Title: CYCLONE


1
CYCLONE
CYClic Operations NEtwork
CIV E 606
2
CYCLONE
  • A symbolic graphic format for simulation of
    construction processes
  • Three basic modeling shapes
  • Active state (square node represents a work task)
  • Idle State (circle represents a delay or waiting
    position for a resource entity)
  • Directional Flow (arc represents the path of a
    resource entity as it moves between idle and
    active states)

3
CYCLONE Active State Modeling Element (1)
  • NORMAL Work task unconstrained in its
    starting logic and indicates active processing of
    (or by) resource entities

4
CYCLONE Active State Modeling Element (1)
NORMAL
5
CYCLONE Active State Modeling Element (2)
  • COMBI Constrained work task which is
    logically constrained in its starting logic,
    otherwise similar to NORMAL

6
CYCLONE Active State Modeling Element (2)
COMBI
7
CYCLONE Idle State Modeling Element
  • Q NODE The idle state of a resource entity
    symbolically represent a queuing up or waiting
    for use passive state of resources

8
CYCLONE Idle State Modeling Element
Q Node
9
CYCLONE Directional Flow Connection
  • ARROW
  • Original CYCLONE Modeling Element
  • Simphony Connection between the elements

10
Supplementary Modeling Elements in CYCLONE
  • GENERATE Units can be generated (as required
    during the process) at QUEUE nodes
  • CONSOLIDATE Aggregate units
  • COUNTER Count the number of entities passing
  • BRANCH Probability branching (Only in Simphony
    version)

11
CYCLONE GENERATE Modeling Element
12
CYCLONE CONSOLIDATE Modeling Element
13
CYCLONE COUNTER Modeling Element
14
CYCLONE BRANCH Modeling Element
15
Properties and Rules of CYCLONE Modeling Elements
16
CYCLONE NORMAL
Resource Entity Arrival
Resource Entity Departure
  • No QUEUE before NORMAL
  • Several entities can traverse it simultaneously
  • If more than one resource type is connected,
    work task can be processed by either resource.

17
CYCLONE NORMAL
Truck Loaded
Travel To Dump
18
CYCLONE COMBI
All three resourcesare required
Resource entities departure
  • All resources are required to process the work
    task

19
CYCLONE COMBI
Empty Truck
Loaded Truck Available
Dirt
Front EndLoader
Front EndLoader Available
10 minutes to load truck
20
CYCLONE QUEUE
Resource entities released sequentially to a
following COMBI node when the COMBI ingredience
logic is satisfied
Resourcesarriving andentering anidle state
  • QUEUE nodes always precede COMBI nodes

21
CYCLONE QUEUE
From Loading Truck activity
From load truck with dirt
Front End Loader idle
22
CYCLONE
The COMBI-QUEUE node ingredience logic
23
CYCLONE - COUNTER
COUNTER can follow COUNTER can precede
24
Building CYCLONE modelsExample Earth Moving
25
CYCLONE Earth Moving
26
CYCLONE Earth Moving
27
CYCLONE Earth Moving
28
CYCLONE Earth Moving