About This Presentation
Title:

THERMATEK SERVICE SPE Alaska Luncheon 17th January 2006

Description:

Thermatek Service General Overview. Thermatek Service Drilling Applications. ... Water Shut Off: Shell Gannet Field in the UK North Sea. ICOTA Presentation & SPE ... – PowerPoint PPT presentation

Number of Views:86
Avg rating:3.0/5.0
Slides: 35
Provided by: hbl1
Category:

less

Transcript and Presenter's Notes

Title: THERMATEK SERVICE SPE Alaska Luncheon 17th January 2006


1
THERMATEK SERVICESPE Alaska Luncheon17th
January 2006
  • Presented by Bruce Robertson

2
Presentation Overview
  • Thermatek Service General Overview.
  • Thermatek Service Drilling Applications.
  • Thermatek Service Conformance Applications.
  • Case Historys.
  • Operations to-date summary.
  • Questions and Answers.

3
THERMATEK SERVICE General Overview
4
Introduction Thermatek was invented and
patented several years ago by a mud engineer
based in Kazakhstan The technology was
licensed by Halliburton in Jan 04 and purchased
outright in April 2005. It has a successful
and developing track record in the North Sea,
Middle East, Mexico and Malaysia. Halliburton
has initially selected 5 market areas to support
in the commercialisation of the Thermatek
Service. North Sea Middle East Mexico M
alaysia Alaska
5
  • What is THERMATEK ?
  • Thermatek is a temperature activated family
    of non-invasive rigid setting fluid
    compositions that are used to provide a range of
    near-wellbore SOLUTIONS!
  • Main Applications Severe Lost Circulation
  • Water / Gas Shut Offs
  • Annular Plugs
  • Consolidation Plugs
  • ALL Thermatek Fluids are characterised by a
    controlled right angle set followed by rapid
    development of compressive strength.
  • The fluids right angle set is a reaction to
    exposure to a specified temperature for a
    specified period of time. The higher the
    temperature the shorter the set time. Unaffected
    by pressure applied to the slurry.
  • The temperature activation results from a
    combination of exothermic reaction from the fluid
    chemistry temperature transfer from the
    formation.
  • The short set time, followed by rapid
    development of compressive strength, is the key
    to designing Thermatek interventions.

6
Key Properties of Thermatek Rigid Setting Fluids
Once set, Thermatek has mechanical
characteristics similar to cement - but it is
definitely not cement.
  • Predictable and consistent right angle set.
  • Rapid build up of compressive strength.
  • Slight expansion on setting (1 - 2).
  • Zero static gel generation.
  • Will not invade formation.
  • 100 Acid Soluble with 15 HCl.
  • 100 return permeability.
  • Immiscible in oil.
  • H2S and CO2 resistant.
  • Tolerates up to 50 contamination with water /
    drilling muds.

7
THERMATEK SERVICE Drilling Applications
8
Primary Applications in Drilling
  • Thermatek Thru-bit Lost Circulation Material.
  • Thermatek to Consolidate Formation.
  • Thermatek Thru-bit Kick-Off Plug. (under
    development)
  • Thermatek as Zonal Isolation Material.

9
Thermatek LCM
  • Thermatek as a Lost Circulation Material comes
    in 2 different forms and is generally used when
    no other avenue is available to the operator, or
    when high rate (100bbl/hr) losses are
    anticipated prior to drilling an interval.
  • Thermatek LC (Lost Circulation)
  • Thermatek low or high temperature fluid can be
    pumped through the drilling BHA and is designed
    to set up soon (5 20 min) after entering the
    loss zone, bringing the well back under control.
  • Thermatek RSP (Rapid Setting Plug)
  • Thermatek RSP is pumped in a similar manner to
    Flex-plug, with an active slurry pumped down the
    drill string to react with an aqueous based fluid
    pumped down the back-side of the drill string.
    The two fluids meet and mix below the BHA
    resulting in a gunking material which will
    quickly stem flow to the loss zone and then
    develop compressive strength for permanent zone
    sealing.
  • Thermatek RSP is not temperature sensitive.

