Modernization of I - PowerPoint PPT Presentation

1 / 33
About This Presentation
Title:

Modernization of I

Description:

Modernization of I – PowerPoint PPT presentation

Number of Views:68
Avg rating:3.0/5.0
Slides: 34
Provided by: entra
Category:

less

Transcript and Presenter's Notes

Title: Modernization of I


1
Modernization of IC Systems of NPPs
  • Experiences Lessons learned
  • KANUPP

Karachi Nuclear Power PlantPAKISTAN
2
Introduction
Owner Pakistan Atomic Energy Commission
Prime Contractor Canadian General Electric
Regulatory Authority Pakistan Nuclear
Regulatory Authority Reactor Type
CANDU (PHWR) Electrical Output 137 MW
Thermal Output 432.8 MW Fuel Natural
U Coolant D2O Moderator D2O Fuel Channels 208
KARACHI NUCLEAR POWER PLANT
3
Introduction
  • Location Paradise Point on the
  • Arabian Sea Coast, Karachi
  • Type of Reactor Single CANDU PHWR
  • Total gross capacity 137,000 kW
  • Civil construction 1965-1971
  • First Criticality August 1, 1971
  • Full Power achieved on October 4, 1972
  • Formally inaugurated on November 28, 1972
  • No radiological incident occurred during life
    time.
  • IAEA missions and WANO Peer Reviews did not find
    any significant deficiency resulting in
    compromise to plant safety

4
Modernization of KANUPP IC
  • AIMS OF MODERNIZATION OF ICModernization of
    KANUPP Computers, Control Instrumentation was
    aimed at providing long term solutions to address
    the aging, obsolescence of equipment and the life
    extension of the plant beyond its designed life

5
Modernization of KANUPP IC
  • Upgradation replacement has been done in the
    following areas
  • Pneumatic discrete electronics based
    instrumentation used for indication, recording
    control of process parameters e.g. pressure,
    level, flow, temperature.
  • Pneumatic discrete electronics based
    instrumentation used for safety related
    functions.
  • Digital computers used for reactor control,
    alarm, annunciation logging and other Control
    monitoring functions.

6
Modernization of KANUPP IC
  • Process Control Computers have now been replaced
    by new IC Systems based on Programmable Control
    Systems. Following distinct Plant Functions are
    now being performed by these systems
  • Reactor Power Regulation
  • Fuel Channel Temperature Monitoring
  • Bearing Temperature Monitoring of Pumps Motors
  • Failed Fuel Activity Monitoring
  • Alarms Annunciation

7
Modernization of KANUPP IC
  • CI LoopsThe selected IC loops of the plant
    have been successfully replaced
  • Measurement 54/238
  • Closed Control 37/49
  • Reactor Protection 49/49
  • Reactor Safeguard 15/15

8
Modernization of KANUPP IC
  • Planning and Pre-project phase
  • Scope of Backfitting
  • Feasibility studies
  • Joint engineering studies
  • Manpower development

9
Modernization of KANUPP IC
  • Project Implementation
  • Preparation of specifications
  • Bid preparation/ Evaluation
  • Contract Negotiation
  • Project Engineering
  • Procurement of equipment

10
Modernization of KANUPP IC
  • InstallationSince the plant had to operate, the
    installation work was carried out in phases.The
    installation of electronic rooms, UPS and cable
    trays were carried out during plant operation.
    Whereas the installation of field and control
    room equipment were carried out during shutdown
    periods. And switch over to new system achieved
    during two six months long shutdowns. Due to this
    the overall installation time was longer than it
    should be but on a running plant it was
    unavoidable.

11
Modernization of KANUPP IC
  • Pre-commissioningPrior to pre-commissioning
    tests Installation verification were done to
    check for proper installation as per design
    documents and remove any deficiencyFollowing
    pre-commissioning tests were performed by the
    dedicated group as per written approved
    procedures -Testing of valves positions as per
    fail safe criteria on Loss of Air and Power
    positions
  • -Loop checks from sensor to final control
    element -Testing of alarms and
    permissive -Signal communication to Process
    Monitoring -Testing of Application Programs

12
Modernization of KANUPP IC
  • CommissioningCommissioning of the new IC loops
    was planned in two stages
  • Partial commissioning For the loops whose
    process was not available, the loops were tested
    by simulated process signals and testing of all
    the functions were performed.
  • Final commissioning During start up of plant
    final commissioning of all the loops was
    performed including all the comprehensive and
    routine tests.

