Title: MWA Directors Report Alan Whitney


1
MWA Directors ReportAlan Whitney
  • MWA Project Meeting
  • Canberra
  • 19-23 January 2009

2
Topics
  • Progress
  • Challenges
  • Looking forward

3
Progress
  • Highly successful Nov 07 site visit
  • 32T tiles/beamformers and four recvrs deployed
    software correlator
  • 1.5TB of 26T data collected on several sources
  • Highly successful image making
  • Performance verified to be close to expectations
  • Sets the stage for full 32T demonstration over
    nextfew months
  • NSF review in Boston last week
  • Happy with the 26T results we presented
  • NSF understands budget shortfalls due to delays
    and technical problems
  • NSF remains committed to project, but is watching
    closely
  • Supplemental funding a possibility

4
More Progress
  • Good progress on hardware correlator
  • Project and budget are rapidly shaping up
  • Tight and effective management team
  • Interim Project Director (Alan Whitney, Haystack)
  • Interim Project Manager (Steven Tingay, Curtin)
  • Interim Project Scientist (Lincoln Greenhill,
    CfA)
  • Interim Project Engineer (Frank Briggs, ANU)
  • Commissioning Engineer (David Emrich, Curtin)
  • Deputy Project Managers
  • Roger Cappallo (U.S.)
  • Uday Shankar (India)
  • ST currently filling in (AU)

5
Near-term challenges
  • Successful AAL review to release NCRIS funds
  • Must meet prescribed criteria, including
  • Full project and budget plan for array completion
    mid Feb 09
  • Successful 32T operation w/ hardware correlator
    mid-09
  • First stage review to release 1st funding
    increment 2nd increment targeted for array
    completion in mid-2010
  • Still much work to do
  • Quite optimistic
  • Facing challenge to stretch funds to full 512T
  • Must find permanent PM
  • Steven has agreed to stay until Jun 09
  • Actively interviewing candidates
  • To be based in Perth

6
More near-term challenges
  • Settle disposition of several workpackages
  • Receiver
  • Clock distribution system
  • RTC selection
  • Communications
  • Geographic and institutional dispersion presents
    many challenges
  • Good project management communications, but still
    wider project challenges
  • Suggestions welcome
  • New website coming alongsee preview at
    www.mwatelescope.org

7
(No Transcript)
8
Looking forward
  • Technical elements are now coming firmly
    together,but still a few rough spots to overcome
  • Hope to report on full 32T success plus
    substantial new contributions to MWA coffers at
    Seattle meeting in June!
  • We are on-track to complete the array in mid-2010!
  • Community interest remains very high

Projection optimistic!
9
Thanks to everyone for their hard work, teamwork
and dedication!