Characterizing new cells (setup ready for density and window) Test new components. Test new optics ... New over ready for cell testing/characterization: April 1 ... – PowerPoint PPT presentation

Number of Views:19
Avg rating:3.0/5.0
Slides: 5
Provided by: jian114
Category:
Tags: 3he | design | items | pol | setup | tasks

less

Transcript and Presenter's Notes

Title: Design Items and Tasks for pol. 3He


1
Design Items and Tasks for pol. 3He
  • Remain design items (total 16 weeks)
  • Main support Structure (7 weeks)
  • Target drive support
  • Target Collimator support
  • RF support
  • Target enclosure
  • Exit windows
  • Reference cell support
  • Pick-up coils (1 week)
  • Laser optics lines (including EPR,
    spectra-analyzer) (2 weeks)
  • Laser optics line support (2 weeks)
  • Personnel access support (1 week)
  • Safety interlock (1 week)
  • Compass mounts (2 weeks)

2
Tasks for pol. 3He (I)
  • Target lab
  • Spin-reversal test (mostly complete)
  • EPR (partially complete)
  • RF sweep water calibration
  • New oven and support arrived
  • assembling, testing
  • Test new cells (two cells ready to be tested)
  • Characterizing new cells (setup ready for density
    and window)
  • Test new components
  • Test new optics
  • Combine polarization measurements with spin-flip
  • Spin-slip signal to DAQ
  • LabView communication with EPICS

3
Other tasks/issues for pol. 3He (II)
  • Other tasks/issues
  • Compass (Kentucky)
  • Vertical coils (order placed, delivery next
    month)
  • Optical fibers (order placed, delivery in April)
  • Lasers new narrow lasers?
  • Cells new contracts with Mike and Princeton
    Willie?
  • medium size (3) pumping chamber,
    production starts
  • Manpower
  • Readiness review
  • Milestones

4
Draft Milestones for Polarized 3He
  • Spin-Flip test done
  • NMR/EPR system working done
  • New over ready for cell testing/characterization
    April 1
  • Vertical coils test June 1
  • Cell production 10 by July 1, 20 by Dec. 1
  • New target structure Sept. 1
  • Compass Sept. 1
  • Laser optics line Oct. 1
  • NMR FM water (optional) Oct. 1
  • EPR with spin-flip (optional) Oct. 1
  • Complete system test Nov. 1