Title: CarbonCast
1- CarbonCast
- Architectural Panels
- Ken Baur, PE
- High Concrete Group
866.GO-ALTUS . www.altusprecast.com
PO Box 10097 Lancaster, PA 17605-0097
2Contents
- Benefits Relative Cost
- Example Projects
- Details
- C-GRID Used
- Manufacturing Process
- Tests
- Ongoing Research Testing
3Benefits Relative Cost
- CUSTOMER BENEFITS
- All the benefits of precast
- Up to 66 lighter
- Less concrete
- Larger pieces
- Reduced shipping
- Reduced erection time or crane size
- Ideal for use with a tower crane where capacities
are limited - Ideal for mid-and high-rise buildings or sites
with poor soils - Non-corrosive face reinforcing
- Ideal for salt-laden environments
- High Thermal Efficiency
- Composite R-values ranging from R-8 to R-12
- Superior mold resistance
- RELATIVE COST
- Installed cost of panels is same as -- or less
than conventional precast - Superstructure and foundation costs are usually
less - Insulation and/or HVAC costs can also be reduced
4Benefits Relative Cost
- PRECASTER BENEFITS
- Can cost less to provide
- Less concrete
- Larger pieces
- Reduced shipping
- Reduced erection time or crane size
- Ideal for use with a tower crane where capacities
are limited - Ideal for mid-and high-rise buildings or sites
with poor soils - Unique, specifiable, proprietary
- Something new to talk about
- Gets you first and last look
- Hard to displace once its designed in
- Alternatives are less desirable
- Brick leaks, EIFS has problems, GFRC is not
readily available and SlenderWall-like systems do
not offer the same appearance or insulation - Can be combined with conventional precast to
value-engineer a job - Precast spandrels on lower-story parking
- CarbonCast panels on upper stories
5Example Costs/SF 8x30x6
- Conventional 75 psf
- - Engineering
- - Forming
- 3.37 - Sub-Total
- 1.42 - Strand/Rebar
- 2.10 - Connectors
- 1.00- Concrete (back)
- 1.24 - Concrete (face)
- .15 - CNI
- .45 - Mesh
- 6.00 - LO
- .76 - Permits
- 1.36 - Hauling
- 5.00 - Erection
- 20.75 - TOTAL
- CarbonCast 30 psf
- - Engineering
- - Forming
- 3.37 - Sub-Total
- .63 - Strand/Rebar
- 1.62 - Connectors
- .25 - Concrete (back)
- .93 - Concrete (face)
- .60 4 Foam
- .95 - C-GRID
- 6.00 - LO
- .38 - Permits
- .68 - Hauling
- 4.50 - Erection
- 19.91 - TOTAL
- Includes shear grid
- Excludes Savings On
- Foundations
- Superstructure
6Shipping
7C-GRID Enabling Technology
ACI minimum cover for steel reinforcing
In-use thicknesses begin at 4 and are usually 6
or more
.
.
5/8
1-5/8
3/4
Exterior face
Minimum cover for carbon fiber reinforcing
1/4
In-use thicknesses begin at 1 ¼
_
_
5/8
1/4
Exterior face
8C-GRID Used
GIRD TYPES C 5500 FX C 5500 OX C 5500 Shear
Grid NOTE The grid we started with costs
1.15/sf. We are now testing grid that costs
.60/sf.
