Title: The evolution of Service Planning in Transnet Freight Rail
1The evolution of Service Planning in Transnet
Freight Rail
Rail Planning Workshop and MultiRail Users
Conference Princeton, New Jersey,21-23 October
2008
21863 to 2008 145 years of evolution
3Agenda
Where is Transnet Freight Rail?What does our
network look like?The role of Service Planning
in the Business ProcessService Planning
challenges in a South African contextService
Planning in the late 1900sNew Service Planning
focus
4South African ports are important links to most
continents
5Southern African Rail Network
6Transnet Freight Rail Network
30 of the core network carries 95 of general
freight tons
Heavy Haul (Iron Ore export)
Heavy Haul (Coal export)
7The role of Service Planning in the Business
Process
8Generic Planning Process Key Elements
Strategy Business Environment
Information-Communication Technology Management
(ICTM) Plan
Safety Plan
Corresponding safety plan for the change in
operational activities
Tons revenue by sector, commodity, OD-pair,
customer, corridor
Train and yard personnel to staff the required
integrated train plans
Marketing Sales Plans
Operations Plan
Human Capital Plan
Required train schedules individual service
designs
Maintenance costs to realise the scheduled train
service
Maintenance Plan
Capacity Plan
No investment
Required number of locomotives, wagons, crew and
network (infra capacity)
Engineering Plan
Investment
Capex required to increase rolling-stock infra
capacity to required levels
Investment Plan
Financial Plan
Pro forma financial statements that highlight
revenue, Opex and impact of Capex on the
bottom-line
Risk Identification Mitigation
9Service Planning Challenges ..
10Transnet Freight Rail Network
Locomotives can only be deployed on certain lines
11Transnet Freight Rail Network
Different maximum axle loads have to be considered
12Transnet Freight Rail Network
Different train authorisation systems affect
point to point running times
13Different services require different operating
models
14Service Planning in the late 1900s
- Up to the mid 1980s services designs were mostly
based on a push philosophy - Working timetables were produced to handle wagon
load traffic - Wagon loads were pushed from yard to yard in the
general direction required - Yard productivity was measured on whether it was
cleared at the end of a shift - Transit times were long as there was little focus
on handling consignments efficiently - In the late 1990s a pull philosophy were
slowly introduced (Predictable Service) - Wagon load trains were serviced by a
hub-and-spoke network of 32 major hub-yards and
connecting links - Trains were scheduled through the network with
defined trip plans and point to point running
times based on actual test trains - Individual highly customised train designs were
produced from these schedules to suit individual
customer requirements - Trains were switched on by a demand trigger
called the Next Weeks Business - Consignments were reserved on wagon load trains
- Last system wide analysis and implementation of a
country wide (national) train plan based on these
principles was in 1998 - Used RPM (Rail Planning Model)
- Since then only customer specific designs and
corridor focused changes were introduced without
redesigning the entire network (incremental
approach)
15New Service Planning Focus
- Incremental additions to the national train plan
resulted in - Sub-optimising of individual service corridors
- Complicated blocking rules linked services and
shared train slots - Duplication of trains with insufficient wagons
per train - Widely differing daily schedules to accommodate
customers that do not have daily consignments - Complicated crew working relying on trains
keeping to running times - Excessive yard shunting with resultant high
costs, risks and transit times - As part of Transnets growth strategy, a decision
was taken to redesign the national train service
plan from a clean sheet perspective (Zero Base
Operating Plan) - To have a fixed, simple and repetitive weekly
time table - Maximize the number of mandatory trains and
provide capacity for additional traffic - Minimize the number of times a wagon is handled
to improve current train transit and wagon
turnaround times - Substantially reduce the number of marshalling
yards and redesign the blocking rules accordingly - Quarterly updates on the Zero Base Plan to
