Wirebonding for TOB and TEC

Description:

1 main wirebond technician (Julie Stoner) 1 backup wirebond technician ... Shorts: 1 repaired short on a hybrid. Open channels: 13 on modules, 5 on hybrids ... – PowerPoint PPT presentation

Number of Views:36
Avg rating:3.0/5.0
Slides: 11
Provided by: affo
Category:
Tags: tec | tob | short | shorts | wirebonding

less

Transcript and Presenter's Notes

Title: Wirebonding for TOB and TEC


1
Wirebonding for TOB and TEC
  • Susanne Kyre
  • University of California, Santa Barbara

2
Wirebonding
  • Equipment and Personnel
  • Scale of the project
  • Bonding times
  • Bond quality
  • TEC
  • Outlook

3
Equipment and Personnel
  • Equipment
  • KS 8090 wirebonder
  • KS 8060 wirebonder (receive end of January)
  • Dage 3000 pulltester
  • Stereo microscope
  • Precision measuring microscope
  • Personnel
  • 1 main wirebond technician (Julie Stoner)
  • 1 backup wirebond technician (Andrea Allen)
  • In the process of hiring a second wirebond
    technician
  • 1 support technician (David Staszak)

4
Scale
  • UCSB will build 4000 Modules with about 10
    million wirebonds (that is 3 times the amount of
    wirebonds done in all of CDF All of UCSBs
    wirebonding for BaBar was 150,000 bonds, we will
    do that in a week)
  • Full production TEC and TOB
  • 15 Modules per day
  • 30 Hybrids per day

5
Bonding times
  • Starting point Bond centers had bonding times of
    up to 40 minutes with about 10 bonds that didnt
    stick and needed to be rebonded
  • Wirebond programs now bond an entire Module or
    Hybrid (previously had separate programs for each
    row of bonds), reduced bonding time by 50
  • Wirebond programs for all Module and Hybrid types
    now use pattern recognition (bonding time
    reduction by about 2-3 minutes)
  • Pure bonding time for a module lt 5min, for a
    hybrid lt 4min (CMS record)
  • Additional time (set up, database entry, pull
    testing)
  • 11min for a module, 8min for a hybrid
  • Total processing time can be reduce by using a
    support technician
  • Actual bonding times during mini production run
  • 2.5 hours for 10 modules (one technician)

6
Bond quality
  • CMS wirebonding spec pull strength gt 6g
  • Extensive pull testing was done to determine a
    set of standard bonding parameters for each
    bonding surface
  • Hybrids
  • We pull test 10 bonds on a test area on each PA
  • Average pull strength 10.0 g, std. Deviation
    0.6g

7
Bond quality
  • Modules
  • First 20 parts of each type, pull test every 50th
    bond
  • PA to Sensor bonds
  • Average pull strength 9.9g, std. Deviation 0.7g
  • Sensor to Sensor bonds
  • Average pull strength 8.2g, std. Deviation 0.8g

8
Bond quality
  • 79 Modules and 92 Hybrids bonded so far
  • Faults introduced during bonding
  • 1 pinhole (first TEC module) out of 84000 bonds
  • Shorts 1 repaired short on a hybrid
  • Open channels 13 on modules, 5 on hybrids
  • Bad channels introduced in bonding 0.034 for
    modules, 0.012 for hybrids (historically 0.5
    2)

9
TEC production
  • We will do TEC Ring 5 and 6 Module production
  • TEC Module and Hybrid wirebonding
  • All fixtures for Rings 5 and 6 are designed
  • TEC Ring 6 module carrier and wirebond fixture
    were built and tested
  • Wrote program and wirebonded 4 Ring 6 modules
  • Wrote program and wirebonded 6 Ring 6 hybrids

10
Future plans
  • Produce hybrid and module carriers and wirebond
    fixtures in machine shop
  • Write remaining wirebond programs for TEC Modules
    and Hybrids
  • Installation and set up of new 8060 Wirebonder
    (end January)
  • Training of new wirebond technician (mid
    February)
  • Training of wirebond technician from Mexico
  • Mini production run
  • 2 weeks at full production capacity of 15 Modules
    per day (start January 26)
  • Production bonding!