9Example Projects
- MillionAir Terminal -- Teeterboro, NJ
- Executive terminal with 7,000 sf of cladding
- Heldrich Plaza New Brunswick, NJ
- 10-story mixed-use project (hotel and high-end
residential) with 40,000 sf of cladding - Symphony House Philadelphia, PA
- 31-story condominium with 120,000 sf of cladding
10Recent Construction Shots
11Heldrich Plaza
12Heldrich Plaza
13Architectural Panel Types
Panels can have any precast finish from
acid-etched to thin brick
14Details
Prestressing or post-tensioning is required for
long or tall panels
15Architectural Panel - Back Ribs
16Architectural Panel - Horizontal Rib
17Architectural Panel - Openings
18Architectural Panel - Secondary Vertical Rib
19Architectural Panel - Thin Brick Veneer
20Architectural Panel - Horizontal Ribs
21Architectural Panel Panel-to-Panel Firestop
22Architectural Panel Solid Rib Firestop
23Architectural Panel Assembly Firestop
24Architectural Panel - Assemblies A B
25Shop Details
Connections are the same as conventional
precast Hardware must be the same from precaster
to precaster
26Thermal Efficiency
8-0 x 30-0 w/o thermally-broken top bottom
ribs
8-0 x 30-0 8 x 30 w thermally-broken top
bottom ribs
27Manufacturing Process Sample Panel
28Manufacturing Process
29Other Manufacturing Examples
30Tests
- Flexural Strength of Thin-faced Architectural
Panels - 2-0 x 8-0 x 1.25 Thick Slabs
- Lehigh University ATLSS Center Bethlehem, PA
- Wind Load Test 110mph
- 86x30-0x6 Architectural Panel
- Architectural Testing, Inc. York, PA
- Rilem Tube Moisture Absorption
- Test
- 1.25 Thick Samples
- Mark Patton, PE, Ph.D Pittsburgh, PA
- Thermal Cycling Test
- 86x30-0x6 Architectural Panel
- Mark Patton, PE, Ph.D
- Carnegie Mellon University,
- Pittsburgh, PA
1 thick panel supports car
31Tests
- Prestressing of C-GRID for use in Architectural
Panels - I - Penn State University State College, PA
- One-hour ASTM E119 Fire Test
- Omega Testing Labs San Antonio, TX
32Full-Scale Testing
33Ongoing Research Testing
- Prestressing of C-GRID for use in Architectural
Panels - II - Lehigh University ATLSS Bethlehem, PA
- Pull-out of Inserts Lifting Devices in
Thin-ribbed Members - Lehigh University ATLSS Center Bethlehem, PA
- Missile Impact Test TAS 201-94
- Clemson University Clemson, SC
- Strand Bond Behavior in SCC
- Kansas State University Manhattan, KS
- Fire Performance of Intumescent Paints on
Skim-coated EPS Foam - Cost-reduction and development of a non-insulated
panel
34Technical Standards
35Technical Standards
- General Technical Standard
- Technical Manual for CarbonCast Architectural
Panels - Technical Manual for CarbonCast Insulated Wall
Panels - Technical Manual for Double Tees
36General Technical Standard
- Table of Contents
- 1. Use of C-GRID in Precast Products
- 2. Design Philosophy
- 3. Material Properties
- 4. Design Properties
- 5. Basic Design Requirements
- Design for Flexure
- Serviceability
- Creep Rupture and Fatigue
- Shear
- Temperature and Shrinkage
- Development and Splices
- 6. Design for Shear Transfer in Composite
Action - References
- Appendix A Shear Deformation
37IWP Technical Standard
- Product Champion Harry Gleich
- TABLE OF CONTENTS
- 1 INTRODUCTION
- 2 GENERAL CONSIDERATIONS
- 3 FLEXURAL DESIGN
- 4 LOAD BEARING DESIGN
- 5 SHEAR WALL CONSIDERATIONS
- 6 DETAILING CONSIDERATIONS
- 7 INSULATION AND THERMAL PERFORMANCE
- 8 MANUFACTURE OF SANDWICH PANELS
- 9 PRODUCT TOLERANCES, CRACKING AND REPAIRS
- 10 HANDLING, SHIPPING AND STORAGE OF SANDWICH
PANELS - 11 ERECTION OF SANDWICH PANELS
- 12 INSPECTION OF SANDWICH PANELS
- 13 REFERENCE DOCUMENTS
38Architectural Technical Manual
- Introduction
- Notation
- Chapter 1 CarbonCast Architectural Panels
- Chapter 2 Design of CarbonCast Architectural
Panels - Chapter 3 - Design of Connections for Gravity and
Wind Loads - Chapter 4 Production of CarbonCast
Architectural Panels - Chapter 5 Fire Resistance of CarbonCast
Architectural Panels - Chapter 6 Insulation Properties
- Chapter 7 Details
- Chapter 8 Guide Specification
39Double Tee Standard
- Table of Contents
- INTRODUCTION
- Notation
- Chapter 1 CarbonCast Double Tees
- 1.1 General
- 1.2 C-Grid
- 1.3 Advantages of CarbonCast Double Tees
- 1.4 Design Responsibility
- Chapter 2 Design of CarbonCast Tees
- 2.1 General
- 2.2 IBC2003 Loading
- 2.3 Design Example
- Chapter 3 Connections
- 3.1 General
- Chapter 4 Production of CarbonCast Tees
- 4.1 General
- 4.2 Fabrication
- 4.3 Curing/Stripping
- 4.4 Finishing
40Current Initiatives
- Refining Design of Architectural Panels
- Stem Decks Housing Wall Panels
- Double Tees
- Finalizing Technical Standards
- Moisture and Thermal Issues
- Fatigue and Sustained loading
- Code Issues
- Shear Capacity
- Minimum Reinforcement
41Design Standards
42- CarbonCast
- Insulated Wall Panels
866.GO-ALTUS . www.altusprecast.com
PO Box 10097 Lancaster, PA 17605-0097
43Contents
- Testing
- Manufacturing
- Thermal Performance
- Competitive Comparison
- Details
- Projects
- Conclusions
44Wall PanelsBenefits, Design Production
- Benefits of CarbonCast Wall Panels
- Example Projects
- Panel configurations and terminology
- Calculating R-values
- Standard and design examples
- Production process and photos
- Cost comparison vs. other systems
- Foams EPS, XPS Polyiso
- Summary of testing completed and in progress
45CarbonCast Sandwich Wall
46Full-Scale Load Testing
- Panel size ? 8-0 x 36- 0
- Panel configuration ? 2/ 4/ 2
- Prestressed
47Load Test Details
- Panel cast in Greenville, SC
- Shipped to Oldcastle plant in RI
- Tested in 4-point bending
- Design load was 24 psf
48Full-Scale Load Test
49Test Procedure
- Loading Protocol
- 50 of designed wind in each direction 300
cycles - 85 of design wind load sustained for one hour in
each direction - Incrementally loaded to failure
This type of testing has never been done on an
insulated sandwich wall before!
