong Nguyen,
    Patrick Tsang, Scott Wolin, several more SS
  • Rod production took place in FY2006
    (November-July)
  • Uncovered and fixed many problems since mid 2005
  • Common mode noise in ST sensors replaced w/
    Hamamatsu
  • Wire bond breakage due to vibration module
    encapsulation
  • I2C communication problems redesigned cards
  • Degradation of the Ag-based epoxy bias connection
    switched to wire-bonding
  • Sensor damage due to discharges between the
    ground and the silicon surface encapsulated
    wire bonds and modified HV power supplies
  • Despite the unexpected delays, the project has
    been successfully finished
  • All the rods have been assembled, tested, and
    delivered to CERN on time!

7
Rods Single-Rod Test Stand
Single-Rod Test Stand (SRT),and the Brown Box
for reading rod temperature.Over 700 rods went
through SRT
An assembled rod and its readout end
8
Typical SRT Rod Failure
SRT Opto Scan and Noise
Saturated AOH laser channel
9
TOB at CERN Rods Being Installed
10
Actual Rod Installation
100 mm axial precisionover the length of therod
(3ft)! 0.5 mil/sensor!
11
LPC Activities
  • LHC Physics Center (LPC) at Fermilab has been
    founded in 2004 as a Mortar and Brick
    foundation to accommodate critical mass of
    experts and support LHC physics efforts by the US
    community
  • Brown group was one of the first groups to join
    (GL served on the Advisory Board in 2004-2005
    Yuri Gershtein, than a Brown RA, became a
    convener of the e/g group)
  • Many successes, from thorough work on development
    and optimization of ID algorithms within the new
    CMS software framework, to support of MC physics
    studies by students and software tutorials
  • Helped our group to move to CMS adiabatically,
    without compromising the DØ connection
  • LPC grew significantly over the last two years
    still remains to be seen if the critical mass of
    experts can be achieved during CMS running
  • Could serve as a good alternative to maintaining
    the core of the group at CERN (COLA, remoteness,
    need to relocate several people at once)
  • 2007 LHC pilot run will serve as a proof of
    principle
  • In 2005-2006 GL took a year-long sabbatical
    supported by LPC and has been appointed as the
    LPC Trigger Group convener
  • Meenakshi Narain just started as an LPC b-tagging
    Group convener
  • Maintain LPC office space to provide students,
    postdocs, and commuting faculty with excellent
    working conditions

12
Triggering at Hadron Colliders
  • ee- colliders low total cross section, low
    rates
  • Trigger pretty much on everything, perhaps with
    the exception of very forward processes
    (low-angle Bhabha)
  • Hadron colliders enormous cross section,
    unattainable rates
  • Trigger is very selective
  • Only small fraction of collisions is written to
    tape
  • Additional complications due to pile-up
  • LHC
  • stot 110 mb, sin 70 mb
  • L 1034 cm-2s-1 10 nb-1s-1
  • 25 ns bunch crossing
  • Total rate 109 s-1 or 20/crossing
  • An order of magnitude more complex triggering
    than that at the Tevatron

PDG
13
Trigger Architecture
  • Must reduce 2.5-40 MHz of input interactions to
    50-100 Hz
  • Do it in steps/successive approximations
    Trigger Levels

x400 rejection
x1000 rejection
14
CMS Level-1 Trigger Scheme
Muons
Electrons, Photons, Jets, MET
3lt?lt5 ?lt3 ?lt3
?lt2.1 0.9lt?lt2.4 ?lt1.2
15
LPC Trigger Group
  • Charge in concert with the international CMS
    Online Selection PRS group
  • Simulate, develop, and maintain L1 and High-Level
    Trigger algorithms
  • Work on creating realistic trigger table for the
    startup pilot run, as well as for low and high
    luminosity physics running
  • Maintain and operate Remote Operations Center
    (ROC) at Fermilab a mirror control room for the
    experiment
  • Participate in the MTCC (Magnet Test Cosmic
    Challenge) shifts and data monitoring and
    analysis
  • LPC Trigger Group Statistics
  • About 25 active members
  • Regular biweekly meetings (one later this
    afternoon!)
  • Two successful workshops (L1 HLT) in the past
    year
  • Deep connection with Online Selection PRS group

