Title: Collins Class Submarine Project: Successful or not
1Collins Class Submarine Project Successful or
not ??
- Cost 1000 over original estimate, 600 over
initial approved budget - Schedule 10 years late
- Performance on initial delivery None, or at
least, much less than required
2The Apollo Project
20 July 1969 Neil Armstrong set foot on the Moon.
May 25, 1961 SS(ID) to FOC Not more than 8
years, 7 months
July 24, 1969. The team safely returns
3Apollo Project Some Gee Whiz Numbers
- Prime contract let 4 months after Presidents
announcement - Project cost US 150 billion (2005 dollars) (3)
- 750 contractor
- Cdn govt contract actions CY 2004 47,690 (1)
- NASA (1965) 300,000 (2)
- Start to finish 98 months
1. Contracts Canada 2. Roger E. Bilstein, Stages
to Saturn A Technological History of the
Apollo/Saturn Launch Vehicles (Washington, DC
NASA SP-4206, 1980), passim, and Appendix E. 3.
NASA and BLS
4Apollo Project Successful or not ??
- Cost CY US150 billion
- Schedule Completed 5 months early
- Performance Met most difficult technical
requirements in history to that point
5DND News Release. Valcartier. Oct 12, 2004 New
vehicle replaces the Iltis fleet
LUVW Project began 10 Dec 1987 Actual schedule
17 years to deliver Chevy Eldorados 19 years
to deliver Mercedes G-wagens
6Observations on DND Project Performance
Measurement and Reporting
7Typical Project Performance Reporting
Level of performance
8Typical Project Performance Reporting
Level of performance
9Very often day-to-day PM management objectives
bear little or no immediate relevance to
Strategic (DND/Corporate) Objectives
10At the project staff level the time required to
perform an activity will always equal the time
available
NSA/MHP spent 26 years, from 1978 to 2004,
refining project documents
DND / PWGSC purchased challenger jets for PM in
72 hours (March 2002), or 3/10,000 the time for
MHP
- JSS will spend at least 9 years developing pre
contract award documents (1999-2008)
11At the project staff level the time required to
perform an activity will always equal the time
available
NSA/MHP spent 26 years, from 1978 to 2004,
refining project documents
Note that this is more than a year longer than it
took Apollo to land mankind on the moon
DND / PWGSC purchased challenger jets for PM in
72 hours (March 2002), or 3/10,000 the time for
MHP
- JSS will spend at least 9 years developing pre
contract award documents (1999-2008)
12The bigger the project the less likely anyone
will be held responsible for overall project
performance
- Very few project sponsors / managers / staff will
be with the project from start to finish - The lengthy schedule will always generate changes
to project scope / deliverables / technology /
expectations, e.g. new G-Wagens require more
armour protection than anyone foresaw when
project began in 1988.
13Project performance is a function of who is
measuring it
- CDS / sponsor Capability delivery
- ADM(Mat) Materiel acquisition
process effectiveness - PWGSC Contracting
effectiveness - Industry Canada Industrial, regional benefits
- Regional agencies Fair share of the pie
- T B Secretariat Accountability framework
- Cabinet and the Prime Minister Political impact
- Canadian industry Contracts, jobs, technology,
competitive advantage, profits - Project manager Those activities he/she is
responsible for
14Measuring Project Performance Hercules
Replacement
15Measuring Project Performance
- Within the project, performance should be
monitored at the lowest possible level, then
rolled up to higher levels - Identify sources and causes of variance
- Recognize that there are many measures of project
performance, and that they are often related to
competing organizational objectives
16Back to the Collins and Apollo
- Collins was a very successful project (at the
strategic level) - RAN will have the largest, and one of the most
effective, conventional subs in the world - Australia has a brand new modern submarine
building and support industry - Australia expects significant submarine exports
17Apollo
- Still considered one of the most successful
projects in history - The space shuttle and International Space
Station nearly the whole of the U.S. manned
space program for the past three decades were
mistakes, NASA chief Michael Griffin said. (27
Sep 2005)
18Mount Everest Project Classic Organization
19Mount Everest Project Classic Organization
Going rate Cdn 65,000 transportation
personal equipment
20 Mount Everest Project Goran Kropp
Organization
21Top Gun 2005 award for Canadas most successful
Green procurement, Performance based,
IRB-tempered, Low electromagnetic signature, Low
logistics footprint, Lowest cost compliant, Low
political risk, ultra strategic project went to
the General Officer Transportation System Project
22(No Transcript)