Title: Design and Status of the ISACII Cryogenic System
1Design and Status of the ISAC-II Cryogenic System
- Outline
- Introduction to ISAC-II
- Accelerator Tour
- Cryogenic Specification
- Cryogenic System
- System components
- Operating modes
- Status
2TRIUMF
Vancouver
ISAC-II
ISAC-I
Cyclotron
3(No Transcript)
4(No Transcript)
5Experiments ISAC II
ISAC II - 2007
ISAC II - 2005
ISAC II - 2009
ISAC II - 2001
6Stage 0 - 2005
E4.5MeV/u A/q6
S0
7Stage 1 - 2007
E6.5MeV/u A/q7
S0
8Stage 2 - 2009
E6.5MeV/u A/q7
S0
9ISAC-II SC Linac
10Medium Beta Cavity
Chemical Polishing at CERN
- Prototype developed in collaboration with A.
Facco of LNL and fabricated in E. Zanon - Simple construction suitable for industry
production - Twenty cavities ordered from E. Zanon in Italy
- Four received at TRIUMF after chemical polishing
at CERN - Remaining cavities to be polished at JLAB
Frequency Measure at Zanon
Four Cavities at TRIUMF
11Superconducting Solenoids
Prototype Solenoid at Accel
- Focussing in the SC Linac is provided by
superconducting solenoids (B?9T) - End fringe fields controlled with active
bucking coils (Bcavity?0.1T) - Medium beta prototype received incomplete from
Everson Electric due to bankruptcy - Production Medium and high beta solenoids in
fabrication at Accel - See table for specifications
12Medium Beta Cryomodule
- First Medium beta cryomodule in assembly
- Goal is to complete first cold test by early 2004
- Stainless steel vacuum enclosure
- LN2 cooled copper shield
- mu metal for magnetic field suppression
Lid Assembly in Assembly Frame
13Vacuum Tank
- 1.9cm thick stainless steel (316L) with external
reinforcing ribs - L176cm, W99cm, H196cm
- All services through 44 flanged ports on lid
14(No Transcript)
15Cryogenic System
- The cryogenic system will be installed in two
equal stages - Timing will follow staged installation of linac
- Smooths cash flow
- Allows redundancy in final configuration
16Cryogenic Loads (Phase 1)
13W
13W
13W
13W
13W
14W
14W
3W
24W
24W
24W
24W
24W
36W
36W
6W
CM1
CM6
CM2
CM3
CM4
CM5
CM7
Medium Beta (4)
High Beta (6)
96W
17Cryogenic Loads (Phase 12)
13W
13W
13W
13W
13W
14W
14W
3W
15W
2W
2.W
3W
22W
8W
64W
8W
0W
0W
64W
32W
32W
32W
32W
32W
48W
48W
CM1
CM6
CM2
CM3
CM4
CM5
Medium Beta (4)
High Beta
CM7
540W
18Phase 1 Refrigerator (500W)
- TC50 ordered from Linde (delivery July 2004)
- 530W _at_ 4.5K and 0.7gm/sec liquifaction with LN2
precooling - Choice based on
- Expected Normal Loads
- 198W static and 192W active ? 390W
- Cooldown mode (maximum liquification)
- Phase 1 5.2gm/sec (150liq-ltr/hour)
- Pressure variation specification