16
LPC Trigger Group Activities
  • Contribution to vol.2 of the CMS Physics TDR
    (Brown, Fermilab, Wisconsin)
  • Trigger tables and rates (Brown, Fermilab,
    Wisconsin)
  • Optimization of the L1 Calorimeter trigger
    (Brown)
  • L1 calorimeter calibration and jet energy
    corrections (Brown, Wisconsin)
  • Implementation of the L1 calorimeter emulator in
    the CMSSW framework (TAMU, Wisconsin)
  • HLT Jet/MET trigger suite implementation and
    timing studies (Brown, UIC)
  • Remote Operations and Control (Fermilab,
    Maryland Brown is getting involved)
  • Test beam and cosmics data analysis (Fermilab,
    UIC)
  • Calorimeter noise studies (Brown, Rochester, UIC)
  • Minbias trigger design (UIC)

17
L1 Calorimeter Trigger Optimization
  • Pursued by GL and Sara Vanini
  • Focus on the basics
  • Systematic studies of noise
  • Adjusting trigger thresholds to match noise
  • Optimizing trigger algorithms
  • Improving turn-on and resolution
  • Improving MET resolution
  • In the process uncovered and fixed many trigger
    simulation bugs and cleaned up ORCA code and
    propagate fixes into CMSSW
  • Example
  • greatly improved single jet trigger turn-on an
    important tool for multiobject triggers (ejets,
    mjets, etc.)

Original defaultthresholds
ETgen, GeV
Optimized thresholds
ETgen, GeV
18
Hardware Implementation
  • Proposed optimized thresholds have been endorsed
    and approved by the CMS HCAL Electronics and
    Trigger groups
  • They are currently being implemented in firmware
    and the new L1 emulator code
  • Brown group spearheads this effort and will redo
    simulations with the new software
  • Also work on implementing and simulating dynamic
    baseline subtraction scheme
  • Energy is determined as a weighted sum E ?fiEi
    over several time-slices

TB04
5 70 23 2
  • Automatic baseline subtraction ?fi 0
  • Being implemented for HCAL fi -1.0, -1.0, 1.0,
    1.0
  • Will require slight timing realignment (1 ns)
  • Robust against coherent noise and hot cells

19
L1 Calorimeter Trigger Calibration
  • Problem CMS calorimeter is
  • Non-linear
  • Non-compensated
  • Has h-dependent response
  • Goal correct for these deficiency via proper
    calibration either at the jet or the trigger
    tower level
  • New L1 JES corrections
  • Fit (or take the mean) of ETgen ETL1
    distributions in bins of ET, h
  • Effect on MET in Wjets
  • Left ME resolution
  • Right ME pull
  • Corrections remove pull ?, but worsen the
    resolution by similar amount ?
  • Next step introduce new dimension in tower
    calibration e/h

GL, Scott Wolin
GL, Sara Vanini
20
Future Plans
  • CMS Hardware Commissioning
  • Our current CMS hardware project has been a
    success, but it came to an end
  • Important to maintain hardware experience in the
    group, especially given new students and postdocs
    joining the group
  • Want to maintain close ties with the US Silicon
    Consortium work well together, common goal in
    bringing tracker online
  • Will participate in TOB commissioning via ROC in
    MTCC-II (later this year) and underground SX5
    cosmic running (2007)
  • Consider manning test beam and commissioning
    shifts at CERN via short-term visits
  • SLHC Upgrade
  • A lot of opportunities for new major hardware
    efforts
  • Participate in the SLHC Steering Group meetings
    and SLHC workshops
  • CMS SLHC LoI will go to the funding agencies
    later this year
  • Hope for enthusiastic support from you guys!
  • Discussed participation in the following areas
  • Construction of a part of the CMS silicon tracker
    replacement
  • L1 tracking trigger design and construction
    (hardware firmware)
  • More in Meenakshis presentation