50Test Results
Testing showed that the CarbonCast insulated wall
panel is 100 composite!
- What does this mean?
- AltusGroup can make thinner panels because both
wythes work together - AltusGroup can span longer with thinner panels
- Panels are thermally efficient
- AltusGroup can supply panels with extremely high
R-Values
51Manufacturing
52Lifting and Rotating Panel
53Thermal Performance
- 1. AltusGroup insulated wall panel is as
thermally efficient as any wall system in the
market place. - We use Expanded Polystyrene (EPS)
- Extruded Polystyrene (XPS) can be used but costs
more
54R-Values
55AltusGroup vs. Competition
Lets Use a Sample Project to Compare AltusGroup
Panels with the DOW or Owens Corning Systems
- Case Study Project Parameters
- Height of building is 32 ft with roof tie point
at 2 ft. from top of panel - Load bearing for steel roof with bar joist span
of 60 ft. - R- Value required for this project is 13 --
steady state
56AltusGroup vs. Competition
- The AltusGroup Panel would be our Standard 8
panel - The Dow or Owens Corning Panel as non-composite
panel would have a 2 outside wythe, 2.5 of
insulation, and depending on the engineer, a 5
to 8 inside wythe
57AltusGroup vs. Competition
- Assume Costs
- Concrete 0.30/inch/ sq. ft.
- EPS insulation 0.12/in/sq.ft.
- Shear grid 0.32/sq.ft. wall surface
- Owens Corning system (w/ pins) 1.40/sq.ft. of
wall surface - DOW System (w/ non-composite pins) 1.40/sq.ft.
of wall surface
58AltusGroup vs. Competition
- AltusGroup Panel
- Concrete cost 0.30 x 4.67 1.41
- Insulation cost .12 x 3.33 0.40
- Shear Grid cost 0.32
- Total cost of material 2.13
59AltusGroup vs. Competition
DOW Panel Concrete cost 0.30 x 7
2.10 Insulation cost 0.12 x 3.33
1.40 Total cost of material (minimum) 3.50
Owens Corning Panel Concrete cost 0.30 x 7
2.10 Insulation cost 0.12 x 3.33
1.40 Total cost of material (minimum) 3.50
60AltusGroup vs. Competition
Comparison of Panel Weights AltusGroup panel
weighs 59 psf (22,700 lbs for a 12 wide x 32
tall panel) DOW or Owens Corning panel weighs
87.5 psf (33,600 lbs for a 12 wide x 32 tall
panel)
More panels/load!
