Title: Decadal Survey Mission Planning
1Decadal Survey Mission Planning
- Presentation to CLARREO Workshop
- Steve Volz
- October 21, 2008
2Agenda
- Decadal Survey Missions
- Overall Decadal Survey study objectives
- Mission Development Approach
3NASA Near-Term Missions (4/15 total)
4NASA Mid-Term Missions (5/15 total)
5NASA Late-Term Missions (6/15 total)
Cloud-independent, high temporal resolution,
lower accuracy SST to complement, not replace,
global operational high-accuracy SST
measurement
6NRC Decadal Survey Recommendations
- NRC made 29 different recommendations in many
areas for Earth Science - NASA is working to address the many
recommendations - Within the Flight group we are addressing only a
few of them - DS missions
- Venture class development
- TSIS CERES recovery
- Completion of current portfolio
- Other ESD groups are addressing
- Technology development (ESTO)
- RA issues
- Applications science
7Earth Science Division Organization
Michael Freilich, Director Peg Luce, Deputy
Director, Flight Randy Friedl, Deputy Director,
Science
1 CS Mgmt Analyst, 2 Program Support, 1 Secretary
SMD-wide Education
Stephanie Stockman, Head
2 IPAs
Research
Flight Programs
Applied Sciences
Earth Science Technology Office (_at_ GSFC)
Steve Volz, Associate
Director Steve Neeck, Deputy Associate Director
Teresa Fryberger,
Associate Director (Vacant), Deputy Associate
Director
Jack Kaye, Associate
Director Lucia Tsaoussi, Deputy Associate
Director
George Komar,Associate Director Amy Walton,
Deputy
14 CS Program Scientists, 5 IPA PS, 2 Detailee PS
In, 1 Detailee PS Out, 1 Secretary
6 CS Program Executives,1 IPA PE, 2 Detailees, 1
Secretary (w/Applied)
4 CS Program Officers
10 CS Technologists (badged to GSFC)
Nov. 28, 2007
8Flight Program Management
Michael Freilich, Director Peg Luce, Deputy
Director Steve Volz, Associate Director Steve
Neeck, Deputy Associate Dir
ESTO IIP, AIST, ATI
Airborne Science
RA
ESSP Program Ed Grigsby, PM
ESM Program Gil Colon, PM
JPL LaRC
Applied Sciences
GRACE (JPL) CloudSat (JPL) CALIPSO Venture
Class OCO (JPL) Aquarius (JPL)
Development Phase A/B/C/D
Operations
Multi-Mission Ops
Decadal Survey Pre-Formulation
Climate Sensors
POES/GOES
NPP LDCM GPM SMAP (JPL) Glory
Terra EO-1 Aqua ICESat Aura QuikSCAT SORCE Jason
(JPL) TRMM Acrimsat (JPL) OSTM (JPL)
ICESat II DESDynI (JPL) CLARREO (LaRC)
Multi-Mission Ops EOSDIS
TSIS CERES (LaRC)
NOAA N GOES-O, -P
9SMAP ICESat II
- SMAP and ICESat II are the first two Decadal
Survey (DS) missions the ESD and NASA will
implement. - SMAP project is being conducted out of JPL, and
completed its transition to Formulation in
September 2008. The projected / planning launch
date is now early 2013. - ICESat II project is being conducted out of GSFC,
and is working to its Mission Confirmation Review
in early 2009. The launch date is under study,
expected between 2014 and 2016 - Both missions (and all DS named missions) are
directed science missions with individual budget
lines. They are managed out of the Earth
Systematic Missions (ESM) Program Office located
at GSFC.
10CLARREO DESDynI
- CLARREO DESDynI are the next Decadal Survey
missions to be addressed by the ESD - Both missions are directed science missions with
individual budget lines. They are managed out of
the Earth Systematic Missions (ESM) Program
Office located at GSFC
- The CLARREO mission is led by LaRC, with GSFC
support - Draft level 1 requirements initial
international partnership discussions, Fall 2008 - Initial mission concepts, Spring 2009,
- Full technology readiness assessment, MCR October
2009 - The DESDynI is led by JPL, with a significant
GSFC contribution - Draft level 1 requirements initial
international partnership discussions, Fall 2008 - Mission configuration down select, Spring 2009
- Full technology readiness assessment, MCR October
2009
11What about the Venture Class?
- NRC Decadal Survey recommended a Venture Class
line of small, cost- and schedule-constrained,
competitively selected missions to complement
the identified strategic missions - Higher risk posture allowed, Class C missions,
single string instruments allowed - High risk, high return demonstration technology a
consideration - Creative spacecraft launch options considered
- FY09 budget does allow a Mission of Opportunity
with start in FY10 and launch NET FY14 -- with
only a small amount of money - The named missions in the Decadal Survey will not
be Venture Class, but will be executed through
the Earth Systematic Missions Program Office - Class B or Class C missions
- NASA certified launch vehicles
- 3 year mission life, with commensurate
reliability requirements - High TRL for instruments required at confirmation
12Technology Readiness Level
TRL levels defined in NPR 7123.1A
High Maturity
TRL 6 is the desired minimum level for
integration of new technology
TRL required fordirected missions
atConfirmation Review
TRL possible forexploratory mission at
Confirmation Review
Low Maturity
13New Decadal Survey-Related IIP Awards
14Where do we expect to be by October 1, 2009?
