Title: Infrastructure and Test Facilities in the U'S'
1- Infrastructure and Test Facilities in the U.S.
Robert Kephart Fermilab
2Work packages in this talk support
- ILCTA test facilities _at_ FNAL
- Vertical and Horizontal test of Cavities
- Determine the maximum operating gradient of each
cavity - Evaluate gradient spread, Q0 and their
operational implications. - Measure dark currents, cryogenic loads, and
radiation levels. - Test of Cryomodules
- Measure gradient of cavities in cryomodules
- Measure vibration of components, system trip
rates recovery times - Beam Based Measurements
- Beam energy, stability, energy spread
- Wakefield measurements, HOM based alignment
LLRF issues - Goal Are the cryomodules good enough for the
ILC ? - RF Activities _at_ SLAC FNAL
- Develop high power RF components for Main Linac
- Development of LLRF and multi-cavity control
systems - RF systems in support of ILCTA _at_ FNAL
3ILCTA ILC RF unit at Fermilab
09
08
07
Plan is to build one RF unit to be tested with
Beam by 2009.
06
07-08
4Work Packages for this talk
- 5.8
- 5.8.1 1.3 GHz RF Power Source SLAC
Adolphsen - 5.8.2 ILCTA support
SLAC Cassel - 5.8.2.1 HA Modulator IGBT Switch array
- 5.8.2.2 ILCTA Cryo design
- 5.8.3 RF Power
FNAL Nagaitsev - 5.8.4 LLRF Controls
FNAL Carcagno - 5.9
- 5.9.1 Cavity Horizontal Test Stand
FNAL Hocker - 5.9.2 Cavity Vertical Test Stand
FNAL Ginsburg - 5.9.3 Cryogenics for test stands
FNAL Theilacker
51.3 GHz RF Power Source
- Description (WBS 5.8.1) SLAC
- Build a 1.3 GHz RF 5 MW power source to test ILC
RF components - HV modulator that is on loan from SNS, 1.5 ms
pulses at 5 Hz - A 5 MW klystron
- High power RF distribution system (3 ATM N2 Gas)
- Epics based LLRF system
- Goal
- Process developmental couplers
- and perhaps process production couplers for FNAL
- Test normal conducting positron capture cavity at
NLCTA, including accelerating beam with them. - Longer Range Goal
- In the next few years, build and test ILC
prototype klystrons and modulators, and by FY10,
have six industry-built ILC prototype rf sources
(modulator, klystron and controls) in operation
(one unit to be used at FNAL to drive three
cryomodules).
6Status Plans
- Status
- Drove a Thales 2104U klystron with the SNS
modulator - 120 kV, 80 A, 5 Hz with 1 msec pulses
- In an initial rf test, produced 3 MW, 0.7 msec rf
pulses at 5Hz - Will receive a Thales 2104C tube in a few weeks
for 5 MW operation - Received parts from LANL to upgrade SNS modulator
to drive the TH2104C and ILC prototype 10 MW
klystrons - Plans
- Complete system checkout with the Thales 2104U
klystron - Upgrade SNS modulator (test at 95 A and 130 A
with a resistor load) - Install the TH2104C klystron, complete waveguide
runs to test areas, and process system with high
power RF - On track to finish 1.3 GHz Source in FY06
71.3 GHz Source _at_ SLAC
SNS Modulator
Current RF source with isolator and load
Thales 2104U Klystron
8Modulator IGBT Switch
- Description (WBS 5.8.2) SLAC
- Design, build, test and deliver two solid state
switches for the Bouncer modulator operating at
10 kV and 1800A peak. - Project is SLAC contribution to ILCTA program.
- Motivation
- Improve reliability through solid state n/N
redundant switch structure and redundant serial
switches to protect klystron in case of switch
failure.
Scope
WBS 5.8.1 WBS 5.8.2
Note that actual cost of IGBT is more like
172 K see next slide
95.8.2.1 Progress FY06
- Status
- Design 100 complete fabrication and testing 75
complete. - Awaiting delayed IGBTs delivery from vendor
- Delivery 1 month after all parts received.
- Budgets
- SLAC funded one switch (75K) in FY05
- Later design requirements changed to two switches
for redundancy, increasing engineering,
fabrication cost estimate to 172K. - Project on track to complete within re-estimate.