13
(No Transcript)
14
Measurement Loop Architecture
15
Reactor Protection Loop Architecture
16
Safeguard Loop Architecture
17
Redundant Control Loop Architecture
18
Normal-Help Control Loop Architecture
19
OLD AND NEW CONTROL STATION
20mA
DEV
PROCESS WATER PUMP DIFFERENTIAL
20

10
C.D.
0
100
HAND
AUTO
50

10
100
50
N2


D I F F
0
20
-
VALVE
4mA
80
40
-
T
U
1.5
GOSSEN
2
-
60
30
20mA
20mA

PSID
CV1
S.P.
50
40
20
100
40
80
TRANSFER
30
60
SP
M.V.
CV2
50
20
10
100
40
SET POINT
40
20
30
50
20
0
0
20
10
HAND
10
N3
N1
0
0
0
0
4mA
4mA
-
T
U
U
T
-
GOSSEN
1.5
1.5
GOSSEN
2
2
-
-
Bailey
PW6Q-CS
PW PUMP P
20
Modernization of KANUPP IC
A view of Installation in Electronic Room
21
Modernization of KANUPP IC
Distributed Control Systems
Installation and signal continuity verification
phase of Electronic and marshaling cubicles.
22
Modernization of KANUPP IC
Test / Calibration of Process CI
Maintainers Training for maintenance, testing
and calibration of new CI Devices before
installation.
23
Modernization of KANUPP IC
OLD CONSOLE WITHOUT VDU
NEW REACTOR POWER REGULATION CONSOLE
24
Modernization of KANUPP IC
KANUPP CONTROL ROOM PANEL ENGINEERING GIVE AN
EASE TO OPERATORS
OLD PANEL WITH PNEUMATIC CONTROLLERS
NEW PANEL WITH PLC CONTROLLERS
25
Modernization of KANUPP IC
OLD LINE PRINTERS
MAN-MACHINE INTERFACE OF NEW IC SYSTEMS
26
KANUPP CONTROL ROOM
27
NEW FEATURES AND ENHACEMENTS
  • Automatic fault detection for measurements and
    the processing hardware
  • Distributed Control System with full function
    backup controllers provides improved control of
    the process and increased reliability and
    availability
  • Valve position measurement provides indication of
    actual valve position in the field as well as
    automatic detection of valve position discrepancy
    if it arises which is annunciated for corrective
    action initiation well in time

28
NEW FEATURES AND ENHACEMENTS
  • PC based Man-Machine Interface providing ease of
    operation and effective navigation using
    Trackball, Mouse, Keyboard
  • Easy Access to Plant Parameters required for
    Plant Operation in different modes and effective
    handling of Transients
  • Data Recording and Display for Analysis of Plant
    Behavior
  • Alarms Management Functions for identification
    and diagnosis of Plant Transients

29
Operator Feed Back
  • The man-machine interface has been improved
    significantly and the operator now feel very easy
    to monitor and control the plant status
  • Annunciation for various faults has enabled the
    operator to take corrective action well in time
  • The performance of the plant has greatly improved
    after replacement of computers and ICs and the
    no. of trips has been reduced significantly

30
LESSONS LEARNED
  • Modernization of IC enhances the performance of
    the system and provide ease of maintenance as the
    vendor support and spares are available easily,
    so it be planned in a plant life as soon as the
    technology advancement makes it necessary.
    Although cost factors involve at first stage but
    pays in the long run after the modernization

31
LESSONS LEARNED
  • The modernization of IC also provides
    opportunity to enhance the previous design,
    enables to remove the short comings of previous
    design and provides an opportunity to improve the
    man machine interface as per operators feed back
    of the particular plant

32
LESSONS LEARNED
  • Modernization of IC provides the opportunities
    to train manpower for new technologies, modern
    equipment, advance tools and testing equipment,
    modern working methodologies

33
THANK YOU
Write a Comment
User Comments (0)
About PowerShow.com