Title: Risk assessment
1Risk assessment
2What is risk - 1
- Risks are characterized by three factors
- They are concerned with events that may or may
not happen in the future. - The events are identifiable but their effect and
probability are uncertain. - The outcome of the events can be influenced by
our actions
3What is risk - 2
- A risk is something that can be a problem in the
future. It is defined by two parameters - The probability - p. What is the probability that
the risk will become a problem? - The consequences - C. What will happen if the
risk becomes a problem? - The risk R is defined as R Cp
4How large is the risk - 1
- In order to find the size of a risk, we need
values for p and C. - In some cases we can estimate these values from
historical data but in most cases we will have to
use expert opinions or other subjective data
sources. - It is not always possible or meaningful to
assign a numerical value to a consequence, e.g.
loss of lives.
5How large is the risk - 2
- Even though assessment is a subjective activity
it is not about throwing out any number that you
like. - To be useful, an assessment must be
- Based on relevant experience.
- Anchored in real world data, e.g. How bad can it
get? - The result of a documented and agreed-upon
process. Having a process makes it possible to
later improve the process based on experiences.
6Assessing risk
- The quality of an assessment increases when the
background info gets more specific. - Dont ask What is the consequence of X? or
What is the probability of Y? - It is better to ask What is the consequence of
X in scenario S? or What is the probability of
Y in scenario S?
7Assessment and scenarios - 1
- If the probability of scenario Si is p(Si), and
pi and Ci are the probability and consequence of
an accident in scenario Si, we have that
- The method is critically dependent on the
- Quality of the scenario descriptions
- Independence of the scenarios
8Assessment and scenarios - 2
- We can improve our assessments even more if we do
not ask for consequences in general but for
consequences for one particular asset. Thus, in
scenario i we have consequence Cj,i for asset j.
9Assessing C and p
- We can assess consequences and probabilities in
several ways - Textual categories e.g. High, Medium, Low.
- Numerical categories e.g. values from 1 to 10.
- Value intervals.
- Statistical distributions.
-
10Textual categories 1
- When using categories, it is important to give a
short description as to what each category
implies. E.g. it is not enough to say High
consequences. We must relate it to something
already known, e.g. - Project size
- Company turn-over
- Company profit
11Textual categories 2
- Two simple examples
- Consequences we will use the category High if
the consequence will gravely endanger the
profitability of the project. - Probability we will use the category Low if
the event can occur but only in extreme cases.
12The CORAS consequence table
Consequence values Consequence values Consequence values Consequence values Consequence values Consequence values
Category Insignificant Minor Moderate Major Catastrophic
Measured related to income 0.0 0.1 0.1 1.0 1 5 5 10 10 100
Measured loss due to impact on business No impact on business. Minor delays Lost profits Reduce the resources of one or more departments Loss of a couple of customers Close down departments or business sectors Out of business
13The CORAS frequency table
Frequency values Frequency values Frequency values Frequency values Frequency values Frequency values
Category Rare Unlikely Possible Likely Almost certain
Number of Unwanted incidents per Year 1/100 1/100 1/50 1/50 - 1 1 - 12 gt 12
Number of Unwanted incidents per Demand 1/1000 (1/500) 1/50 (1/25) 1/1
Interpretation of number of demands Unwanted incident never Occurs Each thousand time the system is used Each five times the system is used Each tenth time the system is used Every second time the system is used
14Consequence and probability - 1
Consequence Consequence Consequence
Probability H M L
H H H M
M H M L
L M L L
15Consequence and probability - 2
- The multiplication table is used to rank risks.
It can not tell us how large they are. - We should only use resources on risk that are
above a certain, predefined level.
16Numerical categories -1
- We can use numbers instead of names. This does
not make the assessment more precise but will
free us from the need to define a multiplication
table in order to identify risks. - In principle we can use any numbers. The best
solution is, however, to just assign number to
the three aforementioned categories
17Numerical categories 2
- The following values are often used in practice,
both for consequences, benefits and
probabilities - 10 high
- 4 medium
- 1 low
- Thus, a medium consequence and a low probability
will give a risk of 41 4.
18Numerical categories 3
Consequence Consequence Consequence
Probability H / 10 M / 3 L / 1
H / 10 H / 100 H / 30 M / 10
M / 3 H / 30 M / 9 L / 3
L / 1 M / 10 L / 3 L / 1
19Value intervals
- If we have more info available we can give better
estimates. Even though we cannot give exact
values, we can give our assessments as intervals.
- An interval has a start and an end value
denoted a and b. We denote the interval I as I
a, b - In our case, the width of the interval is a
measure of our uncertainty.
