Title: TOAST Transient Object Automated Search Telescope
1TOASTTransient Object Automated Search Telescope
- Timothy Young
- Tricia Johnson
- Chris Milford
- Rob Czapiewski
- Department of Physics
- Michael Sprengeler
- Concordia
Lohit Gaddampolly Department of Computer Science
Michael Gerszewski Ryan Kramer Space Studies
2Funding
- Faculty Start-up
- NASA (match Provost, Physics and Space Studies)
- AAS (American Astronomical Society)
- Dakota Science Center
- Physics
- Space Studies
3Briefly what TOAST is
- 10 MEADE telescope
- Dome Robo-dome
- Camera CCD ST-7e Santa Barbara Instrumentation
Group - Filter Wheel BVRI, clear
- Software TheSky, CCDsoft, DDW, Orchestrate,
Lohit-Young software.
4Timeline
- November 2000 Toast originally was two
telescopes combined in a roll-off roof. The
proposal was rejected. - April 2001 - CCD Camera and filter wheel
purchased. - Summer 2001 - REU 8 Meade telescope on top of
Witmer. Michael Sprengeler. - Software control telescope, camera, and new
software to automate the system.
5ST-7e 765 x 510 pixels 390,000 6.9 x 4.6 mm
6Software
Provides connection to telescope
Provides connection to camera
Coordinates actions of CCDSoft and TheSky
7Up on the roof at Witmer
8Timeline
- August 2001 first test of automation mode.
- 60 asteroids were observed in a single night.
- Some in multiple filters.
- Second test (next night) focuser went out.
- Ended the testing
9Timeline
- Summer 2001 contracted concrete foundation and
concrete pier. - Design the metal pier.
- No money for power and ethernet cables, which had
to wait until spring.
10(No Transcript)
11Timeline
- September 2001- Redesign base. Trips to Witmer
basement. Designing a mount without seeing the
wedge that sits on it. - October 2001 Dome arrives. Where to put it? PSO
was not ready, so Graeme Dewars Lab.
12ROBO-DOME from Technical Innovations, Inc.
- Dome automation with be through Digital Domeworks
- Specifications
- Works in cold climates (Fairbanks, Alaska)
- Slaves to telescope, fits up to 10 Meade
- About 4 ½ Feet in Height
- About the same in Diameter
-
-
13(No Transcript)
14(No Transcript)
15Timeline
- January 2002, Money for the cables, but had the
work order in since Dec. - In April I call, never got it.
- In May they say they are booked until October.
- I call and say we need it immediately, we get a
break and it is completed over the summer.
16(No Transcript)
17Timeline
- Nov 2001 present Dome testing.
- Dome computer board was sent back twice.
- Relay problem
- Software incompatibility
- Dome Azimuth gear wore out.
- Dome 2 modes of operation, not working.
- Company changed ownership. UND had gotten the
last Robo-dome from the original owner.
18Timeline
- February 2002 present Computer
- 1.8 GHz Pentium IV
- (2) 60 GB HD
- 256 SDRAM
- Projected image down load 500KB 60 images 5
filters. Fill both drives in 3 months.
19Connections Camera Parallel port Telescope
serial port Dome serial port Webcam
USB Ethernet card Problem needed to turn off
some appliances. Firecracker remote power
switches But needed serial ports.
20(No Transcript)
21Timeline
- February 2002 - Automation Needed a program to
run the other programs and organize an observing
run. - Lohit is hired to write software. It access an
object database of 88,000 and organizes an
observing run based on time rises, sets, limiting
magnitude. Then places the data into an
appropriate folder at the initiation of the
observing run. Lowel Obs.
22Timeline
- March 2002 - We install all programs.
- We install VNC
- We get Hacked and virus
- We load a firewall
23Telescope
- Meade LX200 10 telescope f/6.3
- Limiting magnitude 16.5 - 17.0
- SBIG ST-7E CCD
- FOV size (10X15)
- CFW-8 filter wheel
- Johnson BVRI
24Timeline
- June 2002 AAS - 10 GPS scope arrives
- July 2002 Sent back to Meade.
- August 2002 Doesnt work with Dome software.
Board for dome gets sent back - .During scope test condensation needed to be
removed. Dew Zapper.
25(No Transcript)
26(No Transcript)
27(No Transcript)
28(No Transcript)
29(No Transcript)
30(No Transcript)
31(No Transcript)
32(No Transcript)
33Timeline
- November 2002Finally everything is at the
observatory. Barely fits. - Computer needs keyboard. But also monitor?
- As we change out equipment and do checks we take
off the dome. The synthetic fiber track falls
off. The top dome part comes back to Witmer and
re-glued.
34On cold winter nights in the observatory trailer
this is what happens
- No insulation
- A small heater never heats up
- No bathroom
- No water
- Equivalent to a research station in Antarctica
You turn into an elf
35Motivation
- Why do this?
- There are other, bigger telescopes that do this.
- But there is nothing like having your own.
36TOAST First Light Image(remote) Thursday February
27, 2003
37Purpose
- Originally to automatically obtain follow-up
observations on Minor Planets - Now Search for other transients Supernovae,
Novae, Comets, and gamma-ray bursts.
38Goals Procedure 1) Obtain asteroid information
from MPC 2) Observe critical/follow-up asteroids
3) Astrometry and Mag. (also bands) 4) Send
data back to MPC Research telescope transient
objects Faculty and students
39Galatea-74
40SN 1999em
41Gamma-ray Bursts
42Student Involvement -digital image
analysis -computer programming -astronomy -problem
solving
43Sequence of events
- During the day TOAST calculates an observing
schedule - Comes online 1 hour after sunset.
- Lohit-Young program sent to Orchestrate
- Downloads to local computer
- 1 hour before sunset the system shuts off.
- Morning student identifies transient objects.
44Discovery Algorithms
- Automation to be determined
- How to put in a repeat observations
- How to analyze the data in real time.
- Send out email for new object.
45Closing remarks
- Reactions to TOAST
- Michael Meyer Steward Observatory UofA
- We dont even do that at Kitt Peak, its too
hard - Alex Filippenko UC-Berkeley
- That is really neat, I need pictures of this
- Dr. Granzio UofChicago
- There are not many of these around, you need to
get on the HETE first alert system