Title: Mark Krasberg
1String Commissioning 06/07
IceCube Collaboration Meeting Lake Geneva,
Wisconsin Mark Krasberg, April 25th, 2007
2Commissioning a DOMat The Testing DAQ Level
Question Test
Does the DOM pass communications? MOAT / QuadTool / DMT
Does the DOM function properly? STF
Does the DOMs Local Coincidence connections work? LCCHAIN.PY
Does the DOM calibrate its HV? DOMCAL
Does the DOM have reasonable rates? Multimon/TestDAQ
Does the DOM take data properly? TestDAQ
3Cold Temperature Comm Problem
- DOMHubs were crashing (100 times!)
- Initially slowed commissioning down
- Problem was related to DOM temperature
- old strings were much more likely to crash
- John Jacobsen quickly modified the dor-driver to
prevent hub-crashes - DOMs would also not reliably softboot, which
meant communications test programs would fail
4Cable Checks (cable guys)
- A total of four quads were determined to have
leaks (using Wet Connector Tester), went away
after freeze-in, as expected. - Two quads had DOMs which failed the Quad
Connectivity Tester. After freeze-in, one of
these DOMs was OK ! (string 66 quad 10). - DOM which does not power up is 74-09 Immunology
- This DOM was one of several which had a partially
broken penetrator connector
5Power-up Current Checks
- Quickly read out the DOR card configboot current
- Move DOMs which are drawing too much current to
sps-wczar DOMHub for study - DOR card current readings are recorded in order
to carefully track this issue
6No uncorrected ultra-high current tail in this
plot. Those DOR cards were pulled during testing
using SCUBE at SPTS prior to being shipped to
South Pole.
7S-CUBE 64 mainboards Used to test all DOMHubs
prior to shipment to Pole DOR card current
reporting could be calibrated
8SLIDE FROM MARCH 2006 !!High Current DOMs
- Six high current wire pairs identified at pole
- All anomolous DOMs kept unplugged
- Four of the high currents mysteriously went away
(seemingly not related to temperature or
freeze-in). - Two existing high current pairs plugged in at
station close (we should reconsider this).
9SLIDE FROM MARCH 2006 !! High Current DOM Pairs
- High current pairs which are still high current
pairs - 39-07 Hippophilia 8b56bf63b908
UP5P0888 0 3 - 39-08 Shamal 7b492c28a830
TP5P0527 0 3 - 40-51 Juneberry ce9692f580c9
UP4P0086 6 1 - 40-52 Alfa_Romeo_Spider 0a9dc8de00c3
TP5Y0171 6 1 - High current pairs which are no longer high
current pairs - 49-01 Ceres 754dad1d3800
UP4Y0030 0 0 - 49-02 Marzahn 60cad4124a82
TP5Y0161 0 0 - 50-37 Volkswagen_Beetle 93c6fcb0fe68
UP5Y0216 4 2 - 50-38 Warthog a095b31f89cf
TP4P0315 4 2 - 40-57 Tortellini d54044599535
UP4P0140 7 0
10High Current DOMs from 2006/2007
- There were 7 high current DOM pairs
- High Current DOM pairs are being treated with
care - Only being turned on very briefly every few days
to measure their configboot current - Pathology of high current DOMs looks quite a bit
different this year!
11string 58 67 66 74 73 65
72 78 48 57 47 46 56
High Current / LC breaks on the 13 new strings
High Current DOMs
Does not power up
LC break
12DOMs should freeze-in here
13Were there any high current DOMs found during
surface testing?
Arizona was a high current DOM during surface
testing. DOM name recognized on shelf in the TOS
during deployment! DOM pulled from hole. The
proudest moment in the history of the DOM names!
Arizona just arrived at PSL. Current draw
increases as voltage increases!
14Running DOMs in water
- We ran three strings and a handful of other DOMs
in water this season - Two DOMs behaved very badly!
- In 2005 / 2006, there was
- 38-59 Blackberry
1538-59 Blackberry failure
DOM stops triggering
Nasty temperature rise
HV never worked again, Otherwise DOM OK
Blackberry turned on in water here
1638-59 Blackberry failure zoom
DOM stops triggering
Nasty temperature rise
HV never worked again, Otherwise DOM OK
17Operating DOMs in water
- In 2006 / 2007 there were
-
- 78-49 The_Exorcist
-
- and
-
- 48-55 Captain_Spaulding
1878-49 The Exorcist
Rate spikes!
