Methodology - PowerPoint PPT Presentation

1 / 33
About This Presentation
Title:

Methodology

Description:

Critical Steps in Process Design. Michel Gigon, Associate, Laporte ... Dead legs. Weld quality. Etc... Construction and Fabrication. Documentation follow-up ... – PowerPoint PPT presentation

Number of Views:21
Avg rating:3.0/5.0
Slides: 34
Provided by: mgi6
Category:

less

Transcript and Presenter's Notes

Title: Methodology


1
Critical Steps in Process Design
Michel Gigon, Associate, Laporte Consultants
September 28, 2006
2
Agenda
  • Definitions and General Considerations
  • Critical Steps in Process Design

3
Definitions
  • Product Development  Creation of a new product
  • Process Development  Development of a production
    method (recipe)
  • Process Design  Design of the equipment required
    for the production of a product, according to a
    pre-determined process.

4
Process Design in the pharmaceutical industry
Process Design versus Product Life Cycle
5
(No Transcript)
6
(No Transcript)
7
(No Transcript)
8
(No Transcript)
9
The four pivots of process design
Mechanical
Automation
Science
Process
Validation
Pharmaceutical Process
10
Project Life Cycle
11
Conceptual design
  • Definition of the user requirements
  • Process
  • Production capacity
  • Product specification
  • Development phase of the product

12
Conceptual design
  • Definition of the user requirements
  • Process
  • Pilot plant unit operations, lab procedure
    example
  • First commercial plant lab method, preliminary
    results from pilot plant
  • Subsequent facility existing process

13
Conceptual design
  • Definition of the user requirements
  • Production capacity
  • Requirements (kg/year, units/year)
  • Batch size (kg/batch, units/lot)
  • Titre (kg/L)
  • Production time (days/lot)
  • Production schedule (24/7, 8/5)
  • Operation (by campaign, by lots)
  • Production opening (weeks/year)
  • Losses ()
  • Equipment utilisation ()

14
Conceptual design
  • Definition of the user requirements
  • Production capacity
  • Requirements (kg/year, units/year)
  • Batch size (kg/batch, units/lot)
  • Titre (kg/L)
  • Production time (days/lot)
  • Set-up, production process, cleaning,
    sterilisation, testing, product change-over.

15
Conceptual design
  • Definition of the user requirements
  • Production capacity
  • .
  • Equipment utilisation ()
  • Pilot plant  20-50
  • First commercial plant  70 max
  • Mature process  gt 80

16
Conceptual design
  • Definition of the user requirements
  • Product specification
  • Sterility
  • Water quality
  • Concentration
  • Impurity levels

17
Conceptual design
  • Definition of the user requirements
  • Development phase of the product

18
Conceptual design
  • Definition of the user requirements
  • Process
  • Production capacity
  • Product specification
  • Development phase of the product
  • Risks
  • Inability to manufacture the product
  • Inadequate plant capacity
  • Lower quality product
  • Inappropriate flexibility

19
Preliminary design
  • Facility definition and sizing
  • Preliminary specifications of the process
    equipment
  • Sizing of utilities
  • Sizing of spaces
  • Preliminary specifications of the automation
    system

20
Preliminary design
  • Facility definition and sizing
  • Preliminary specification of the process
    equipment
  • Volume, capacity
  • Material
  • Functionality
  • Process paramaters
  • Design and operation range (pressure,
    temperature, etc)

21
Preliminary design
  • Facility definition and sizing
  • Sizing of utilities and spaces

Process equipment
Spacesproduction, mechanical rooms, warehouse
Process supportCIP, solution prep
Building utilitiesHVAC, Steam, chilled water,
power
Process Utilitieswater, effluent treatment
22
Preliminary design
  • Facility definition and sizing
  • Preliminary specification of the automation
    system
  • Manual vs automated operation
  • Transfer panel vs manifold
  • Level of automation
  • Local controller, unit operation control,
    batching, archiving
  • General architecture

23
Preliminary design
  • Facility definition and sizing
  • Risks
  • Inadequate process equipment
  • Insufficient space and utilities
  • Inadequate control and automation
  • gt Production capacity cannot be met
  • gt Difficulties of operation

24
Detailed design
  • Detailed specification of all components of the
    installation
  • Mechanical components
  • Fabrication specification
  • Installation specification
  • Automation
  • Hardware
  • Software

25
Detailed design
PID
Sequences of operation
I/O List
Components List
Automation components specifications
Alarms InterlocksAccess rights
Mechanical components specification
Control panel drawings loop diagram wiring
diagram
Installation drawing (3D, isometrics)
Programming
26
Detailed design
  • Detailed specification of all components of the
    installation
  • Risks
  • Inappropriate installation
  • Cleaning and sterilisation issues
  • Corrosion issues
  • Operational difficulties
  • Maintenance difficulties
  • Accessibility issues

27
Construction and Fabrication
  • Construction follow-up
  • Documentation follow-up
  • Start-up and testing (FAT, SAT)

28
Construction and Fabrication
  • Construction follow-up
  • Ergonomy and accessibility
  • Slopes
  • Dead legs
  • Weld quality
  • Etc

29
Construction and Fabrication
  • Documentation follow-up

Update of design document (PID, specifications)
Data SheetsIsometricsTest Certificates
Turn-Over Package
Maintenance
Validation
30
Construction and Fabrication
  • Start-up and testing
  • Verification of the quality of fabrication
  • Verification of all design hypothesis
  • Control of process parameters
  • Process sequences are achievable
  • Equipment drainable, cleanable and sterilisable

31
Construction and Fabrication
  • Construction follow-up
  • Documentation follow-up
  • Start-up and testing (FAT, SAT)
  • Risks
  • Inadequate installation
  • Cleaning and contamination issues
  • Ergonomic and operational issues
  • Inadequate documentation
  • Validation issues
  • Maintenance issues

32
Validation
  • Adequate documentation facilitates protocol
    preparation and execution
  • Review of validation criterion can avoid
    unnecessary deviation
  • Participation in protocol execution facilitates
    and accelerates protocol execution

33
  • Questions ?
Write a Comment
User Comments (0)
About PowerShow.com