10IGBT Switch Array
First Assembled Unit
Design Complete
IGBTs
Gate Drive Board
IGBT Stack
6 Plastic Stand-Off
Diode Stack
Aluminum Plate
11RF Power (WBS 5.8.3)
- WBS 5.8.3 RF For ILCTA _at_ FNAL
- Purpose RF Power (Modulator, Klystron,
distribution system) for Horizontal Vertical
Test Stand and ILC cryomodule. - Small RF System 1 for HTS/Capture Cavity II
- Klystron Phillips YK1240 ( 300 KW)
- Modulator 600 KW
- LLRF Simcon 2.1 ( More on this later)
- Status
- System installed and operational in MDB
- RF has been applied to Capture cavity II
- System will move to HTS when this is ready
12MDB Small RF System 1
Charging supply and Series Tube Modulator
Klystron 300 KW
RF Controls
13RF Power (WBS 5.8.3)
- Large 10 MW Modulators (2 being built, ILC PD)
- Klystrons 1.3 GHz Thales, CPI, or Toshiba
- Modulator FNAL Bouncer type
- Status
- Both modulators are being assembled
- 112 HV Pulse transformers have arrived
- Plans
- PD modulator in FY06 in MDB (325 MHz klystron)
- On track to install 1st large ILC modulator in
ILCTA_NM (New Muon lab) in FY07 - Modulator will be used to supply RF power for the
test of the first U.S. built cryomodule (TTF
type III)
14Large Modulator
112 HV Pulse transformer For PD 4.5 mS
Capacitor Frame
Capacitor Frame, Main Capacitors and Bouncer
Capacitors On site Bouncer Choke, High
Voltage Stripline, and Bus
On Site High Voltage Resistors and Undershoot /
Snubber Capacitors On site Cabinets and First
IGBT Switch from SLAC scheduled to arrive April
15Scope and Schedule
- FY06
- Scope
- Status Schedule
- Small RF system for HTS/Cap Cav II done
- Big Modulators PD in May 06, ILC in FY07
- VTS RF system (small CW) in late FY06
16Low Level RF (WBS 5.8.4)
- Purpose
- Develop LLRF for ILCTA test areas, work towards
ILC LLRF system - Stand alone RF systems for ILCTA VTS, HTS, New
Muon - LLRF Capture Cavity II/HTS
- FPGA based Simcon 2.1 LLRF system from DESY
- Master Oscillator 8 channel timer designed at
FNAL - Status
- System installed and operational in MDB
- RF has been applied to Capture cavity II
- System will move to HTS when this is ready
- Plans
- Develop multi-cavity control system for New Muon
FNPL cryomodule - Evaluating Simcon 3.1 boards from DESY
alternatives
17Stand-alone LLRF System
- VME Modules
- Sparc CPU-56 running DOOCS and Matlab
- 8-Ch Timer Module (FNAL design)
- 8-Ch, 10 MHz fast digitizer (DESY design)
- 8-Ch Function Generator board (DESY design)
- Simcon 2.1 FPGA board (DESY design commercial
FPGA board)
The CC2 LLRF Portable Rack was commissioned at A0
and is ready to support CC2 operations
Drive Vector Modulator and Downconverter Vector
Modulator/Mixer (New FNAL design, upgradeable to
3.9 GHz operation)
18New DESY Simcon 3.1 Board
3 prototypes received from DESY Jan 06. This can
control 8 Cavities from one Klystrons.
Fermilab (AD, TD, CD) in collaboration with DESY
and Poland are working on developing and
debugging this new board. Expanding the
collaboration on LLRF to include UPenn, SLAC and
INFN.
