Title: Comprehensive Master Plan: Pre-Preliminary Draft Master Plan
1Comprehensive Master PlanPre-Preliminary Draft
Master Plan
Coastal Protection and Restoration
Authority November 8, 2006
Integrated Planning Team
2Agenda
- What has happened in the past two weeks to
compile the Pre-Preliminary Draft Master Plan? - What does this Pre-Preliminary Draft Master Plan
represent? - Show us the plan!!
- What are potential policy, legislative, or
institutional issues that would affect
implementation of the plan? - What comes next?
3What has happened in the past two weeks to
compile the Pre-Preliminary Draft Master Plan?
4Recent Meeting Schedule
- CPRA Meeting..October 19
- Science and Engineering
- Review Team and Agencies..October 24-25
5SERT and Agency Plan Formulation Meeting
- Federal Agencies
- USACE, USFWS, NRCS, EPA, NMFS
- State Agencies
- DNR, DOTD, DWF
- Stakeholders
- BTNEP, EJLD, LBLD, TLCD, Plaquemines Parish
- University and Other Scientists
- UNO, LSU, UM, SFWMD
6Recent Meeting Schedule
- CPRA Meeting..October 19
- Science and Engineering
- Review Team and Agencies..October 24-25
- Interdisciplinary
- Technical TeamOctober 31
7ITT Plan Refinement Workshop
- Federal Agencies
- USACE, USFWS, NRCS, EPA, NMFS, FHWA
- State Agencies
- DNR, DOTD, DEQ
- Stakeholders
- BTNEP, CRCL, LPBF, WTC-New Orleans, EJLD, LBLD,
TLCD, OLD, Jefferson Parish, Lafourche Parish,
St. Bernard Parish, St. Mary Parish, Vermilion
Parish, Plaquemines Parish - University and Other Scientists
- LSU Ag Center
8Recent Meeting Schedule
- CPRA Meeting..October 19
- Science and Engineering
- Review Team and Agencies..October 24-25
- Interdisciplinary
- Technical TeamOctober 31
- CPRA Master Plan
- Steering Committee.November 1
- CPRA Meeting..November 8
9What does this Pre-Preliminary Draft Master Plan
represent?
10What Are We Discussing Today?
- A detailed conceptual vision of the future of
coastal Louisiana - Completely integrated approach must be
implemented to meet objectives - Strives to balance objectives, although further
work is needed to refine strategies and better
balance objectives - Represents starting point for discussion with
CPRA - Open to revision
- Once revised, will be the starting point for
discussion with the public
11Background
- Stabilizing the landscape is paramount importance
for protection and restoration - Complete plan based on Multiple Lines of
Defense strategy - Hurricane protection strategies are defined based
on a stable landscape
12What Does Science and Engineering Say?
- Anything we do to fix the system will alter
hydrology and therefore alter the ecosystem - Cant fix the problem if you dont change the
system - Communities are adaptable
13Show us the plan!!
14Delta PlainStabilizing the Landscape
15Shorelines and Ridges
16Navigation Channels
17Land Sustaining Diversions
18Marsh Creation
19Land Building Diversions
20Special Focus MRGO
21Total Closure of the MRGO
navigation channelsand their associated levees
and spoil banks may offer opportunities to
integrate storm protection and coastal
restoration. These artificial features of the
coastal landscape might be modified to distribute
freshwater and sediment resources across the
landscape. -- Working Group for Post-Hurricane
Planning for the Louisiana Coast
22Delta PlainHurricane Protection
23What Does Science and Engineering Say?
- First line of defense should not be last line of
defense - Longer and more complex protection systems are
more prone to failure - Give water room to move
- Altered hydrology can be opportunities
24Pontchartrain Barrier (Pre)
25(No Transcript)
26(No Transcript)
27Pontchartrain Barrier (Post)
28Barataria Basin and West Bank
29Plaquemines Parish
30Terrebonne Parish and Atchafalaya Delta
31Delta Plain Protection
32Manage Remaining Risk
33Compartmentation
4
1
2
3
5
6
Old Monticello Levee
34Levees Failing- Levees Holding Orleans
Jefferson Parish Line
Digital Globe
35Water Management
36Chenier PlainStabilizing the Landscape
37Shoreline Stabilization
38Evacuation Routes
39Navigation Channels
40Marsh Creation
41Managing Water and Sediment
42Chenier PlainHurricane Protection
43Acadiana Area
44Western Chenier Plain
45What are potential policy, legislative, or
institutional issues that would affect
implementation of the plan?
46Policy, Institutional, and Legislative Issues
- Land Use Planning/Zoning
- Land Owner Concerns
- Adaptive Management
- Federal/State Partnership
- Consistency
- Priority
47What comes next?
48What Comes Next?
- Public Discussion
- Refine and define measures
- Develop cost estimates
- Develop implementation sequencing
- Modify plan based on analyses and inputs