Material%20Requirements%20Planning - PowerPoint PPT Presentation

About This Presentation
Title:

Material%20Requirements%20Planning

Description:

BOM shows all the parts required to make one of the item. Each part has only one part number ... accurate BOMs and Inventory data. Normally a computer-based ... – PowerPoint PPT presentation

Number of Views:55
Avg rating:3.0/5.0
Slides: 27
Provided by: johnpe68
Category:

less

Transcript and Presenter's Notes

Title: Material%20Requirements%20Planning


1
Material Requirements Planning
Chapter 4
2
MRP
  • Computerized inventory control production
    planning system
  • used to avoid missing parts
  • establishes a schedule
  • shows components required at each level of
    assembly
  • calculates time components are needed

3
Nature of Demand
  • Independent
  • Not related to the demand of any other product
  • E.g. a wooden table by itself is an independent
    demand item
  • Must be forecasted
  • Only independent items are in the MPS
  • Dependent
  • Related to the demand of another item
  • E.g the legs of the wooden table ot the table top
    would be consider dependent demand, unless it was
    a replacement
  • Must be calculated
  • Sometimes both

4
Objectives of MRP
  • Determine requirements
  • Right materials in the right quantities available
    at the right time, to meet demand
  • What to order
  • How much to order
  • When to order
  • When to schedule delivery
  • Keep priorities current
  • Monitor all aspects of production to see where
    problems might affect delivery

5
Grand Scheme of Things
6
Inputs to MRP System
  • 1) Master Production Schedule
  • Schedule of end items produced
  • This drives the MRP system
  • 2) Inventory Records
  • Planning factors
  • Order quantities, lead times, safety stock and
    scrap
  • Status of each item
  • Quantity, allocation, availability
  • Inventory record file
  • Also called the part master file (or item master
    file)
  • 3) Bills of Material (BOMs)
  • Most important document

7
Bill Of Material (BOM)
  • According to APICS, BOM is
  • a listing of all the subassemblies,
    intermediates, parts, and raw materials that go
    into making the parent assembly showing the
    quantities of each required to make an assembly.
  • Three important aspects
  • BOM shows all the parts required to make one of
    the item
  • Each part has only one part number
  • A part is defined by its form, fit and function.
    If any of these change then the part number must
    change

8
BOM Structure
  • Formats
  • Product Tree
  • Parent / component relationship

Parent
Component
9
BOM Structure
  • Formats
  • Multilevel bill

10
BOM Structure
  • Formats
  • Multiple bill

11
BOM Structure
  • Formats
  • Single-level bill

Parent
Component
12
BOM Structure
  • Formats
  • Indented bill

LEVEL ITEM Unit of Measure Quantity 0 - - -
- Clipboard Ea 1 - 1 - - - Clip Assembly Ea 1 -
- 2 - - Top Clip Ea 1 - - - 3 - Sheet
Metal In2 8 - - 2 - - Bottom Clip Ea 1 - - - 3
- Sheet Metal In2 8 - - 2 - - Pivot Ea 1 - - -
3 - Iron Rod In 3 - - 2 - - Spring Ea 1 - - - 3
- Spring Steel In 10 - 1 - - - Rivet Ea 2 - 1 -
- - Board Ea 1 - - 2 - - Press Board Ea 1 - -
2 - - Finish Oz 2
13
BOM Structure
  • Formats
  • Summarized parts list

Part Number Description Quantity Required
203 411 622 023 722 Wooden Leg Wooden Ends Wooden Sides Table Top Hardware Kit 4 2 2 1 1
14
Uses of BOM
  • Product definition
  • Specifies the components needed to make a product
  • Engineering change control
  • record and control engineering changes
  • Service parts
  • Ids replacement parts
  • Planning
  • Material/component purchasing scheduling
  • Order entry
  • price the product based on options selected
  • Manufacturing
  • Lists parts assemblies needed
  • Costing
  • determines direct material, direct labor, and
    distributing costs

15
MRP Planning Process
  • The following will be discussed
  • 1. Exploding and offsetting
  • 2. Gross and net requirements
  • 3. Releasing orders
  • 4. Low-level coding and netting

16
Exploding Offsetting
  • Lead Time
  • The time needed to perform a task

Planning Horizon gt 12 wks
17
Exploding Offsetting
  • Exploding
  • The process of multiplying requirements by usage
    quantity recording appropriate requirements
    throughout the product tree
  • Offsetting

18
Time-phase (example)
Lead time 3 weeks Weekly demand
forecast 20 units Safety stock 30
units Order quantity 100 units An order of
100 units is scheduled for receipt in Week 2 On
hand quantity 40 units
19
  • When will quantity fall below the safety stock
    (30) level?
  • Week 6
  • An order release must be planned for Week 3 to
    have a scheduled receipt in Week 6

20
Releasing an order means that authorization
(planned release date) is given to purchasing to
buy the necessary material or to manufacturing to
make the component. Remember Lead Time is a
critical factor here!
21
Released Orders
  • Scheduled receipts
  • Are orders on manufacturing or on a vendor and
    represent a commitment to make or buy
  • Necessary materials are committed
  • Work-center capacity is allocated
  • Shows quantity ordered and when they expect
    completion and availability
  • Open Orders
  • Scheduled Receipts

22
The Big Picture
23
Basic MRP Record Structure
  • Period
  • Vary in length from a day to a week or longer,
    also
    referred to as the time bucket
  • Planning horizon number of periods in record
  • Gross requirements
  • Anticipated future demand of usage for an item
  • Scheduled receipts
  • Quantities that have already been ordered and
    when we expect them to be completed
  • On hand
  • Projected balance after replenishment orders have
    been received and the gross requirement has been
    satisfied (at the end of the period)
  • Planned order releases
  • Planned replenishment orders for an item (at the
    beginning)

24
  • Low-level Code Netting
  • The lowest level on which a part resides in a BOM
  • (Work through procedure)

25
Multiple Bills of Materials
  • Work Example

26
MRP Summary
  • Used to produce the right components at the right
    time
  • Must have accurate BOMs and Inventory data
  • Normally a computer-based software system
Write a Comment
User Comments (0)
About PowerShow.com