Title: Modernization of I
1 Modernization of IC Systems of NPPs
- Experiences Lessons learned
- KANUPP
Karachi Nuclear Power PlantPAKISTAN
2Introduction
Owner Pakistan Atomic Energy Commission
Prime Contractor Canadian General Electric
Regulatory Authority Pakistan Nuclear
Regulatory Authority Reactor Type
CANDU (PHWR) Electrical Output 137 MW
Thermal Output 432.8 MW Fuel Natural
U Coolant D2O Moderator D2O Fuel Channels 208
KARACHI NUCLEAR POWER PLANT
3Introduction
- Location Paradise Point on the
- Arabian Sea Coast, Karachi
- Type of Reactor Single CANDU PHWR
- Total gross capacity 137,000 kW
- Civil construction 1965-1971
- First Criticality August 1, 1971
- Full Power achieved on October 4, 1972
- Formally inaugurated on November 28, 1972
- No radiological incident occurred during life
time. - IAEA missions and WANO Peer Reviews did not find
any significant deficiency resulting in
compromise to plant safety
4Modernization of KANUPP IC
- AIMS OF MODERNIZATION OF ICModernization of
KANUPP Computers, Control Instrumentation was
aimed at providing long term solutions to address
the aging, obsolescence of equipment and the life
extension of the plant beyond its designed life
5Modernization of KANUPP IC
- Upgradation replacement has been done in the
following areas - Pneumatic discrete electronics based
instrumentation used for indication, recording
control of process parameters e.g. pressure,
level, flow, temperature. - Pneumatic discrete electronics based
instrumentation used for safety related
functions. - Digital computers used for reactor control,
alarm, annunciation logging and other Control
monitoring functions.
6Modernization of KANUPP IC
- Process Control Computers have now been replaced
by new IC Systems based on Programmable Control
Systems. Following distinct Plant Functions are
now being performed by these systems - Reactor Power Regulation
- Fuel Channel Temperature Monitoring
- Bearing Temperature Monitoring of Pumps Motors
- Failed Fuel Activity Monitoring
- Alarms Annunciation
7Modernization of KANUPP IC
- CI LoopsThe selected IC loops of the plant
have been successfully replaced - Measurement 54/238
- Closed Control 37/49
- Reactor Protection 49/49
- Reactor Safeguard 15/15
8Modernization of KANUPP IC
- Planning and Pre-project phase
- Scope of Backfitting
- Feasibility studies
- Joint engineering studies
- Manpower development
9Modernization of KANUPP IC
- Project Implementation
- Preparation of specifications
- Bid preparation/ Evaluation
- Contract Negotiation
- Project Engineering
- Procurement of equipment
10Modernization of KANUPP IC
- InstallationSince the plant had to operate, the
installation work was carried out in phases.The
installation of electronic rooms, UPS and cable
trays were carried out during plant operation.
Whereas the installation of field and control
room equipment were carried out during shutdown
periods. And switch over to new system achieved
during two six months long shutdowns. Due to this
the overall installation time was longer than it
should be but on a running plant it was
unavoidable.
11Modernization of KANUPP IC
- Pre-commissioningPrior to pre-commissioning
tests Installation verification were done to
check for proper installation as per design
documents and remove any deficiencyFollowing
pre-commissioning tests were performed by the
dedicated group as per written approved
procedures -Testing of valves positions as per
fail safe criteria on Loss of Air and Power
positions - -Loop checks from sensor to final control
element -Testing of alarms and
permissive -Signal communication to Process
Monitoring -Testing of Application Programs
12Modernization of KANUPP IC
- CommissioningCommissioning of the new IC loops
was planned in two stages - Partial commissioning For the loops whose
process was not available, the loops were tested
by simulated process signals and testing of all
the functions were performed. - Final commissioning During start up of plant
final commissioning of all the loops was
performed including all the comprehensive and
routine tests.
13(No Transcript)
14Measurement Loop Architecture
15Reactor Protection Loop Architecture
16Safeguard Loop Architecture
17Redundant Control Loop Architecture
18Normal-Help Control Loop Architecture
19OLD AND NEW CONTROL STATION
20mA
DEV
PROCESS WATER PUMP DIFFERENTIAL
20
10
C.D.
0
100
HAND
AUTO
50
10
100
50
N2
D I F F
0
20
-
VALVE
4mA
80
40
-
T
U
1.5
GOSSEN
2
-
60
30
20mA
20mA
PSID
CV1
S.P.
50
40
20
100
40
80
TRANSFER
30
60
SP
M.V.
CV2
50
20
10
100
40
SET POINT
40
20
30
50
20
0
0
20
10
HAND
10
N3
N1
0
0
0
0
4mA
4mA
-
T
U
U
T
-
GOSSEN
1.5
1.5
GOSSEN
2
2
-
-
Bailey
PW6Q-CS
PW PUMP P
20Modernization of KANUPP IC
A view of Installation in Electronic Room
21Modernization of KANUPP IC
Distributed Control Systems
Installation and signal continuity verification
phase of Electronic and marshaling cubicles.
22Modernization of KANUPP IC
Test / Calibration of Process CI
Maintainers Training for maintenance, testing
and calibration of new CI Devices before
installation.
23Modernization of KANUPP IC
OLD CONSOLE WITHOUT VDU
NEW REACTOR POWER REGULATION CONSOLE
24Modernization of KANUPP IC
KANUPP CONTROL ROOM PANEL ENGINEERING GIVE AN
EASE TO OPERATORS
OLD PANEL WITH PNEUMATIC CONTROLLERS
NEW PANEL WITH PLC CONTROLLERS
25Modernization of KANUPP IC
OLD LINE PRINTERS
MAN-MACHINE INTERFACE OF NEW IC SYSTEMS
26KANUPP CONTROL ROOM
27NEW FEATURES AND ENHACEMENTS
- Automatic fault detection for measurements and
the processing hardware - Distributed Control System with full function
backup controllers provides improved control of
the process and increased reliability and
availability - Valve position measurement provides indication of
actual valve position in the field as well as
automatic detection of valve position discrepancy
if it arises which is annunciated for corrective
action initiation well in time
28NEW FEATURES AND ENHACEMENTS
- PC based Man-Machine Interface providing ease of
operation and effective navigation using
Trackball, Mouse, Keyboard - Easy Access to Plant Parameters required for
Plant Operation in different modes and effective
handling of Transients - Data Recording and Display for Analysis of Plant
Behavior - Alarms Management Functions for identification
and diagnosis of Plant Transients
29Operator Feed Back
- The man-machine interface has been improved
significantly and the operator now feel very easy
to monitor and control the plant status - Annunciation for various faults has enabled the
operator to take corrective action well in time - The performance of the plant has greatly improved
after replacement of computers and ICs and the
no. of trips has been reduced significantly
30LESSONS LEARNED
- Modernization of IC enhances the performance of
the system and provide ease of maintenance as the
vendor support and spares are available easily,
so it be planned in a plant life as soon as the
technology advancement makes it necessary.
Although cost factors involve at first stage but
pays in the long run after the modernization
31LESSONS LEARNED
- The modernization of IC also provides
opportunity to enhance the previous design,
enables to remove the short comings of previous
design and provides an opportunity to improve the
man machine interface as per operators feed back
of the particular plant
32LESSONS LEARNED
- Modernization of IC provides the opportunities
to train manpower for new technologies, modern
equipment, advance tools and testing equipment,
modern working methodologies
33THANK YOU