61CarbonCast Wall Panel Details
62CarbonCast Wall Panel Details
63CarbonCast Wall Panel Details
64Sample CarbonCast Projects
65Sample CarbonCast Projects
66Conclusions
- High R-values for less cost
- 2 hour design
- Lighter weight panels
- 100 composite action leads to thinner panels,
reduced construction costs, and more net rentable
or usable floor area - Horizontally-spanning hardwall panels can
eliminate column-to-column foundations on
pre-engineered buildings
67- CarbonCast Pre-topped Double Tees
- Ken Baur, PE
- High Concrete Group
866.GO-ALTUS . www.altusprecast.com
PO Box 10097 Lancaster, PA 17605-0097
68Contents
- Benefits Relative Cost
- Example Projects
- Enabling Technology
- Details
- Manufacturing Process
- Tests
- Ongoing Research
69Benefits Relative Cost
- BENEFITS
- Superior flange durability
- Ideal for salt-laden environments
- Seaside locations
- First floor roof decks in the Northeast,
Mid-Atlantic, Ohio Valley Midwest states - 12 Lighter (if using one-hour rated 3 ¼
flange)Reduction or elimination of - Corrosion Inhibitors
- Epoxy-coated Mesh
- Post-applied Sealants - initial future
applications - RELATIVE COST
- Same as -- or slightly more than --
steel-reinforced
70Example Costs/SF 12TT
- Conventional 4
- - Engineering
- - Forming
- - Strand
- - Connectors
- - LO
- - Permits
- - Hauling
- - Erection
- 8.02 - Sub-Total
- .22 - Steel Mesh
- .21 - Epoxy or CNI
- 2.30 - Concrete
- 10.75 - Sub-Total
- .50 - Field Sealant
- 11.25 - TOTAL
- CarbonCast 3 1/4
- - Engineering
- - Forming
- - Strand
- - Connectors
- - LO
- - Permits
- - Hauling
- - Erection
- 8.12 - Sub-Total
- .60 - C-GRID
- .00 - Epoxy or CNI
- 2.05 - Concrete
- 10.75 - Sub-Total
- .00 - Field Sealant
- 10.75 - TOTAL
- Excludes Savings On
- Foundations
71Example Projects
- GE Parking Deck Milwaukee, Wisconsin
- 90,000 sf installed on roof deck of 360,000 sf
garage - Channel Club Parking Garage Monmouth Co., NJ
- 90,000 sf to-be-built deck to replace badly
deteriorated CIP garage
72C-GRID Enabling Technology
ACI minimum cover for steel reinforcing
In-use thicknesses begin at 4
.
.
5/8
1-5/8
3/4
Exterior face
Minimum cover for carbon fiber reinforcing
1/4
In-use thicknesses begin at 1 ¼
_
_
5/8
1/4
Exterior face
73C-GRID Used
GRID TYPES C 5500 FX C- 5500 - EX
74Double Tee Narrow Leg
Design is Straight-forward per AltusGroup Design
Handbook
75Double Tee - Wide Leg
76Double Tee - Stem Blockout
77Details
Max Span
Flange Thickness
Overall Depth
3 ¼ 4 5/8
Common spans and depths are used
26
62
3 ¼ 4 5/8
66
30
3 ¼ 4 5/8
70
34
NOTE 3 ¼ flange 1 hour-rated 4 5/8 flange
2 hour-rated
Assumes 50psf Live Load
78Details
Vector connectors are required and should be
stainless steel
79Manufacturing Process
80Manufacturing Process
81Manufacturing Process New Method
82Manufacturing Process New Method
83AltusGroup IMPRESSOR
84Tests
- Uniform Concentrated Load Testing 4 Flange
- 3000 point load per IBC 2003
- Uniform live load per IBC 2003
- JWPeters Burlington, WI Rochelle, IL
- Washington University St Louis, MO
- Uniform Concentrated Load Testing 3 ¼ Flange
- 3000 point load per IBC 2003
- Exceeded requirements by 2x
- w/o cracking or excessive deflection
- Uniform live load per IBC 2003
- High Concrete Denver, PA
- Penn State Univ Harrisburg, PA
- One-hour E119 Fire Test
- 3 ¼ Flange
- Pre-cracked, joint at center, unrestrained
- Southwest Research Labs San Antonio, TX
85Ongoing Research
- Cyclic load testing of C-GRID in double tee
flange specimens - Washington University, St. Louis
- C-GRID radiant heating applications
- TechFab, LLC Anderson, SC
- Prestressing of C-GRID for use in Architectural
Panels - II - Lehigh University ATLSS Bethlehem, PA
86- Lightweight CarbonCast Architectural Panels
- When to Recommend Use
866.GO-ALTUS . www.altusprecast.com
PO Box 10097 Lancaster, PA 17605-0097
87When to Recommend Lightweight CarbonCast Panels
- When deep window recesses, reveals or the
appearance of thick panels is desired - For high rises and mid-rises above 7 stories
- For salt-laden environments
- In high seismic or poor soil zones
- For recladding projects
- For LEED-certifiable buildings
- In Design Development
- Before the foundation and superstructure are
designed - Before a tower crane is selected
- In Value Engineering
- When the foundation superstructure can be
rethought - When the tower crane can be rethought
- When the theres a long crane reach required
- When the cost/pick is extremely high
- When site access is limited in hours
- When the project is a long way from your plant
- When you want to develop a proprietary spec
88Lightweight CarbonCast Panels - Customer Benefits
- Enables more points toward certification than