10
Thermatek - LC
  • Thermatek LC has been used successfully in
    several geographic regions to control losses in
    excess of 600 bbl/hr. The success of an
    application relies as much on obtaining quality
    data from the customer as it does on the
    predictability of the fluids set time.
  • Key Points
  • Placed safely through the drilling BHA.
  • Material is used as a lost circulation treatment
    for major fracture losses, typically gt
    100 bbl/hr. Below this conventional LCMs may be
    sufficient.
  • It is non-invasive and acid soluble allowing it
    to be used safely in producing formations.
  • Thermatek is used to shut off losses quickly and
    effectively in highly deviated and horizontal
    sections as well as vertical wells.
  • Typical treatment sizes are 15 35 bbl.
  • The challenge is to pre-engineer the Lost
    Circulation plan so that drilling operations can
    re-commence within 8-12 hours of hitting initial
    losses.

11
Thermatek LC
  • Highest Up-side for Successful Shut Off
  • Very small particle size allows Thermatek to be
    Pumped thru the bit to eliminate time
    consuming and costly trips in and out hole.
  • Treatments are designed with very short set time
    after exiting the BHA (5 20 mins)
  • Thermatek has a right angle set transition
    from fluid to solid.
  • Rapid generation of compressive strength follows
    the initial right angle set. (Reducing WOC times)
  • Even with high compressive strength Thermatek is
    easily drilled out from well-bore.
  • Thermatek is non-invasive to the producing
    formation. Its temperature activated set
    prevents fluid from entering the formation.
  • Acid soluble with a solution of 15 HCl
  • Surface equipment and lines are easily cleaned
    with water.

12
Thermatek LCPLACEMENT PROCEDURE
Thermatek LCPLACEMENT PROCEDURE
  • Thermatek Placement

13
Thermatek - Rapid Setting Plug
  • Thermatek RSP has been developed in response to
    specific well-bore conditions where Thermatek-LC
    cannot be used due to temperature restrictions,
    or where static loss rates are so high that the
    standard Thermatek-LC treatment is less
    effective.
  • Thermatek-RSP is a newly developed Thermatek
    formulation and we are actively seeking field
    application opportunities that fit some or all of
    the following criteria
  • Wellbore temperatures during losses in excess of
    2500F.
  • Water based drilling fluids.
  • Static loss rates in excess of 100 Bbls/hr.
  • Thermatek RSP can only be used with water based
    drilling fluids.


14
Thermatek - RSPHOW DOES IT WORK?
  • The Thermatek-RSP treatment is split into an
    active fluid and a reactive fluid PUMPED IN
    A RATIO OF 4 1
  • The active (Thermatek) fluid is pumped to the
    loss zone down the drill string and through the
    drilling BHA.
  • The reactive fluid (aqueous drilling fluid) is
    pumped down the drill string annulus to the loss
    zone.
  • The two fluids meet and mix below the drilling
    BHA as the Thermatek exits the BHA into the
    wellbore.
  • A strong gunk is formed within 60 secs of the
    fluids mixing and this quickly and effectively
    shuts off flow to the loss zone.
  • Thereafter, the heat from the formation causes
    the Thermatek to set, with compressive strength
    up to 1000 psi developing within 2-3 hrs to
    provide a permanent isolation plug that will not
    wash away or be extruded into the loss zone.
  • Thermatek RSP is un-restricted by bottom-hole
    temperature.
  • It is non-invasive and acid soluble - allowing
    it to be used safely in producing formations.
  • Typical treatment sizes are 15 35 bbl.


15
Thermatek - Formation Consolidation
Thermatek can be used as a Formation
Consolidation (FC) treatment to consolidate
specific well sections prior to changing mud
weights up or down to drill lower well sections.
  • The Thermatek - FC Treatment can prevent the
    occurrence of the following well problems
  • Induced fracture losses as a result of drilling
    lower sections with the high mud weights required
    to prevent collapse of upper sections into the
    wellbore.
  • Sloughing of upper well sections and stuck pipe
    as a result of reducing mud weights to levels
    that are required to drill lower well sections.

Thermatek is pumped through the drilling BHA and
used to squeeze off loose or unconsolidated sand
or shale sections. If the section cannot be
squeezed off consolidation may still be achieved
by under-reaming and squeezing a Thermatek plug
over the section. After set the original wellbore
diameter is drilled through the Thermatek plug.
16
Thermatek - Kick Off Plug
  • This application is currently under development.
  • Test projects using various additives are
    on-going to attempt to reduce the drillability
    of Thermatek to attain a slurry design which can
    be pumped through the BHA, set quickly and have
    suitable mechanical properties to allow kick-off
    from the plug.