19Scope and Schedule
- FY06
- Scope
- Status Schedule
- LLRF system for HTS/Cap Cav II done
- LLRF for VTS FY07
- LLRF system for New Muon FY07
20Vertical Test Stand (WBS 5.9.2)
- Our goal is to rapidly advance the intellectual
understanding of SCRF surface physics and
establish process controls to reliably achieve
high gradient ( 35 MV/M) SCRF cavity operation - Approach Establish a tight loop processing and
test infrastructure in the U.S. - Tight loop elements
- Cavity fabrication improvements ( e.g. single
crystal) - BCP Electro-polish facilities
- High purity water and High pressure rinse
- Vertical test facilities
- SCRF experts materials program to interpret
results - Vertical test facilities exist at Cornell and
TJNL (bare cavities) - These are being modified for near-term use by ILC
RD - On a longer term ( 2007) new Vertical Test Stand
(designed for 35 MV/M) cavity testing is being
built at FNAL
21ILCTA_VTS
- A Vertical Test Stand VTS is sited in IB1 because
this building currently houses the Magnet Test
Facility ? large refrigerator capable of 60 W at
1.8 K - Bare 1.3 GHz 9-cell Tesla-style cavities
- Measure Q vs. T and Q vs. Eacc
- 250 W (CW) RF power required at maximum gradient
(Q5x109, Eacc35 MV/m) - Installed in a vertical pit in the Floor
- Shielding against X-rays and Neutrons is an
important issue for 35 MV/M cavities - Maintain Controlled Area status in IB1
- lt5 mrem/hr immediately outside shielding
- lt0.25 mrem/hr in normal working areas
LHe vacuum lines
Industrial Building 1
Cornell
22VTS Status Plans
- Cryostat Design
- Added phase separator to DESY design to improve
He Quality - Estimated RF duty factor possible based on IB1
cryogenic capacity - Started cryogenics controls modifications
- Cryostat design in progress
- Radiation Shielding
- Estimated x-ray flux from DESY data
- Finalizing shielding design prerequiste for
finalized civil construction design - Secure OK from Safety, then proceed with Civil
work 2 months - RF instrumentation
- Instrumentation design has begun
- Rack layout, etc
- Input coupler design will start soon
VTS Civil Design
One or two 9 cell cavities
23VTS Scope Schedule
FY06 Scope
Schedule
- Some costs will spill over to FY07. On track to
have a Vertical Test System to test high gradient
cavities at Fermilab in 2007
24Horizontal Test Facility
- Purpose Verify dressed cavity performance (Eacc
vs. Q0) to qualify cavities for assembly into a
cryomodule - Bare cavities that pass vertical test are
dressed with LHe cryostat, coupler, tuner
then tested with RF pulsed power - Usually referred to as Horizontal Test since
this test is performed in this orientation at
DESY in the Chechia facility - Horizontal Test Systems (HTS) are under design
for ILCTA_MDB (Meson Detector Building) and
ILCTA_IB1 (Industrial Bldg 1)
Bare 1.3 Ghz 9 cell Cavity
Horizontal Test_at_DESY
4 cavities received from ACCEL 4 cavities on
order at AES 2 cavities on order at TJNL 4
cavities expected from KEK
Dressed Cavity
25HTS (WBS 5.9.1)
- ILCTA_MDB HTS
- Cryostat
- Accepts single dressed cavities, 1.3 GHz or
3.9 GHz - Similar to the DESY HTS but has access at both
ends. - Cryogenics
- MDB has an existing 1800 W _at_ 4 K cryogenic system
- New distribution system built to supply cavity
test areas - Large vacuum pump has been added to achieve 60 W
at 1.8 K - Cryogenic costs for this are in WBS 5.9.3
- RF System
- 300 KW klystron modulator provides pulsed RF
power - Costs associated with RF system are in 5.8.3
- ILCTA_IB1 HTS
- A second HTS will be built for IB1
- Improved throughput (HTS is bottleneck _at_ DESY)
- Design improvements
- Accepts two 1.3GHz cavities simultaneously.
26HTS Status Plans
- ILCTA_MDB
- Phase I Qualify six 3.9 GHz cavities for DESY
TTF-VUV-FEL - Phase II Qualification and RD for 1.3 GHz
cavities for ILC - Cryostat being fabricated at PHPK (Columbus, OH)
- Delivery date 14-APR-2006
- Cryo lines to cave installed, interface to
cryostat (feed can) under construction - Working 1.3 GHz RF system in MDB
- Operated daily (A0 Capture Cavity 2 testing)
- Gathering components for 3.9 GHz
27HTS Scope and Schedule
- Scope
- Schedule
- Delivery of MDB cryostat in mid-April
- Connect to MDB cryo system and commission
- RF commissioning in parallel
- Ready for 3.9 GHz cavity testing by end June
- FY07 Construction of 2nd HTS in IB1
- Exploits existing facility to increase cavity
throughput - Allows LLRF RD on driving multiple cavities w/
one klystron
28Cryogenics (WBS 5.9.3 5.8.2.2)
- WBS 5.9.3 Cryogenics for Test Stands _at_ FNAL
- Purpose Develop cryogenic capability to cool
cavities in Vertical and Horizontal Test Stands - WBS 5.8.2.2 ILCTA Cryogenics Designer from SLAC
- Funded via SLAC core vs GDE provided funds
- HTS
- Upgrade the existing 1800 W (4K) refrigerator
system at the Meson Detector building at Fermilab
to supply 60 W of 1.8 K refrigeration for the HTS - Transfer lines extended from upstream locations
to MDB - Build and install Feed cans
- Install New Large Vacuum pump skid and associated
plumbing and infrastructure - Modify cryogenic controls
- Near-term Goal Cool 1st 9 cell ILC cavity to 4 K
(Cap. Cavity 2) - Next Goal Achieve 60 Watt capacity at 2K by May
06.