Nasty temperature rise!
Normal temperature rise
Unstable pressure readings!
19The_Exorcist and correlated spikes with nearby
DOMs
The_Exorcist
20The_Exorcist may have been sparking
The_Exorcist
21Water leaking into DOM?
- Allan Hallgren speculated water had leaked into
the DOM, resulting in sparks - Just before The_Exorcist was powered down, it
had become high current (96 mAmps instead of 80
mAmps) and it was not communicating properly! - The_Exorcist was moved to the sps-wczar debug
hub, pending freeze-in and retest.
2248-55 Captain_Spaulding
small bump
Other than rate increases, no other anomolous
readings detected for Captain_Spaulding
23Waveform/timing plot
There are lots of TestDAQ runs which were taken
while the sparking was going on
Light appears to originate at Captain_Spaulding
24Sparking DOMs
- 78-49 The_Exorcist, after freeze-in, behaved
normally. - 48-55 Captain_Spaulding, after freeze-in,
behaved normally. - Powering down these DOMs may have saved them from
destruction
25Two TestDAQ string processors
- Made it possible to perform different
commissioning tasks or take flasher runs for the
verification group in parallel. - Both string processors were used heavily (often
24 hours per day) - Increased satellite bandwidth meant that a large
fraction of the data could be transferred by
SPADE. - Around four thousand TestDAQ runs taken, half for
verification group.
26Could take calibrated TestDAQ data very quickly!
- String 48 example
- String tied off at 920pm NZT
- DOMs powered up by 1030pm NZT
- Calibrations and DB insertions made quickly
- String 48 was ready to take calibrated data by
midnight!
27Other Issues
- Two DSBs blew fuses during the season
- Kael asked LBNL to send more DSBs
- 6 spares arrived on the last flight (and 50 spare
fuses) - All spare DSBs used as of last night
- A few cabling mixups which were easily corrected
- We hooked up SPOTS again (the South Pole
Outdoor Test System) so we could do tests on DOMs
which were not deployed - Orphaned DOMs are being commissioned and moved to
the strings as appropriate (currently, sps-wczar
has twelve DOMs on it, of which six to ten should
eventually be able to be integrated into the
detector) - Many DOMs were found to not have their flash
completely loaded DOMAPP was missing! Problem
quickly dealt with in almost all cases.
28QUADTOOL results
74-10 Selaphobia (partner of Immunology) Sel
aphobia means fear of light flashes
29(No Transcript)
30(No Transcript)
31(No Transcript)
32(No Transcript)
33Data taken with 22 strings on Feb 11, Animation
made at pole with help of Phil Roth, Georges
Kohnen 49-57 Popcorn is flashing 378 DOMs
fire All 22 strings are hit!
34FLASHER BOARD 49-17 Popcorn
Standard Candle
352006/2007 InIce Commissioning
361,403 Commissioned DOMs
- There are 1,424 deployed DOMs
- 1,387 DOMs were commissioned by seasons end!
(now 1,403) - IceCube-9 596 of 604 DOMs commissioned
- Same as end of last year
- Zero failures as a result of DOMs being turned
off for several weeks! - Of the 596, two have broken LC and one has broken
HV - Other 8 two are on the debug hub sps-wczar
(Juneberry, Alfa_Romeo_Spider) - 13 new strings and new IceTop 807 of 820 DOMs
commissioned - Only one DOM, 74-09 Immunology, does not power
up - Twelve DOMs are on the debug hub, sps-wczar.
- Four pairs are high current, under study
- One pair has 56-58 Tengu which was still in
water yesterday (40 kHz noise rate!) - Last year, Fusilli didnt freeze-in until the
beginning of May - One pair communicates very badly
- Of the newly commissioned DOMs
- 58-45 Kokolik_River suffers from SHDR and
DOMCal cannot calibrate its HV - 1E7 gain tuned by eye
- One DOM requires a special DOR firmware setting
- 72-33 Mahischa, 72-35 Ant_Nebula and 72-43
Spirograph have broken LC (like Shamal and
Universitet from last year)
37Some of these DOMs are high current pairs
(partners could be fine)
38(No Transcript)
3976 DOMs
589 DOMs
1390 DOMs
39-22 Liljeholmen stops communicating properly
30-60 Rowan stops communicating properly
4076 DOMs
589 DOMs
1390 DOMs
39-22 Liljeholmen stops communicating properly
30-60 Rowan stops communicating properly
41(No Transcript)