- dP/dtlt1Torr/sec
- ?Plt10Torr
19(No Transcript)
20Phase 1 Refrigerator
- TC50 comprises
- Cold box
- Main compressor
- Kaeser ESD441
- Recovery compressor
- Kaeser BSD62
- ORS and gas management system
- TRIUMF to install Linde components plus
- Helium dewar, buffer tank, warm piping and cold
distribution
21ISAC-II Building
f1/225Hz
f1/225Hz
f1/225Hz
Compressor Room
Buffer Tanks
Refrigerator Room
Linac Distribution
22Compressor Room
- Delivery scheduled for June 2004
- TRIUMF to do installation
- Main compressor equipped with VFD for power
saving - ORS and gas management
- Linde system
- 17Bara
23Refrigerator Room
- Cold box
- Delivery scheduled for July 2004
- TRIUMF to do installation
- Helium dewar (1000 ltr)
- Specification written for tender
- Delivery scheduled for July 2004
24Helium Buffer Tank (Phase 1)
- Specification for tender issued
- Required for Aug. 2004
25Cold Distribution
Cold Helium Return
LHe
CM1
CM2
CM3
CM4
Cold Box
Dewar
Warm Helium Return
- Parallel supply feed from dewar through main
header (4.5K) - Cold helium return (lt20K) during normal operation
- Warm helium return (gt20K) to compressor suction
used during cooldown and for power lead cooling
26Cold Distribution Cryomodule
- Individual vacuum jacketed lines for supply and
return - U-tubes for supply and return to cryomodule from
main trunk-line
27Cryogenic Distribution (Phase 1)
- Specification in preparation
- Required for June 2005
28Cryomodule Distribution
- Cryomodule cooled by forcing helium vapor to
bottom of each cold element with a distribution
spider
Supply He
Cold Return
29- Cryogenic Controls
- Linde TC50
- Siemans local controller
- TRIUMF to monitor with EPICS site control system
and Prophi-bus communication - Distribution system
- TRIUMF to control via EPICS interface
30(No Transcript)
31Operating Modes
- Normal Mode (cold linac)
- Three power levels available (rf off, rf
moderate, rf maximum) - VFD on main compressor to save wall power
- Cooldown mode
- One or more cryomodules require cooling down
- Controlled warm-up mode
- Emergency shut-down
32- Cooldown Simulation
- Assume
- ?150 liq-ltr/hour production
- 5 hours to cool down a CM and 2 hours to fill
- Require two fills to reach thermalization
33 Cool Distribution (4 hours)
CM1
CM6
CM2
CM3
CM4
CM5
CM7
150l/hr
150l/hr
34Cooldown Flows (0-7 hours) Fill CM7
4.2g/s
4.2g/s
CM1
CM6
CM2
CM3
CM4
CM5
CM7
120l/hr
50l/hr
35Cooldown Flows (7-15 hrs) Fill CM6
7.9g/s
3.9g/s0.2x
3.8g/s
CM1
CM6
CM2
CM3
CM4
CM5
CM7
1
110l/hr
10l/hr
50l/hr
36Cooldown Flows (15-19 hrs) Refill CM7
8.1g/s
3.0g/s1.0x
3.9g/s0.2x
CM1
CM6