address new market operational requirements
16Design Objectives for Zero Base Operating Plan
Reason
Design Objective
- To achieve minimum 30 wagon train size for 1
train in and out per day - To achieve daily service (At least 5 days/week)
- Must handle at least 60 wagons per day
Ops Yard
- To achieve maximum efficiency for 24 hour
operation - Originates and terminates 1 train per hour (20
trains in, 20 trains out per day
- Must handle at least 600 wagons per day
Hub Yard
- Simplifies planning and execution
- Maximizes utilization of ring-fenced locomotives
and wagons
- Must handle minimum 30 wagons per train
- Must operate at least 3 times per week
megaRAIL Trains
- Simplifies and standardizes plan
- Provides better utilization of locomotives and
wagons - Concentrates management focus on handling
deviations to plan
- S1 and S2 average train size of 30 wagons
- Must operated at least 5 days/week
accessRAIL Trains
Repetitive Plan
- Manage the exceptions
- Predictable safe working environment
17Example Combine irregular wagon load traffic
into regular full trainsThe new plan will move
traffic more regularly and reliably
- The objective of the new plan is to improve
service and reduce costs through - Improved train capacity utilization on the vacuum
brake network - Improved locomotive and wagon utilization on all
trains, with a particular focus on the vacuum
brake train network
Old Schedule
- Timber from MAM to RCB and/or MWI 11 trains/week
- Ferro-manganese from COR to RCB a few days/week.
- Any day 2 or 3 short trains operating between MAM
and RCB.
New Plan
- One train daily to handle all three flows.DAILY
OPERATION!
18Example Densification of the core networkFocus
train density on core network to improve train
capacity and locomotive utilization
Vacuum Traffic Flows
TFR Network to Bypass BFX
- Cape Corridor becomes main trunk
- Increased time partially offset by elimination of
1 locomotive change - Improved network density
- Lower maintenance costs
- Reduction in overheads
- Better asset utilization
- Larger train sizes
19Operating Plan Implementation To achieve the
Zero based Plan benefits, a well conceived
implementation plan PLUS an operate to plan
culture is needed requiring 2 cultural shifts
1. Plan Driven Operating Results
2. 100 Operate to Plan
- Issue mandatory fixed train plan for
- - megaRAIL AND accessRAIL
- Pre-allocate all
- Locomotives - Crews
- Slots - Wagons
- Minimum 5 days/week
- Simplifies resource planning AND plan execution
- Maximizes asset utilization
- Conditional flexiRAIL trains
- Operate only AFTER resources to mandatory trains
allocated (plus sufficient slack) - Planned 7 days in advance and updated up to 48hrs
in advance (as markets require) - Quarterly review of mandatory fixed train plan to
accommodate market and operational changes
20Operating Plan Implementation To achieve Zero
based Plan benefits careful implementation plan
PLUS an operate to plan culture is needed
requiring 2 cultural shifts
1. Plan Driven Operating Results
2. 100 Operate to Plan
- All TRAINS must run to plan regardless!
- This positions resources correctly for ongoing
maximum utilization for - Locomotives
- Wagons
- Crews
- Enables management of exceptions only
- Predictable, safer working environment
21Operating Plan Implementation (Our credo)To
achieve the cultural shift - perseverance and a
methodical approach is required
- We require persistence to address
- Geography
- Scope of activities, and
- Cultural change
- All work will be aligned with existing TFR work
streams and initiatives - We will communicate early and clearly so everyone
understands the plan, its objectives and their
individual responsibilities - We will measure performance constantly to ensure
success - We must be prepared for when deviations occur
- Create Recovery-to-Plan capabilities
- Position spare resources strategically to
facilitate recovery-to-plan - Assess and eliminate root causes, through process
analysis and improved designs - Schedule to typical, achievable running times,
not the best possible running times - Consistent, repetitive trains are preferred to
minimum transit times with high variability
Implementation will not proceed to the next route
until all agreed upon targets have been met
22Our new baby is here . Wish us good luck!
23Thank youAny questions?