17
Thermatek - Zonal Isolation Plug
  • Thermatek has been used successfully to protect
    the producing formation from impairment damage
    during cementing / completion operations.
  • Deployed through the drill string / BHA after
    the well is TDd, the plug is left over the top
    of the producing formation for removal by
    drilling / milling with coiled tubing after the
    well has been completed.
  • A cross linked K-max pill is pumped ahead of the
    treatment to provide support to the Thermatek
    fluid until the set time is reached.

18
THERMATEK SERVICE Conformance Applications
19
Thermatek Primary Applications in Conformance
  • Zonal Isolation Water / Gas Shut-Off.
  • Temporary production formation protection.
  • Gravel pack / Sand screen selective shut-offs.
  • Remedial Casing Repairs

20
Thermatek - Water / Gas Shut Off
  • Mixed and pumped from surface with standard
    cementing equipment.
  • Very small volumes can be placed accurately.
  • Placed through work-string, coiled tubing or dump
    bailed. Can be pumped through drilling / milling
    assemblies or lubricated into B-annulus if oil
    based fluid.
  • Near well-bore solution, if there is a
    requirement to seal off in formation matrix,
    additional, polymer based gels are usually
    required.
  • Used to seal off fracture communication between
    water injectors and oil / gas producers.
  • In applications where we do not wish Thermatek to
    pass through sand screens, we use a bridging
    agent which prevents slurry from re-entering
    annulus.

21
Thermatek - Production Formation Protection.
  • Due to the low depth of penetration and the acid
    solubility nature of the set product Thermatek
    has been used to protect reservoir intervals to
    allow intervention to be carried out in other
    intervals. Once removed via milling and
    acidizing, full production was restored.
  • Suitable for most formations, however is
    dependant on permeability and presence of natural
    fractures to ensure product can be contacted with
    acid to remove.

22
Thermatek -Remedial Casing Repair.
  • Controlled right angled set is the most important
    characteristic when designing jobs to rectify
    flow or pressure emanating from secondary
    annulus.
  • As the fluid is immiscible in oil based fluids it
    can be lubricated into B-Annulus to sink to leak
    zone or designed to set up in the annulus if no
    injection rate can be established.
  • As with any setting fluid placed in an annulus, a
    full work-over including cutting / milling the
    tubing would be required should the completion
    need to be replaced in future.

23
Thermatek - Gravel Pack / Sand Screen Selective
Shut-Off
  • Laboratory testing confirm Thermatek can be
    pumped through a 16/30 sand gravel pack, however
    cannot be pumped through 20/40 sand gravel pack.
  • Results on each test above shows the 16/30 pack
    to be completely consolidated, with the filtrate
    setting up with considerable compressive strength
    (gt 1500 psi), however whilst the test with 20/40
    sand did consolidate the pack, the filtrate did
    not contain enough solids to develop compressive
    strength.
  • In applications where we do not wish Thermatek to
    pass through sand screens, we use a bridging
    agent called Delta P which prevents slurry from
    re-entering annulus

24
THERMATEK SERVICE Case Historys
Water Shut Off Shell Gannet Field in the UK
North Sea. ICOTA Presentation SPE Water Shut
Off Centrica Resources Limited Rose Field in UK
Southern North Sea. SPE 94175 Water Shut Off
BP Amethyst Field in UK Southern North Sea.
Lost Circulation Shell F6 Wells in Sarawak
Field in Malaysia (SPE paper once campaign
complete) Lost Circulation PDO in Fahud Field
in Oman
25
Thermatek-WS Case Study
  • North Sea Operator has a field which was 85
    100 watered out and considered to be nearing the
    end of its economic life.
  • Logs acquired in March 2002 showed the oil rim
    had been displaced upward into the gas cap.
  • Oil rim could be significantly drained from the
    heel of these wells
  • The wells chosen were watered out
  • Opportunity to learn more about the reservoir and
    prove fluids efficiency.
  • Engineered designs, selectively placing small
    quantities of Thermatek to shut-off water
    producing zones and re-perforating above the oil
    rim has rejuvenated the field and extended its
    life.
  • Interventions typically paid for themselves
    within 70 days.

