decision analysis - PowerPoint PPT Presentation

1 / 41
About This Presentation
Title:

decision analysis

Description:

As machines age, they break down more frequently and maintenance costs tend to increase. ... Seasonal index for season 2 (Father's Day) = 1.236 ... – PowerPoint PPT presentation

Number of Views:29
Avg rating:3.0/5.0
Slides: 42
Provided by: johns577
Category:

less

Transcript and Presenter's Notes

Title: decision analysis


1
Lecture
4
MGMT 650 Network Models Shortest Path Project
Scheduling Forecasting
2
Shortest Path Problem
  • Belongs to class of problems typically known as
    network flow models
  • What is the best way to traverse a network to
    get from one point to another as cheaply as
    possible?
  • Network consists of nodes and arcs
  • For example, consider a transportation network
  • Nodes represent cities
  • Arcs represent travel distances between cities
  • Criterion to be minimized in the shortest path
    problem not limited to distance
  • Other criteria include time and cost

3
Example Shortest Route
  • Find the Shortest Route From Node 1 to All Other
    Nodes in the Network

5
2
5
6
4
3
2
7
7
3
3
1
1
5
2
6
6
4
8
4
Management Scientist Input
5
Example Solution Summary
  • Node Minimum Distance Shortest
    Route
  • 2 4
    1-2
  • 3 6
    1-4-3
  • 4 5
    1-4
  • 5 8
    1-4-3-5
  • 6 11
    1-4-3-5-6
  • 7 13
    1-4-3-5-6-7

6
Applications
  • Stand alone applications
  • Emergency vehicle routing
  • Urban traffic planning
  • Telecommunications
  • Sub-problems in more complex settings
  • Allocating inspection effort in a production line
  • Scheduling operations
  • Optimal equipment replacement policies
  • Personnel planning problem

7
Optimal Equipment Replacement Policy
  • The Erie County Medical Center allocates a
    portion of its budget to purchase newer and more
    advanced x-ray machines at the beginning of each
    year.
  • As machines age, they break down more frequently
    and maintenance costs tend to increase.
  • Furthermore salvage values decrease.
  • Determine the optimal replacement policy for ECMC
  • that minimizes the total cost of buying, selling
    and operating the machine over a planning horizon
    of 5 years,
  • such that at least one x-ray machine must be in
    service at all times.

Year Purchase Cost (000)
1 170
2 190
3 210
4 250
5 300
Age Maintenance cost (000) Salvage value (000)
1 50 20
2 97 15
3 182 10
4 380 0
8
Lecture
4
Project Scheduling Chapter 10
9
Project Management
  • How is it different?
  • Limited time frame
  • Narrow focus, specific objectives
  • Why is it used?
  • Special needs
  • Pressures for new or improves products or
    services
  • Definition of a project
  • Unique, one-time sequence of activities designed
    to accomplish a specific set of objectives in a
    limited time frame

10
Project Scheduling PERT/CPM
  • Project Scheduling with Known Activity Times
  • Project Scheduling with Uncertain Activity Times

11
PERT/CPM
  • PERT
  • Program Evaluation and Review Technique
  • CPM
  • Critical Path Method
  • PERT and CPM have been used to plan, schedule,
    and control a wide variety of projects
  • RD of new products and processes
  • Construction of buildings and highways
  • Maintenance of large and complex equipment
  • Design and installation of new systems

12
PERT/CPM
  • PERT/CPM is used to plan the scheduling of
    individual activities that make up a project.
  • Projects may have as many as several thousand
    activities.
  • A complicating factor in carrying out the
    activities is that some activities depend on the
    completion of other activities before they can be
    started.

13
PERT/CPM
  • Project managers rely on PERT/CPM to help them
    answer questions such as
  • What is the total time to complete the project?
  • What are the scheduled start and finish dates for
    each specific activity?
  • Which activities are critical?
  • must be completed exactly as scheduled to keep
    the project on schedule?
  • How long can non-critical activities be delayed
  • before they cause an increase in the project
    completion time?

14
Project Network
  • Project network
  • constructed to model the precedence of the
    activities.
  • Nodes represent activities
  • Arcs represent precedence relationships of the
    activities
  • Critical path for the network
  • a path consisting of activities with zero slack

15
Planning and Scheduling
16
Project Network An Example
6 weeks
3 weeks
8 weeks
11 weeks
1 week
9 weeks
4 weeks
17
Management Scientist Solution
18
Uncertain Activity Times
  • Three-time estimate approach
  • the time to complete an activity assumed to
    follow a Beta distribution
  • An activitys mean completion time is
  • t (a 4m b)/6
  • a the optimistic completion time estimate
  • b the pessimistic completion time estimate
  • m the most likely completion time estimate
  • An activitys completion time variance is
  • ?2 ((b-a)/6)2

19
Uncertain Activity Times
  • In the three-time estimate approach, the critical
    path is determined as if the mean times for the
    activities were fixed times.
  • The overall project completion time is assumed to
    have a normal distribution
  • with mean equal to the sum of the means along the
    critical path, and
  • variance equal to the sum of the variances along
    the critical path.

