3.9 GHz 3rd Harmonic Cavities
  • Current Status
  • Prototype cavity No. 1 at Jlab for repair of
    hole.
  • Prototype cavity No. 2 main coupler end
    assembly complete -- pick up end assembly 75
    complete (awaiting repair of Sciaky four spindle
    positioner) -- dumbbells welded.
  • Cavities No. 3-6 end tubes complete -- 36
    dumbbells welded (Jlab) -- all additional parts
    complete -- dumbbells will be trimmed and NW40
    flanges touched up to fit end tubes -- all parts
    and required welding fixtures will be shipped to
    Jlab.
  • Cavities No. 7 8 end tubes complete -- half
    cell blanks cut -- all additional parts complete.

2
(No Transcript)
3
(No Transcript)
4
3.9 GHz 3rd Harmonic Cavities
  • Schedule
  • Prototype cavity No. 1 mid-November 2005
  • Prototype cavity No. 2 ?
  • Cavities No. 3-6 March 2006
  • Cavities No. 7 8 April 2006 ?

5
3.9 GHz 3rd Harmonic Cavities
  • Projected Costs (November 1 to completion)
  • Machine shop 34K
  • Welding (Sciaky) 23.5K
  • Jlab 30K

6
3.9 GHz 3rd Harmonic Cavities
  • Required Resources November 1 to completion
  • Engineer 1.0 FTE
  • Technician 0.5 FTE (priority 1)
  • A0 Technicians 1.5 man-days two times per month
    on average
  • Machine Shop 0.5 FTE (priority 1)