26
GA-14S1
  • Run 1 Drift on CT
  • Run 2 MPNN
  • Run 3 Bridge Plug
  • Run 4 Tubing Punch
  • Run 5 Cement retainer
  • Run 6 ThermatekTM ZIM
  • Run 7 Perforating
  • Run 8 Retrieve SSSV Protector from
    Nipple


TUBING HANGER
GROUND LEVEL
5-1/2", 17lb/ft, L80, 13
10-3/4", 55.5lb/ft,
Cr, Tubing _at_ 2183'
L80 XO 2021'
AHBDF (2176' TVBDF)
AHBDF (2017'
TVBDF)
13-3/8", 68lb/ft, N80 Casing
Shoe _at_ 4411' AHBDF
(4347' TVBDF)
4", 9.5lb/ft, L80, 13 Cr,
Tubing _at_ 7828' AHBDF
(7328' TVBDF)
9-5/8", 47lb/ft, L80, Casing Shoe _at_ 7894' AHBDF
(7356' TVBDF)
Perforations at 7955ft AHBDF
Cement retainer set at 7962ft AHBDF
Holes punched in 4 liner
ThermatekTM ZIM Squeezed away
Bridge plug set at 8117ft AHBDF
7", 29lb/ft, 13Cr, Liner Shoe 7446' TVBDF (8491'
AHBDF)
Pre-packed screens
4" Liner Shoe 7446' TVBDF (11460' AHBDF)
27
Gannett Field Results
28
Thermatek-LC Case Study
  • F6 Area in Sarawak, Malaysia consistently
    incurred high-rate losses (gt11 bpm) while
    drilling through the Carbonate reservoir
    interval.
  • Previous experience of pumping multiple cement
    plugs proved unsuccessful, time consuming and
    potentially damaging to the reservoir.
  • A revised drilling schedule and method was
    engineered to cure losses rapidly and allow
    completion to be run.

29
  • Losses in excess of 660 bbl/hr incurred in 6 OH
    reservoir interval.
  • Drilled well to TD using dynamic mud-cap method
    while on losses
  • Intended to place plug inside 7 Liner to allow
    completion to be run prior to CT removal.
  • 1 x 15 bbl Thermatek treatment actually entered
    loss zone and cured the losses. Allowing
    completion to be run.
  • CT RIH and tagged plug, acidized and brought
    well onto production.
  • Down-Hole temperatures were lower than
    anticipated, which delayed the set time allowing
    the plug to travel further than expected.
  • Well Sounder technology was invaluable for
    determining loss rates and fluid level drop-off.
  • Trial continuing in February 2006.

30
THERMATEK SERVICE Operations to Date Summary
31
Operations to Date Summary
  • Water / Gas Shut-Off
  • 17 operations performed to date with 94
    success rate.
  • 6 for Shell and 2 for BP in the UK.
  • 6 for Pemex in Mexico.
  • Temporary Isolations
  • 1 operation successfully performed for Pentex
    oil UK Ltd. Removed with 15 HCl, full production
    regained.
  • Permanent Isolation
  • 6 operations performed to date with 80 success
    rate.
  • 1 for Shell in UK, 1 for Maersk in Denmark and 3
    for BP in Alaska.

32
Operations to Date Summary
  • Lost Circulation
  • 3 successful operations performed in Oman for
    PDO where total losses gt10 bpm were cured with
    single 25 bbl treatments.
  • 1 successful operation performed in Sarawak,
    Malaysia for Shell where total losses were cured
    with single 15 bbl treatment to allow completion
    to be RIH prior to removal with 15 HCl on CT.
  • Dump Bailer Operations
  • 3 successfully placed operations have been
    completed to date.

33
Major operators Who Have approved use of
Thermatek
  • Shell UK.
  • Chevron USA.
  • PDO Oman.
  • Talisman Energy Resources Ltd.
  • Gaz de France.
  • Total (Pau).
  • BP (Aberdeen).
  • Centrica.
  • Pemex.

34
THERMATEK SERVICE Questions and Answers