29Cryogenics
- VTS
- Connect existing VTS to existing 60 W 1.8 K
refrigerator system in IB1 for the HTS - Modify existing IB1 LHe transfer and vacuum lines
to connect to VTS top plate - Must wait until LHC quad testing is complete (end
of Apr) - Modify cryogenic controls
- Goal Achieve 60 Watt capacity at 2K to VTS by
the end of FY06.
30Scope and Schedule
- FY06
- Scope
- Current Labor is yyy FTE
- Status Schedule
- Transfer line and feed cans done
- Refrigeration connected to capture cavity 2
- Capture Cavity 2 cooled to 4 K with RF power
- Vacuum Pump skid refurbished installed
- Electrical, water, piping, controls in progress
- Plan 2K capability to Cap Cavity 2 in April
- Plan 2K capability to HTS cryostat by June 06
31MDB Transfer Lines feed cans
This feed can was designed at SLAC and built at
FNAL WBS 5.8.2.2
32Capture Cavity II Cold RF power
First 1.3 GHz TESLA Cavity in MDB Cold and RF
power
MDB Cryogenics 60 W _at_ 1.8 K
25 MV/M _at_ 4.5 K Reasonable Dark Current
33Vacuum Pump Connected in MDB
Electrical Installation
Mechanically Installed
This is a BIG vacuum pump 2 motors total 300 hp!
34ILCTA_NM Cryogenics
- ILCTA_NM
- Installing Cryogenics, vacuum pump, plumbing,
electrical infrastructure, laser room, controls,
etc - Plan to move FNPL photo-injector to New Muon in
07 - Will provide ILC like beam to test cryomodules
- Building transfer lines, feed cans, etc.
- FY06 Funded from Fermilab SCRF infrastructure
from core program funds at FNAL ? ie not via
GDE - FY06 progress is limited by available cash
- Needs serious funding in FY07
- Need to procure a new large refrigerator
- Will provide test of 1st U.S. built Cryomodule in
2007
35 ILCTA_NM _at_ Fermilab
New Muon Lab
FNPL Photo-injector
11/05
- Building a ILC cryomodule test area in the New
Muon Lab (ILCTA_NM) - Cleaning out building (Done) except for CCM
- Bid package out remove CCM
- Plan to move Photo-injector
- Work is in progress to install interim cryogenic
solution in FY06 - Will build part of the cryogenic distribution
system in FY06 - Funding ? Can not start Cryomodule feed cans
until FY07
36NML Heat xchanger LN2 Dewar
37Cryomodule end cans Delayed to FY07 ()
Cryomodule Test at DESY TTF
End Cans
38Current Status
- New Muon Lab
- He storage tanks - 60 complete
- LN2 storage tank was refurbished
- Drawings and specification for Mycom piping
contract - done - PS-1 heat exchanger relocation done
- Helium piping and purifiers bid package - 70
complete - Designing test cave distribution system
- Cryogenic controls - 30 complete
- Budgetary estimate for the ILC CM feed and end
caps done - PLANS
- Long Term goal is one ILC RF unit (3 cryomodules,
modulator, 10 MW klystron, LLRF, etc by 2009
39Conclusions
- Our prime objective is to build and evaluate the
components of the ILC main Linac - Also we need to acquire experience expertise in
the U.S. on SCRF technology - We are building extensive infrastructure at
Fermilab and SLAC in support of these goals - Cavity test facilities ( horizontal and vertical)
- High Power RF test systems
- LLRF test systems
- Cryomodule Test facilities ( including beam tests
) - Significant Technical Progress in FY05?06
- Progress is limited by the available funding