- For each of the Near- and Mid-Term missions in
the Decadal Survey - Quantitative assessment of the readiness to
proceed to Formulation (Phase A) - Draft level 1 science requirements, baseline
mission concept, draft formulation authorization
document, partnership evaluations, technology
readiness level assessments - Mission Confirmation Review (MCR) readiness
expected for CLARREO and DESDynI based on FY09
budget, but to be determined by teams
demonstrated progress - Mission maturation plan for FY10 and beyond,
through launch and ops - Life Cycle Cost, independent cost and schedule
estimates - Decadal Survey Program assessment, including
- Cross cutting mission analyses, constellation
measurement requirements, ground systems,
platform, and ground networks - Definition of scope and implementation approach
for the Venture Class of small mission
opportunities
15BACKUP
16Programmatic Implementation within SMD
Associate Administrator (AA) (Ed Weiler) Deputy
AA (Chuck Gay)
Deputy AA for Programs(Mike Luther)
Deputy AA for Management(Roy Maizel)
Chief Scientist (Paul Hertz) - Lead for
Research (Max Bernstein) - Lead for
E/PO (Stephanie Stockman)
AAA for Strategy, Policy International (Marc
Allen)
Senior Advisor(Colleen Hartman)
Strategic Integration Management DivisionDir.
(R. Maizel-Act)Dep. (Vacant)
HeliophysicsDivision Dir. (R. Fisher)Dep. (V.
Elsbernd)
AstrophysicsDivision Dir. (J. Morse)Dep. (R.
Howard)
Resource Management DivisionDir. (R.
Maizel-Act)Dep. (Vacant)
Earth Science Division Dir. (M. Freilich)Dep.
Programs (M. Luce)Dep. Science (R. Friedl)
Planetary Science Division Dir. (J. Green)Dep.
(J. Adams)
Research (J. Kaye)
Mars Program(D. McCuistion)
Applied Science (T. Fryberger)
Flight (S. Volz)
Decadal Survey Directed Missions
Competitively Selected Venture Class missions
Draft July 22, 2008
17ESD Execution of Decadal Survey Missions
- All Decadal Survey Missions concepts studies are
directed by the ESD and will be managed by the
Earth Systematic Missions (ESM) Program Office at
GSFC - All mission development will have a study
management team, led from HQ ESD by the HQ
Program Scientist and Program Executive, and
including representatives from ESTO, data
systems, applied sciences, and the ESM program
office - All members of the mission study ESD teams should
be involved in all relevant study discussions,
and the PS and PE are expected to participate in
cross mission science and mission trades
18NASA Hierarchy of Directives
- NPR 7120.5D - NASA Space Flight Program and
Project Management Requirements governs the
processes associated with formulating and
implementing a new flight project - Important details for GEO-CAPE
- Defines the Major Milestones
- Identifies all requirements for each phase of the
Project - Identifies all gate products for each phase
- Defines roles and responsibilities
- Identifies all major reviews
19Flight Project Life Cycle
Extracted from NPR 7120.5D
20Mission Requirements for Pre-Phase A
Scope of Major Pre-Phase A Activities
- Headquarters
- Approve a Formulation Authorization Document
- Develop DRAFT Level 1 Requirements
- Conduct Acquisition Strategy Planning Meeting
- Technical Activities
- Develop and document preliminary mission concepts
- Conduct internal Reviews
- Conduct Mission Concept Review Project Planning,
Costing and Scheduling - Develop and document a DRAFT Integrated Baseline,
including - High level WBS
- Assessment of Technology Readiness Levels
- Assessment of Infrastructure and Workforce needs
- Identification of potential partnerships
- Identification of conceptual acquisition
strategies for proposed major procurements - KDP Readiness
- Obtain KDP A Readiness products
- Approval through the governing PMC
Areas the Science Community must work
- Development of DRAFT Level 1 Science Requirements
- Support development of preliminary mission
concepts - Support the assessment of Technical Readiness
Levels - Identify potential partnerships
21Key Pre-Phase A Questions
- What science MUST this mission achieve?
- What specific measurements?
- To what accuracy?
- What are the required data products?
- What mission parameters can achieve the science?
- What orbit (inclination/altitude)?
- Which instruments?
- What is the baseline mission duration?
- How can NASA achieve these measurements?
- Are there other missions required/desired to
achieve the science? - Who can NASA partner with to achieve this
mission?
Should be resolved 12 months prior to KDP A
Should be resolved 6 months prior to KDP A
22Notional Mission Timeline
NOTE The time for each phase is considered
nominal - could be accomplished earlier