Title: Construction Site Erosion and Sediment Controls
1Construction Site Erosion and Sediment Controls
Section 4. Temporary Control Measures
2Temporary Control Measures
Temporary control measures are employed during
construction to control erosion and sediment
until permanent protection can be provided
3Erosion and Sediment Control
- Divert water so it does not flow across disturbed
areas - Establish temporary cover on disturbed areas
- Implement downslope controls to minimize the
quantity of sediment that leaves the site - Practice good housekeeping
4Temporary Control Measures
- Temporary control measures can be divided into
three general categories - Runoff control
- Erosion control
- Sediment control
5Temporary Control Measures
- Runoff control protects exposed soil by diverting
runoff away from exposed soil - Erosion control protects the soil and limits the
amount and rate of erosion on disturbed areas - Sediment control traps soil particles after they
have been detached and prevents them from leaving
the site
6Temporary Runoff Control
7Temporary Runoff Control
Temporary runoff controls are implemented to
prevent formation of rills and gullies of the
exposed soils onsite by controlling offsite
sheet-flow and concentrated flow
8Temporary Runoff Control BMPs
- Diversion ditches and berms
- Slope drains
- Ditch checks and other grade control measures
9Diversion Ditches
A diversion ditch is a temporary berm and channel
combination used to divert water flow
10Diversion ditches intercept runoff and direct it
to a desirable collection or discharge point
Seed and mulch is generally needed for ditches
with slopes less than 5
11Diversion ditches should be installed at the top
of slopes
Riprap can be used to stabilize ditches with
slopes greater than 8
12Diversion ditches can also be installed below
slopes to divert excess runoff to stabilized
outlets
Seed or erosion control matting can be used to
further stabilize ditches with slopes between 5
and 8
13Temporary Slope Drains
A slope drain is a device that conveys surface
water down a slope
14Slope Drains
15Slope Drains
Slope drains may be constructed of various
materials
16Slope Drains
Berms or dikes should direct less than 8 acres of
drainage to slope drains
17Slope Drains
Temporary pipe slope drains
18Slope Drains
Outlet to stone check dams to dissipate energy
19Ditch Checks
- Ditch checks are temporary barriers placed across
channels - Ditch checks are usually constructed of rock,
sandbags, gravel bags, or baled straw
20Rock Ditch Checks
21Rock Ditch Checks
Stone check dams work well to slow flow velocities
22Rock Ditch Checks
Rock has to meet requirements of Section 207
(stone backfill)
23Rock Ditch Checks
Space ditch checks so that the toe of the
upstream check is no higher than the top of the
downstream check
24Sand/Gravel Bag Ditch Checks
Place one line of bags on back (overflow area) of
ditch check to prevent undermining
25Sand/Gravel Bag Ditch Checks
Sandbag ditch checks are adequate for smaller
swales with lower flow rates
26Baled Straw Ditch Checks
Baled straw ditch checks shall only be used in
conjunction with sediment basins, diversion
ditches, other ditch checks, or other site
specific locations
27Baled Straw Ditch Checks
Baled straw ditch check used in a grassed lined
swale
28Baled Straw Ditch Checks
Baled straw ditch checks used in series
29Baled Straw Ditch Checks
Baled straw ditch check in series with a rock
ditch check
30Temporary Erosion Control
31Erosion Control
- Erosion control should be the first line of
defense against off-site impacts - Erosion control practices are generally more
effective and preferred over sediment control
practices - Objective is soil stabilization
32Stabilized Soil
- Stabilized soil is defined by the Specifications
(Section 110.06(d)) as being soil that is - Covered by grass
- Seeded and mulched
- Mulched
- Covered by erosion control matting
- Covered by permanent stabilization
33Temporary Erosion Control BMPs
- Surface roughening
- Ground cover
- Rolled erosion control products (RECP)
34Surface Roughening
- Surface roughening is a temporary erosion control
measure to protect disturbed areas and prepare
areas for seeding - Roughening creates depressions on the soil
surface by mechanical means stores rainwater,
slows runoff, and enhances seed germination
35Surface Roughening
- Roughening is performed parallel to slope
contours, or perpendicular to runoff direction - Surface roughening techniques include
- Sheepsfoot rolling
- Track walking
- Scarifying
- Stair stepping
- Imprinting
36Track Walking
Grooves formed during track walking shall be
perpendicular to the flow of water down the slope
37Track Walking
Track walking enhances germination
38Imprinting
An imprinter creates soil texture
39Ground Cover
- Ground cover is vegetation, mulch, or a
combination of both used to protect the soil from
the erosive force of water - Disturbed areas must be stabilized within 14
calendar days after activity ceases unless work
is to be performed within 21 calendar days after
activity ceases
40Temporary Vegetation
Applications must conform to Sections 620 and
621 of the Standard Specifications
41Temporary Seeding
- Rye and cereal grasses shall be planted at the
rate of 110 kg/ha between August 15 and January
20 - Brown Top Millet or Sudan Grass shall be planted
at the rate of 55 kg/ha between January 21 and
August 14 - Fertilizer shall be applied at the rate of 560
kg/ha of 10-20-10 or the equivalent amount of
plant food - The Engineer may adjust the above limitations
42Straw Mulch
Straw mulch is commonly used for temporary
erosion control
43Mulch
Mulch cover shall be applied at the rate of 4500
kg/ha (4000 lbs/ac)
44Mulch
Mulch shall be spread uniformly over the entire
disturbed area using approved blowing equipment
45Mulch
When approved by the engineer, the Contractor may
use hand methods to apply mulch to small or
inaccessible areas
46Mulch
Immediately following or during the application
of the mulch, the mulch shall be anchored by
crimping or tackifier
47Mulch
Crimpers have teeth that incorporate the straw
into the soil
48Mulch
The anchoring shall be performed so that the
grooves are perpendicular to the flow of water
down slopes
49Mulch
Tackifiers listed on the Departments Qualified
Products List (QPL) shall be applied at
appropriate rates
50Mulch
Mulch armors soil against raindrop impact and
sheet erosion
51Mulch
Mulch protects the soil surface from compaction
and increases infiltration
52Mulch
Mulch moderates the soil temperature and reduces
moisture loss from evaporation
53Mulch
Mulch reduces weed competition for desirable
plants
54Mulch
Mulch should be used in combination with other
BMPs
55Rolled Erosion Control Products
- Erosion control matting allows the establishment
of vegetative growth in an area of concentrated
water flow - Erosion control matting is commonly used on steep
slopes and in ditches, swales, or channels where
excessive velocities are expected - RECP materials shall be furnished according to
AHTD Class 1, Class 2, and Class 3 (all shall be
listed in the QPL)
56Rolled Erosion Control Products
The class of matting will be shown on the plans
and/or specs
57Rolled Erosion Control Products
The type of matting used within a particular
Class shall be at the option of the Contractor,
unless otherwise specified
58The matting shall be applied to the area after
the area has been shaped, fertilized, and seeded
as specified
59RECP Installation
The matting shall be installed according to the
manufacturers recommendations
60Questions? 10-Minute Break