20

Example
Activity Immediate Predecessor Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b)
A -- 4 6 8
B -- 1 4.5 5
C A 3 3 3
D A 4 5 6
E A 0.5 1 1.5
F B,C 3 4 5
G B,C 1 1.5 5
H E,F 5 6 7
I E,F 2 5 8
J D,H 2.5 2.75 4.5
K G,I 3 5 7
21
Management Scientist Solution
22
Key Terminology
  • Network activities
  • ES early start
  • EF early finish
  • LS late start
  • LF late finish
  • Used to determine
  • Expected project duration
  • Slack time
  • Critical path

23
Example Two Machine Maintenance Project
Immediate Completion Activity
Description Predecessors
Time (wks) A Overhaul machine I
--- 7 B Adjust machine I
A 3 C Overhaul
machine II --- 6 D
Adjust machine II C 3 E
Test system B,D
2
Start
24
Normal Costs and Crash Costs
Activity Normal Time Normal Cost () Crash Time Crash Cost () Maximum Reduction in Time Crash Cost per day ()
A Overhaul Machine I 7 500 4 800 3 (800-500)/3 100
B Adjust machine I 3 200 2 350 1 150
C Overhaul Machine II 6 500 4 900 2 200
D Adjust machine II 3 200 1 500 2 150
E Test System 2 300 1 550 1 250
25
Linear Program for Minimum-Cost Crashing
Let Xi earliest finish time for activity i
Yi the amount of time activity i is crashed
10 variables, 12 constraints
Crash activity A by 2 days Crash activity D by 1
day Crash cost 200 150 350
Crash activity A by 1 day Crash activity E by 1
day Crash cost 100 250 350
26
Lecture
4
Forecasting Chapter 16
27
Forecasting - Topics
  • Quantitative Approaches to Forecasting
  • The Components of a Time Series
  • Measures of Forecast Accuracy
  • Using Smoothing Methods in Forecasting
  • Using Trend Projection in Forecasting

28
Time Series Forecasts
  • Trend - long-term movement in data
  • Seasonality - short-term regular variations in
    data
  • Cycle wavelike variations of more than one
    years duration
  • Irregular variations - caused by unusual
    circumstances

29
Forecast Variations
Irregularvariation
Trend
Cycles
90
89
88
Seasonal variations
30
Smoothing/Averaging Methods
  • Used in cases in which the time series is fairly
    stable and has no significant trend, seasonal, or
    cyclical effects
  • Purpose of averaging - to smooth out the
    irregular components of the time series.
  • Four common smoothing/averaging methods are
  • Moving averages
  • Weighted moving averages
  • Exponential smoothing

31
Example of Moving Average
  • Sales of gasoline for the past 12 weeks at your
    local Chevron (in 000 gallons). If the dealer
    uses a 3-period moving average to forecast sales,
    what is the forecast for Week 13?
  • Past Sales
  • Week Sales Week
    Sales
  • 1 17
    7 20
  • 2 21
    8 18
  • 3 19
    9 22
  • 4 23
    10 20
  • 5 18
    11 15
  • 6 16 12 22

32
Management Scientist Solutions

MA(3) for period 4 (172119)/3 19
Forecast error for period 3 Actual Forecast
23 19 4
33
MA(5) versus MA(3)
34
Exponential Smoothing
  • Premise - The most recent observations might have
    the highest predictive value.
  • Therefore, we should give more weight to the more
    recent time periods when forecasting.

Ft1 Ft ?(At - Ft), Formula 16.3
35
Linear Trend Equation
Suitable for time series data that exhibit a long
term linear trend
Ft
Ft a bt
a
  • Ft Forecast for period t
  • t Specified number of time periods
  • a Value of Ft at t 0
  • b Slope of the line

0 1 2 3 4 5 t
36
Linear Trend Example
Linear trend equation
F11 20.4 1.1(11) 32.5
Sale increases every time period _at_ 1.1 units
37
Actual vs Forecast
Linear Trend Example
35
30
25
20
Actual
Actual/Forecasted sales
15
Forecast
10
5
0
1
2
3
4
5
6
7
8
9
10
Week
F(t) 20.4 1.1t
38
Measure of Forecast Accuracy
  • MSE Mean Squared Error

39
Forecasting with Trends and Seasonal Components
An Example
  • Business at Terry's Tie Shop can be viewed as
    falling into three distinct seasons (1)
    Christmas (November-December) (2) Father's Day
    (late May - mid-June) and (3) all other times.
  • Average weekly sales () during each of the three
    seasons
  • during the past four years are known and given
    below.
  • Determine a forecast for the average weekly sales
    in year 5 for each of the three seasons.
  • Year
  • Season 1 2
    3 4
  • 1 1856 1995
    2241 2280
  • 2 2012 2168
    2306 2408
  • 3 985 1072
    1105 1120

40
Management Scientist Solutions

41
Interpretation of Seasonal Indices
  • Seasonal index for season 2 (Fathers Day)
    1.236
  • Means that the sale value of ties during season 2
    is 23.6 higher than the average sale value over
    the year
  • Seasonal index for season 3 (all other times)
    0.586
  • Means that the sale value of ties during season 3
    is 41.4 lower than the average sale value over
    the year
Write a Comment
User Comments (0)
About PowerShow.com