Title: Project Scheduling
1Project Scheduling
2Introduction
- A project is a collection of tasks that must be
completed in minimum time or at minimal cost. - It is made up by a set of tasks or activities,
some of which must be completed before others can
be started. - The ones that must be completed before a
particular activity can be started are called
predecessors. - Immediate predecessors are the ones that must be
done just prior to the commencement of a
particular activity. - A feasible scheduling is one that schedules the
activities without violating any of the immediate
predecessor scheduling constraints.
3Possible Objectives
- Some objectives of project scheduling include
- Completing the project as early as possible by
determining an earliest start and finish time for
each of the activities - Determining the likelihood a project will be
completed within a certain time period - Finding a minimum cost schedule that completes
the project by a certain date - Finding a minimum time to complete a project
within budget restrictions - Investigating the results of possible delays in
one or more of an activitys completion time - Evaluating the costs and benefits of reducing the
time of performing one or more of the activities
4Activities
- An activity could be
- Quite specific
- e.g. install light switch in third bathroom
- Less detailed
- e.g. install electrical for the house
- The degree of specificity used depends on the
application and availability of data. - Each activity has a set of immediate predecessor
activities that must be completed immediately
prior to starting the activity.
5Activity Completion Times
- Associated with each activity is an estimated
completion time. These time could be - Deterministic
- The completion time is known with certainty
- Probabilistic
- The completion time varies according to some
probability distribution with an estimated mean
and standard deviation - Determined by the amount spent to perform the
activity.
6Example
- KLONE COMPUTERS, INC.
- KLONE Computers manufactures computers.
- It is about to design, manufacture, and market
the Klonepalm 2000 palmbook computer. - In broad terms, the three major tasks to perform
are to - Design and manufacture the computer
- Train staff and vendor representatives on the
features and use of the computer - Advertise the computer
7Detailed Activities
Activity Description A Prototype model
design B Purchase of materials Manufacturing
C Manufacture of prototype model
activities D Revision of design E Initial
production run
F Staff training Training activities G Staff
input on prototype models H Sales training
I Pre-production advertising Advertising
activities campaign
J Post-redesign advertising campaign
8Precedence Relations
9The PERT/CPM Approach for Project Scheduling
- PERT stands for Program Evaluation and Review
Technique and CPM stands for critical path
method. - Both were methods for project scheduling
developed independently in the late 1950s. - The concepts have merged over the years so that
now we simply call the approach the PERT/CPM
approach. - It uses a network representation (a set of nodes
and a set of arcs) of the project. - Nodes represent the activities and reflect their
completion times - Arcs reflect immediate predecessor relationships
with arrows - PERT/CPM is used for scheduling activities such
that the projects completion time is minimized.
10The PERT/CPM Network
A 90
11OBJECTIVES
- Management at KLONE would like to schedule the
activities to minimize the project completion
time. - Management wishes to know
- The earliest start and finish times for each
activity that will allow the project to be
completed in this minimal time. - The latest start and finish times for each
activity which will not alter this minimal time. - Which activities must adhere to rigid schedules
and which activities have slack in their
schedules.
12 Earliest Start (ES) andEarliest Finish (EF)
Times
- The ES and EF times are determined by making a
forward pass through the network as follows - For all the activities which have no immediate
predecessors - The earliest start time (ES) 0
- The earliest finish time (EF) the activitys
duration - Then select a node for which EF of all its
immediate predecessors has been determined. - ES Max EF (of all its immediate predecessors)
- EF ES Activity Duration
- Repeat this process until all nodes have been
evaluated
Minimum Project Completion Time is The maximum EF
in the project.
13Earliest Start and Finish Times
- We enter these as (ES,EF) above each node.
170)
(149,
110)
(90,
(105,
105)
21
15
5
(149,
177)
90)
115)
(0,
(90,
(115,
129)
(129,
149)
28
90
25
14
20
194)
(149,
120)
(90,
45
30
Earliest Project completion time MAX(EF) 194
14 Latest Start (LS) andLatest Finish (LF) Times
- The LS and LF times are determined by making a
backward pass through the network as follows - For all the activities which are not predecessors
for any other activity - The latest finish time (LF) project completion
time - The latest start time (LS) LF Activity
Duration - Select a node which is the immediate predecessor
for nodes whose LS times have all been determined
- LF Min LS (all nodes for which it is a
predecessor) - LS LF - Activity Duration
- Repeat this process until all nodes have been
evaluated
15Latest Start and Finish Times
- We enter these as (LS,LF) below each node.