20Simple interval arithmetic
- As long as all interval limits are positive, we
can write - I I1 I2, I a1a2, b1b2
- I I1 I2, I a1 a2, b1 b2
- I I1 - I2, I a1 - a2, b1 - b2
- I I1 / I2, I a1b2, b1/a2
- If we use intervals for consequence (C) and
probability (p) we get - R C1p1,C2p2
21Statistical distributions - 1
- We can use statistical distribution for C and p.
In this case, the distributions are used to show
our uncertainty. - Practical solutions could be
- Beta distribution for p
- Gamma distribution for C
22Statistical distributions - 2
- Based on the distributions of p and C, we can
compute the distribution of the risk in three
ways - Mellin transforms
- Monte Carlo simulation
- Approximation methods
- We will only look at the third alternative.
23Statistical distributions - 3
- The following approximation holds
24Risk approximation
- Using the expressions from the previous slide we
get the following approximations
It is now straight forward to find the expected
value and variance for R
25Simple risk assessment
- In order to a simple risk assessment we need to
identify - Dangerous events
- Each events
- consequence C
- probability p
- Possible barriers changes or controls
- Person responsible for each risk - Resp.
26Simple risk table
Event C p R Barriers Resp
27Events
- We start by identifying dangerous events. The
simple way to do this is to use brainstorming
just sit down and envisage your worst nightmares
related to the activities under consideration. - Be realistic only consider things that you
believe can happen.
28Barriers
- Barriers can be realized through
- Prevention we change the system so that the
event cannot occur. - Mitigation we can
- change the system in order to reduce the events
probability or consequences. - define activities that will reduce the problems
if the event occurs.
29(No Transcript)
30Benefits
- It is important to bear in mind that
- We usually expect to gain something through
change new products, new ways to work etc. - Risks stem from changes.
- Reducing risk is a cost factor
- We need to look at the total picture.
31The total picture - 1
- The total picture of the situation shows the
risks and the benefits that stem from a planned
change. - This is not a mechanism that can be used to
identify the best solution. - It is, however, an important input when we want
to make a decision.
32The total picture - 2
- The total picture shows risks and benefits. Risk
can be shown in two ways - Unmitigated risks
- Mitigated risks include the effect of risk
reduction activities, e.g. barriers. This can be
done by - Modifying the risk assessment
- Indicate how the risk will move in the diagram
33Consequences and benefits
B H Reduced number of MMI-related defects
B M
B L
p L M H
C L Extra work needed for MMI-specification
C M
C H
34Unmitigated risks
B H Reduced number of MMI-related defects
B M
B L
p L M H
C L Extra work needed for MMI-specification
C M
C H Large disagreements between designers and MMI experts Partnership does not work
35The mitigation effect
B H Reduced number of MMI-related defects
B M
B L
p L M H
C L Extra work needed for MMI-specification
C M
C H Large disagreements between designers and MMI experts Partnership does not work
36Including benefits
B H Reduced number of MMI-related defects Better MMI for existing products Better MMI requirements will reduce imp. costs
B M
B L
p L M H
C L Extra work needed for MMI-specification
C M
C H Large disagreements between designers and MMI experts Partnership does not work
37C and p as intervals - 1
38C and p as intervals - 2
39The tyranny of either or
- All too often we are confronted by the statement
that we can get only get X if we are willing to
suffer Y. - This is the wrong attitude. The right attitude is
that we will - Do what is needed to get X
- Perform activities that will remove or reduce the
bad effects of Y.
40Leverage
- Leverage is a prioritizing mechanism
- Leverage (Benefit Cost) / Cost
- Leverage will prioritize activities with
- Large net benefits
- Small costs
41Extended risk table -1
- We can use cause consequence chains or event
trees for a risk to identify the best place to
insert a barrier. - For each barrier, we need to assess
- Cost - the cost of implementing it. We will use
the scale H 10, M 3 and L 1. - E how effective is the barrier? We will use the
scale h 1.0, m 0.5 and l 0.2
42Extended risk table - 2
Event C p R Barrier Cost E L Resp.
43Barrier leverage
- Leverage (CpE Cost) / Cost
- The leverage will prioritize barriers which
- Have low costs Cost is small
- Have high efficiency E is large
- Attack important risks Cp is high
44Barrier example
Event Cons. p R Mitigation E Cost L Resp
Partnership does not work business conflicts 10 3 30 Do a thorough research on selected partners business goals 0.5 10 0.5 John
Customers do not prioritize project participation 10 3 30 State the conditions and consequences of customer participation in the contract 1.0 3 9.0 Pete
45Some comments on barriers
- It is important to remember that
- Each risk will usually need a different barrier
a barrier that works against one risk can be
valueless against another risk. - It is important to consider the three main
barrier strategies - Prevent the risk from becoming a problem
- Control the problem to avoid the consequences
- Reduce the consequences
46ALARP and GALE
- There are two competing principles in the
assessment of risk - ALARP As Low As Reasonably Possible- We have
done all that is reasonable to prevent problems
and dangers. - GALE Globally At Least Equivalent. E.g.
introducing a new process will not increase the
risks compared to what it is today.