21
The LHC Schedule Winter 2006
  • Physics running 140 days/year
  • ATLAS/CMS running 100 days/year
  • Typical efficiency for physics 40
  • Effective ATLAS/CMS running time/year 1000
    hours 4 x 106 s 4 x 1038 cm-2 4 x 1014 b-1
    400 pb-1 _at_ 1032cm-2s-1
  • Note that the schedule below R. Bailey, Aspen
    2006 is all goes well scenario

2010, 25ns L1x1034 cm-2s-1?Ldt 40 fb-1
Pilot run, 75ns L5x1030 cm-2s-1?Ldt 20 pb-1
2008, 75/25ns L3x1032 cm-2s-1?Ldt 1.2 fb-1
2009, 25ns L1x1033 cm-2s-1?Ldt 4 fb-1
22
Revised LHC Schedule (Summer 2006
  • Pilot 2007 Run
  • Starts 2 months later than previously expected
  • Accelerator runs at injection energy (450 x 450
    GeV pp)
  • Expected luminosity 1029 cm-2s-1
  • Collision data sometimes in November 2007 50
    nb-1
  • Three-month shutdown following with 14 TeV data
    in Spring 2008
  • The goal to deliver a few fb-1 by the end of the
    run
  • The rest of the schedule stays the same

23
CMS Physics
  • All what we have been doing is really driven by
    our desire to become major players in the CMS
    physics, in the same way we maintained physics
    leadership within DØ over the last 15 years
  • Currently focus on low-level task optimization,
    validation, and certification of trigger,
    reconstruction and particle ID
  • See Tulikas talk on this
  • Actively contributed to the Volume 2 of the CMS
    Physics TDR
  • Getting involved in the Pilot 2007 Run data
    analysis as a preparation to the 2008 physics run
  • Picking/negotiating physics topics to work on
    from rediscovering SM with the first data to
    searches for black holes at the LHC
  • Use our two-decade experience and leading role in
    the Tevatron physics as a guiding star

24
(Wo)manpower on CMS Doubling!
  • FY2006
  • Greg Landsberg PI (90)
  • Tulika Bose RA (50)
  • Ryan Hooper RA, NSF (75)
  • Sara Vanini VRA (75)
  • Zongru Wan VRA (20)
  • Hai Duong Nguyen GS, MO (100)
  • Patrick Tsang SS (25)
  • Scott Wolin SS, UTRA (20)
  • Total 4 FTE
  • FY2007
  • Dave Cutts PI (50)
  • Greg Landsberg PI (80)
  • Meenakshi Narain PI (50)
  • Tulika Bose RA (75)
  • Leonard Christofek RA (50)
  • Selda Esen RA, NSF (100)
  • Aram Avetisyan GS (75)
  • Paul Huwe GS (40)
  • Hai Duong Nguyen GS (100)
  • Patrick Tsang GS (100)
  • 2-3 SS (50-75)
  • Total 8 FTE
  • FY2005
  • Greg Landsberg PI (30)
  • Ryan Hooper RA, NSF (100)
  • Hai Duong Nguyen SS, MO (25)
  • 3 Temps SS (75)
  • Total 2 FTE

25
Our Newest Addition to the Group
  • Selda Esen, who is graduating from Turkish
    University of Cukurova this week and will start
    with us on October 1
  • CMS thesis based on jet studies and HCAL
    test-beam data analysis
  • Will work 100 on CMS and replace Ryan Hooper
  • Supported by the NSF grant

26
Conclusions
  • Our 2004 bid for LHC, made possible by the NSF
    support, has paid up
  • Our group is now well-plugged and recognized
    within the CMS community and has contributed to
    several aspects of hardware, firmware, and
    software
  • Our adiabatic transition from DØ to CMS has been
    successful we still maintain important
    responsibilities in DØ (Luminosity Monitoring,
    Level 3/DAQ, B-physics, Top, Single Top, New
    Physics Searches), while ramping up our CMS
    effort
  • Our CMS involvement doubled every year since we
    have joined CMS while such a growth cant be
    sustained much longer, its up to you to ensure
    that it will continue
  • LHC is imminent three years from now we very
    well may be reporting a major discovery made
    possible by the Brown group efforts!
Write a Comment
User Comments (0)
About PowerShow.com