Title: Methodology
1Critical Steps in Process Design
Michel Gigon, Associate, Laporte Consultants
September 28, 2006
2Agenda
- Definitions and General Considerations
- Critical Steps in Process Design
3Definitions
- Product Development Creation of a new product
- Process Development Development of a production
method (recipe) - Process Design Design of the equipment required
for the production of a product, according to a
pre-determined process.
4Process Design in the pharmaceutical industry
Process Design versus Product Life Cycle
5(No Transcript)
6(No Transcript)
7(No Transcript)
8(No Transcript)
9The four pivots of process design
Mechanical
Automation
Science
Process
Validation
Pharmaceutical Process
10Project Life Cycle
11Conceptual design
- Definition of the user requirements
- Process
- Production capacity
- Product specification
- Development phase of the product
12Conceptual design
- Definition of the user requirements
- Process
- Pilot plant unit operations, lab procedure
example - First commercial plant lab method, preliminary
results from pilot plant - Subsequent facility existing process
-
13Conceptual design
- Definition of the user requirements
- Production capacity
- Requirements (kg/year, units/year)
- Batch size (kg/batch, units/lot)
- Titre (kg/L)
- Production time (days/lot)
- Production schedule (24/7, 8/5)
- Operation (by campaign, by lots)
- Production opening (weeks/year)
- Losses ()
- Equipment utilisation ()
-
14Conceptual design
- Definition of the user requirements
- Production capacity
- Requirements (kg/year, units/year)
- Batch size (kg/batch, units/lot)
- Titre (kg/L)
- Production time (days/lot)
- Set-up, production process, cleaning,
sterilisation, testing, product change-over. -
15Conceptual design
- Definition of the user requirements
- Production capacity
- .
- Equipment utilisation ()
- Pilot plant 20-50
- First commercial plant 70 max
- Mature process gt 80
-
16Conceptual design
- Definition of the user requirements
- Product specification
- Sterility
- Water quality
- Concentration
- Impurity levels
-
17Conceptual design
- Definition of the user requirements
- Development phase of the product
18Conceptual design
- Definition of the user requirements
- Process
- Production capacity
- Product specification
- Development phase of the product
- Risks
- Inability to manufacture the product
- Inadequate plant capacity
- Lower quality product
- Inappropriate flexibility
19Preliminary design
- Facility definition and sizing
- Preliminary specifications of the process
equipment - Sizing of utilities
- Sizing of spaces
- Preliminary specifications of the automation
system
20Preliminary design
- Facility definition and sizing
- Preliminary specification of the process
equipment - Volume, capacity
- Material
- Functionality
- Process paramaters
- Design and operation range (pressure,
temperature, etc)
21Preliminary design
- Facility definition and sizing
- Sizing of utilities and spaces
Process equipment
Spacesproduction, mechanical rooms, warehouse
Process supportCIP, solution prep
Building utilitiesHVAC, Steam, chilled water,
power
Process Utilitieswater, effluent treatment
22Preliminary design
- Facility definition and sizing
- Preliminary specification of the automation
system - Manual vs automated operation
- Transfer panel vs manifold
- Level of automation
- Local controller, unit operation control,
batching, archiving - General architecture
23Preliminary design
- Facility definition and sizing
- Risks
- Inadequate process equipment
- Insufficient space and utilities
- Inadequate control and automation
- gt Production capacity cannot be met
- gt Difficulties of operation
24Detailed design
- Detailed specification of all components of the
installation - Mechanical components
- Fabrication specification
- Installation specification
- Automation
- Hardware
- Software
25Detailed design
PID
Sequences of operation
I/O List
Components List
Automation components specifications
Alarms InterlocksAccess rights
Mechanical components specification
Control panel drawings loop diagram wiring
diagram
Installation drawing (3D, isometrics)
Programming
26Detailed design
- Detailed specification of all components of the
installation - Risks
- Inappropriate installation
- Cleaning and sterilisation issues
- Corrosion issues
- Operational difficulties
- Maintenance difficulties
- Accessibility issues
27Construction and Fabrication
- Construction follow-up
- Documentation follow-up
- Start-up and testing (FAT, SAT)
28Construction and Fabrication
- Construction follow-up
- Ergonomy and accessibility
- Slopes
- Dead legs
- Weld quality
- Etc
29Construction and Fabrication
Update of design document (PID, specifications)
Data SheetsIsometricsTest Certificates
Turn-Over Package
Maintenance
Validation
30Construction and Fabrication
- Start-up and testing
- Verification of the quality of fabrication
- Verification of all design hypothesis
- Control of process parameters
- Process sequences are achievable
- Equipment drainable, cleanable and sterilisable
31Construction and Fabrication
- Construction follow-up
- Documentation follow-up
- Start-up and testing (FAT, SAT)
- Risks
- Inadequate installation
- Cleaning and contamination issues
- Ergonomic and operational issues
- Inadequate documentation
- Validation issues
- Maintenance issues
32Validation
- Adequate documentation facilitates protocol
preparation and execution - Review of validation criterion can avoid
unnecessary deviation - Participation in protocol execution facilitates
and accelerates protocol execution
33