47ALARP
- ALARP requires that we analyze each risk
separately and then implement mitigation
activities. - A reasonable goal is to reduce each risk until
the extra mitigation costs exceed the value of
the risk reduction achieved. - All that we have seen up till now fits into an
ALARP policy .
48GALE
- GALE requires us to look at the total risk of a
change. In this way we can start by attacking the
cheapest risk or the risk with the largest
leverage. - The problem with the GALE principle is that we
need to perform arithmetic on risks. E.g. we need
to decide how many medium risks we need before we
have a large risk
49ALARP vs. GALE
- The one important thing with using the GALE
principle is that it forces us to ask What is
the current risk level? - All too often we act as it the current way of
doing things is risk free and all risk stems from
changes. - This stance is enforced by the human tendency to
underestimate the risk of status quo.
50Using GALE
- Important points
- GALE is a method for risk analysis. Benefits must
be included elsewhere - We need to look at both our current risk and the
risk resulting from the proposed changes. - Always perform a sensitivity analyses.
51Risk status quo vs. change
- In many cases, maybe even in most of them, we do
risk assessment because we want to compare two or
more alternatives, e.g. - Status quo no changes
- One or more changes - improvements
-
52Event identification
- All significant dangerous events must have been
identified. - There must be a minimal overlap between the
dangerous events . - There must be a maximum of commonality between
the dangerous events considered for the status
quo and for the system after the proposed changes
53The three event sets
- The previous rules split the dangerous events
into three sets dangerous events that - Apply both to the status quo and to the new
system. - Are unique to the status quo
- Are unique to the new system
54GALE and risk assessment - 1
- GALE uses the following parameters for risk
assessment - FE the event frequency
- PE the probability that the event will lead to
an accident - S the severity score of an event
55GALE and risk assessment - 2
- We can compute individual and accumulated risk
indices - IE FE PE S
- IGR log Sumi(10I)
- IE is the risk index for a hazardous event
- IGR is the global risk index
56The GALE scoring scheme
- The scoring scheme of GALE
- Focuses on deviations from current average. This
is reasonable, given that it is mainly concerned
with comparing status quo to a new situation. - Must be tailored to each situation. The next
slide shows an example from road safety. We need
a scheme adapted to SPI.
57Road safety - frequency score for event
Frequency classification Occurrences / year on M42 ATM section Occurrences / year on M42 ATM section FE
Very frequent 10000 Hourly 6
Frequent 1000 A few times a day 5
Probable 100 Every few days 4
Occasional 10 Monthly 3
Remote 1 Annually 2
Improbable 0.1 Every 10 years 1
Incredible 0.01 Every 100 years 0
58Frequency score for event
Frequency classification Occurrences per project Occurrences per project FE
Very frequent 200 Every project 6
Frequent 100 Every few projects 5
Probable 40 Every 10th project 4
Occasional 10 Every 100th project 3
Remote 1 A few times in the companys lifetime 2
Improbable 0.2 One or two times during the companys lifetime 1
Incredible 0.01 Once in the companys lifetime 0
59Probability score for event
Classification Interpretation PE
Probable It is probable that this event, if it occurs, will cause a problem 3
Occasional The event, if it occurs, will occasionally cause a problem 2
Remote There is a remote chance that this event, if it occurs, will cause a problem 1
Improbable It is improbable that this event, if it occurs, will cause a problem 0
60Severity score for event
Severity classification Interpretation S
Severe The portion of occurring problems that have serious consequences is much larger than average 2
Average The portion of occurring problems that have serious consequences is similar to our average 1
Minor The portion of occurring problems that have serious consequences is much lower than average 0
61Sensitivity analysis
- The global risk index is made of many indices.
Each index will have a certain degree of
uncertainty connected to it. - Usually, a few indices will have a large
influence on the result while the rest will have
but little influence. - Paretos rule applies - we need to identify the
few important indices.
62Important things to remember - 1
- The most important things to remember
- Risk assessment is by its nature subjective.
- Use group techniques and include all stakeholders
- Use simple techniques so that you do not exclude
one or more stakeholders - Anchor it in experience and available data will,
however, improve the quality - Subjective values like High must be anchored in
each companys reality. One companys High may
be another companys Low.
63Important things to remember - 2
- Include the effect of choosing status quo in all
risk analyses. - Always include opportunities
- Consider the three barrier categories
prevention, handling and reduction - Rank risks and opportunities according to their
leverage - The results from a risk assessment is just one of
several inputs to a decision