Title: Best Management Practices: Evaluating the Benefits
1Best Management PracticesEvaluating the Benefits
An Interactive Tool for Performing a
Comprehensive Site Assessment
Developed by Tetra Tech, Inc. for the Prince
Georges County Department of Environmental
Resources
2BMP Evaluation Method
Existing Flow Pollutant Loads
HSPF LAND SIMULATION
Unit-Area Output by Landuse
SITE-LEVEL LAND/BMP ROUTING
BMP Module
Simulated
Surface Runoff
BMP DESIGN
Simulated Flow/Water Quality Improvement
Cost/Benefit Assessment of LID design
Site Level Design
3BMP Module
- Input Data
- Surface runoff flow and pollutant loads from
contributing areas in site
- BMP Simulation
- User designs/selects each BMP and defines the
flow routing at the site - Flow and pollutant time series routed through the
BMP or IMP network - Physical processes are simulated in the BMP
- Output timeseries and data summary available at
each land, BMP, or watershed outlet
BMP Module
BMP DESIGN
Site Level Design
4BMP Physical Processes
- Possible storage processes include
- Evapotranspiration
- Infiltration
- Orifice outflow
- Weir-controlled overflow spillway
- Underdrain outflow
- Bottom slope influence
- Bottom roughness influence
- General loss or decay of pollutant
- (Due to settling, plant-uptake,
volatilization, etc) - Pollutant filtration through soil medium
(Underdrain outflow) - Depending on the design and type of the BMP, any
- combination of processes may occur during
- simulation
5BMP Class A Storage/Detention
Evapotranspiration
Outflow
Inflow
Modified Flow Water Quality
From Land Surface
OverflowSpillway
Storage
Bottom Orifice
Underdrain Outflow
Infiltration
6BMP Class B Open Channel
Outflow
Inflow
From Land Surface
Evapotranspiration
Overflow at Max Design Depth
Open Channel Flow
Modified Flow Water Quality
Underdrain Outflow
Infiltration
7BMP Class A Example
Bioretention
8BMP Class B Example
Grassed Swale
9BMP Underdrain System
Holtan Infiltration Method
Soil and subsurface flow configuration is
available for both Class A and Class B BMPs
10LID Modeling and Evaluation
- BENCHMARK (example)
- Representative pre-development condition is
runoff from a forested site of the same area
- LID ECONOMICS
-
- User can weigh costs of BMP implementation or
retrofit against long-run environmental benefits
and cost savings - RATIONALE
- The closer to pre-development conditions, the
more credits received - Optimum BMP Design Low cost high environmental
benefit
Simulated Flow/Water Quality Improvement
Cost/Benefit Assessment of LID design
11For More Information, please contact
- Dr. Leslie Shoemaker or John Riverson
- Tetra Tech, Inc.
- 10306 Eaton Place, Suite 340
- Fairfax, VA 22030
- (703) 385-6000