conventional precast - Can improve wall assembly R-value and reduce
HVAC/utility costs - Can provide integral insulation and a smaller
footprint or more net rentable/useable floor
space - Reduces opportunity for in-wall condensation
- Lighter weight works in many applications where
precast doesnt and provides a superior result
to other lightweight cladding options - Reduces foundation, superstructure tower crane
costs - Reduces erection time
- Enables thick panels when they otherwise cant be
afforded - Provides a face that wont stain or spall
89Lightweight CarbonCast Panels - Precaster
Benefits
- Provides a competitive performance advantage
- Provides access to work you wouldnt ordinarily
get - Provides competitive advantage on cost of project
- Can reduce the number of trucks required to
service the job - Can provide access to work you wouldnt
ordinarily get - Provides an opportunity to be competitive on jobs
that are far away - Limits the number of bidders to a select few who
can do a good job
90When to Recommend CarbonCast Architectural Panels
91When to Recommend CarbonCast Architectural Panels
92When to Recommend CarbonCast Architectural Panels
93When to Recommend CarbonCast Architectural Panels
94When to Recommend CarbonCast Architectural Panels
95Benefits
- Fewer pilings
- Smaller spread footers
- Fewer perimeter columns
- Less load on slabs less slab reinforcing
required for gravity loads - Smaller/shorter shear walls w/lesser or fewer
connections - Lighter gravity connections
- Larger panels
- Thinner stud walls
- Less or no additional insulation
96- High Performance CarbonCast Wall Panels
- When to Recommend Use
866.GO-ALTUS . www.altusprecast.com
PO Box 10097 Lancaster, PA 17605-0097
97When to Recommend High Performance CarbonCast
Wall Panels
- When thermally-efficient panels are needed
- When a high R value is needed
- When Thermomass panels are being considered
- In lieu of block and brick
- When a load-bearing exterior wall is needed or
when an opportunity to eliminate perimeter
structure exists - When a precast interior finish is desirable
- When a 2-3 hour fire rating is required
- When reducing the thickness of the perimeter wall
is desirable - For low and mid-rise buildings
- For salt-laden environments
- In high seismic or poor soil zones
- For LEED-certifiable buildings
- In Design Development
- Before the foundation and superstructure are
designed - In Value Engineering
- When the foundation superstructure can be
rethought - When the field construction schedule is
constrained - When theres a long crane reach required
- When the project is a long way from your plant
98CarbonCast High Performance Wall Panels -
Customer Benefits
- Enables more points toward certification than
conventional precast - Can improve wall assembly R-value and reduce
HVAC/utility costs - Can provide integral insulation and a smaller
footprint or more net rentable/useable floor
space - Eliminates opportunity for in-wall condensation
- Reduces foundation, superstructure tower crane
costs - Reduces construction time vs. other systems
- Can provide a face that wont stain or spall
99High Performance CarbonCast Wall Panels -
Precaster Benefits
- Provides a competitive performance advantage
- Provides competitive advantage on cost of project
- Can reduce the number of trucks required to
service the job - Provides an opportunity to be competitive on jobs
that are far away - Limits the number of bidders to a select few who
can do a good job
100- CarbonCast Pretopped Double Tees
- When to Recommend Use
866.GO-ALTUS . www.altusprecast.com
PO Box 10097 Lancaster, PA 17605-0097
101When to Recommend CarbonCast Pretopped Double Tees
- When a pretopped deck is desired
- When pourstrips can be eliminated
- When eliminating maintenance is desireable
- In salt-laden environments
- 1-2 hour fire rating is required
- When reducing the weight of the tee is is
desirable - In high seismic or poor soil zones
- For LEED-certifiable buildings
- In Design Development
- Before the foundation and superstructure are
designed - In Value Engineering
- When the foundation superstructure can be
rethought - When the field construction schedule is
constrained - When theres a long crane reach required
- When you want to develop a proprietary spec
102CarbonCast Pretopped Double Tees Customer
Benefits
- Enables more points toward certification than
conventional precast - Reduces foundation superstructure costs
- Provides a longer-lasting flange that needs less
maintenance
103CarbonCast Pretopped Double Tees Precaster
Benefits
- Provides a competitive performance advantage
- Provides competitive advantage on cost of project
- Limits the number of bidders to a select few who
can do a good job