21
15
5
194)
(173,
110)
(95,
115)
(110,
28
90
20
25
14
194)
(166,
(115,
115)
(90,
129)
(0,
149)
(129,
90)
45
30
(149,
194)
149)
(119,
16Slack Times
- Activity start time and completion time may be
delayed by deliberate reasons as well as by
unforeseen reasons. - Some of these delays may affect the overall
completion date. - The effects of these delays can be determined by
the slack time, for each activity.
Slack time for an activity LS-ES or LF-EF
17The Critical Path
- The activities with 0 slack time form at least
one critical path of connected activities, each
of which is an immediate predecessor for another
activity on the path from the beginning (time
0) to the end (the completion time of the
project). - Critical activities must be rigidly scheduled.
- Any delay in a critical activity will delay the
entire project. - The critical path is the longest in the network
Sum of the completion times of activities on a
critical path Project completion time
18Slack Time Calculations
Critical Path A ?F ?G ?D ? J
19 The Critical Path
20Possible Delays
- There could be a delay in just one activity.
- Any delay more than the slack time for the
activity will delay the entire project by the
difference between the activity delay and the
slack time - There could be delays in more than one activity.
- If activities are on different paths or on the
same path but separated by a critical activity,
each of the delays is evaluated separately. The
project delay max (these delays corresponding
slack). - Activities on the same path which are not
separated by a critical activity share the slack.
Both will have the same value for the slack and
any combined delays in these activities that
exceed this common slack results in a project
delay equal to (total activity delay) (common
slack). - Usually with multiple delays the model is simply
re-solved!
21Examples of Activity Delays
- Activity G is delayed 5 days
- G is on the critical path (has 0 slack) so the
project will be delayed 5 days. - Activity E is delayed 15 days
- E has 24 days of slack so the project will not be
delayed - Activity B is delayed 15 days
- B has 5 days of slack so the project will be
delayed 10 days - Activity E is delayed 30 days and Activity I is
delayed 30 days - E and I are on different paths. E has 24 days of
slack which could cause a 30-24 6 day delay I
has 29 days of slack which could cause 30-29 1
day delay. The project is delayed by the
MAX(6,1) 6 days. - Activity B is delayed 4 days and Activity E is
delayed 4 days - B and E are on the same path but are separated by
critical activities (G and D). This is the same
as the case above. B has 5 days slack so
delaying it 4 days would not delay the project E
has 24 days of slack so a 4 day delay will not
delay the project Net effect No delay. - Activity B is delayed 4 days and Activity C is
delayed 4 days - B and C are on the same path with no critical
activity in between. They share the same 5 days
of slack. So sense both are delayed 4 days for a
total of 8 days, the project is delayed 8 5 3
days.
22A Linear Programming Approach to PERT/CPM
- Variables
- Xi The start time of the activities for iA,
B, C, ,J - X(FIN) Finish time of the project
- Objective function
- Complete the project in minimum time.
- Constraints
- For each arc a constraint
states that the start time of M must not occur
before the finish time of its immediate
predecessor, L.
23The Linear Program
Minimize X(FIN) ST
- X(FIN) ³ XE 21
- X(FIN) ³ XH 28
- X(FIN) ³ XJ 45
- XD ³ XG 14
- XE ³ XD 20 XG ³ XC 5
- XH ³ XD 20 XG ³ XF 25
- XJ ³ XD 20 XI ³ XD 90
- XJ ³ XI 30 XF ³ XA 90
- XC ³ XB 15
- XD ³ XG 14
- XB ³ XA 90
Example ofConstraints
Start Time for C Cs Duration
and
Start Time for F Fs Duration
All Xs ³ 0
24Using the PERT-CPM Template
25Using the PERT-CPM Template
26(No Transcript)
27(No Transcript)
28Review
- Objectives of Project Scheduling
- Precedence Relation Chart showing immediate
predecessors - How to construct a PERT/CPM network
- Forward Pass for finding the earliest
start/finish times (ES,EF) - Backwards Pass for finding the latest
start/finish times (LS,LF) - Calculation and analysis of slack
- Finding the critical path
- Linear programming formulation
- Use of PERT-CPM template