Title: Status of Inner Triplet Correctors
1Status of Inner Triplet Correctors
- For Corrector Team(
- M. Karppinen, AT-MEL-MC
) C. Fernandes, C. Giloux, V. Granata, H. Lopes,
J. Mazet, D. Rodrigues, W. Venturini
2Status of Inner Triplet Correctors
- MCBX Horizontal and Vertical Dipole-corrector
- MCSTX Sextupole-dodecapole Insert of the MCBXA
- MQSX Skew quadrupole
- MCSOX Skew octupole octupole skew sextupole
- Summary
3Inner Triplet Correctors
Q3
Q2
Q1
MQXA
MQXB
MQXB
MCBX
MQXA
MCBXA
MQ S X
MCS OX
MCBX
B PM
B PM
LMQXC
LMQXA
LMQXB
A1 / B1
A1 / B1
A1 / B1 B6 / B3
B4 A4 A3
A2
To IP ?
FNAL supplied
KEK supplied
CERN supplied
4MCBX(A), Inner Triplet Dipole Corrector
27 3 off single-aperture assemblies supplied
by Sigmaphi (F)
5MCBX Status
- In production delivery rate 2 MCBX/month
- 21 magnets delivered to CERN (3 failed)
- 10 magnets delivered to FNAL (incl. 1 MCBXA)
- Last magnet to Fermilab by the end of 2004
- Warm and cold tests at CERN (bottle neck, 2
tests/month) - Starting-up took more time than expected
- Short (520 mm) prototypes (MCBXS, MCBXT) adapted
and shipped to FNAL for the first two Q2s - First pre-series (720 mm) delivered Aug -02
- Magnet destroyed during cold test at CERN Dec -02
- Coil assembly Pre-preg ? Vacuum impregnation
- Assembly tooling modification and trials made in
Jan-Feb -03
6MCBX Deliveries
Block 4 shutdown
7MCBX Quench performanceIndividual powering of
MCBXV (inner dipole)
8MCBX Quench performanceIndividual powering of
MCBXH (outer dipole)
9MCBX Quench performanceCombined powering
10MCBX(A)
11MCBX Transfer function at 1.9 K
12MCBX Hysteresis of B1/A1
Outer dB1 3.8 E-03 Tm, ?k 2.5 / 0.16 µrad _at_
450 GeV / 7 TeV
Inner dA1 6.1 E-03 Tm, ?k 4.1 / 0.26 µrad _at_
450 GeV / 7 TeV
13MCBXV (Inner dipole) Field Quality at 550 A
14MCBXH (Outer dipole) Field Quality at 550 A
15MCBX 12 Warm Cold Field Quality
16MCSTX (of MCBXA) Status
- 9 off production of B3-B6 inserts at CERN
- 6 completed
- 1 destroyed in MCBX 2 test
- 2 tested in MCBX 4, problems with data
acquisition and power supplies - 4 successfully tested in MCBX 8
- 3 being tested in MCBX 7
- 7-10 completed by May -04
- Request for more sextupole strength
- Short (520 mm) prototype reached 150 A in
rotating 3.3 T dipole field - 4 reached 120 A during combined powering.
- Inom 50 A ? 100 A
17MCSTX Parameters
18CD1000630 - MQSXA
9 single-aperture assemblies supplied by Ansaldo
(Ormet)
19MQSX MCSOX
Skew octupole (MCSOX)
Skew sextupole (MCSSX)
Skew quadrupole (MQSX)
Octupole (MCOX)
20MQSXA Status
- 1 model, 1 pre-series MQSXA (combined design)
tested by March -03 - Design change due to modified Q3 lay-out
- 8 MQSX and 8 MCOSX at CERN. Last MCSOX 1 spare
MQSX-MCSOX pair by March 04. - 3 MQSX and 3 MCSOX- assemblies of the new design
successfully cold tested at CERN and shipped to
Fermilab - Warm and cold tests at CERN
- Delays
- In shadow of MQT/S-contract (shared resources)
- Delays in G11-items (central posts/end spacers)
- Tooling development required close follow-up by
CERN staff
21MQSXA Parameters
22MQSXA Quench Performance
23MQSX Skew quadrupole Transfer function at 1.9K
24MQSX Field quality at 1.9 K and 550 A
25MCSSX Skew Sextupole Magnetic performance at 1.9K
26Summary
- MCBX
- In production 2/month, 17 of 27 delivered to
CERN, - 10 tested at CERN
- 10 delivered to FNAL, last delivery expected by
Dec -04 - Field quality seems ok
- MCSTX
- 6 completed at CERN. MCSTX 10 complete by May
-04. - 2 tested, 1 MCBXA shipped to FNAL
- MCSX 100 A seems feasible
- MQSX / MCSOX
- 1 MQSXA, 8 MQSX and 8 MCSOX assemblies delivered
- MCSOX 9 and spare MQSX/MCSOX expected in March
- 3 pairs tested and shipped to FNAL