CM2
CM3
CM4
CM5
CM7
1
110l/hr
10l/hr
50l/hr
37Cooldown Flows (19-26hrs) Fill CM5
6.6g/s
0.0g/s0.4x
3.5g/s
2.5g/s0.2x
CM6
CM1
CM2
CM3
CM4
CM5
CM7
2
1
100l/hr
10l/hr
10l/hr
50l/hr
38Cooldown Flows (26-30hrs) Refill CM6
6.9g/s
0g/s.4x
2.5g/s1.0x
2.8g/s.2x
CM5
CM1
CM6
CM2
CM3
CM4
CM7
2
1
100l/hr
10l/hr
10l/hr
50l/hr
39Cooldown Flows (30-37hrs) Fill CM4
6.1g/s
2.0g/s0.2x
3.1g/s
0.0g/s0.4x
0.0g/s0.4x
CM6
CM1
CM2
CM3
CM4
CM5
CM7
2
2
1
90l/hr
10l/hr
10l/hr
10l/hr
50l/hr
40Cooldown Flows (37-41hrs) Refill CM5
6.3g/s
0.0g/s0.4x
2.8g/s0.2x
0.0g/s0.4x
1.7g/s0.8x
CM6
CM1
CM2
CM3
CM4
CM7
CM5
2
2
90l/hr
10l/hr
10l/hr
10l/hr
50l/hr
41Cooldown Flows (41-48hrs) Fill CM3
5.6g/s
0.0g/s.4x
2.8g/s
0.0g/s.4x
1.4g/s.2x
0.0g/s.4x
CM6
CM1
CM2
CM4
CM7
CM5
CM3
2
2
2
80l/hr
10l/hr
10l/hr
10l/hr
10l/hr
50l/hr
42Cooldown Flows (48-52hrs) Refill CM4
6.7g/s
0.0g/s.4x
2.8g/s.2x
0.0g/s.4x
0.0g/s.4x
1.7g/s0.8x
CM6
CM1
CM2
CM4
CM7
CM5
CM3
2
2
2
80l/hr
10l/hr
10l/hr
10l/hr
10l/hr
50l/hr
43Cooldown Flows (52-59hrs) Fill CM2
6.0g/s
0.0g/s.4x
0.0g/s.4x
0.0g/s.4x
0.0g/s.4x
1.4g/s.2x
2.8g/s
CM6
CM1
CM2
CM4
CM7
CM5
CM3
2
2
2
80l/hr
10l/hr
10l/hr
10l/hr
10l/hr
10l/hr
50l/hr
44Cooldown Flows (59-63hrs) Refill CM3
7.0g/s
0.0g/s.4x
1.7g/s0.7x
0.0g/s.4x
0.0g/s.4x
0.0g/s.4x
2.8g/s.2x
CM6
CM1
CM2
CM4
CM7
CM5
CM3
2
2
2
80l/hr
10l/hr
10l/hr
10l/hr
10l/hr
10l/hr
50l/hr
45Cooldown Flows (63-70hrs) Fill CM1
6.0g/s
0.0g/s.4x
1.4g/s.2x
0.0g/s.4x
0.0g/s.4x
0.0g/s.4x
0.0g/s.4x
2.8g/s
CM6
CM1
CM2
CM4
CM7
CM5
CM3
2
2
2
2
2
80l/hr
10l/hr
10l/hr
10l/hr
10l/hr
10l/hr
10l/hr
50l/hr
46Cooldown Flows (70-74hrs) Refill CM2
7.0g/s
0.0g/s.4x
0.0g/s.4x
0.0g/s.4x
0.0g/s.4x
1.7g/s0.7x
2.8g/s.2x
0.0g/s.4x
CM6
CM1
CM2
CM4
CM7
CM5
CM3
2
2
2
2
2
80l/hr
10l/hr
10l/hr
10l/hr
10l/hr
10l/hr
10l/hr
50l/hr
47Cooldown Flows (74-81hrs) Refill CM1
6.0g/s
0.0g/s.4x
0.0g/s.4x
0.0g/s.4x
0.0g/s.4x
1.4g/s0.2x
2.1g/s0.7x
0.0g/s.4x
CM6
CM1
CM2
CM4
CM7
CM5
CM3
2
2
2
2
2
10l/hr
10l/hr
10l/hr
10l/hr
10l/hr
80l/hr
10l/hr
50l/hr
48Cooldown Flows (81-86hrs) Refill CM7
3.9g/s
0.0g/s.4x
0.0g/s.4x
0.0g/s.4x
0.0g/s0.4x
1.7g/s0.2x
0.0g/s.4x
0.1g/s
CM6
CM1
CM4
CM7
CM5
CM3
CM2
2
2
2
2
2
10l/hr
10l/hr
100l/hr
10l/hr
10l/hr
10l/hr
10l/hr
1.0g/s0.9x
50l/hr
49Cooldown Flows (86-91hrs) Refill CM6
2.2g/s
0.0g/s.4x
0.0g/s.4x
0.0g/s.4x
0.0g/s0.4x
0.0g/s0.4x
0.1g/s
0.1g/s
CM6
CM1
CM4
CM7
CM5
CM3
CM2
2
3
2
2
2
10l/hr
20l/hr
10l/hr
10l/hr
100l/hr
10l/hr
10l/hr
0.8g/s0.4x
1.0g/s0.9x
50l/hr
50Cooldown Flows (91-96hrs) Refill CM5
2.0g/s
0.0g/s.4x
0.0g/s.4x
0.0g/s0.4x
0.0g/s0.4x
0.1g/s
0.1g/s
0.1g/s
CM6
CM1
CM4
CM7
CM5
CM3
CM2
2
3
3
2
2
10l/hr
30l/hr
10l/hr
80l/hr
20l/hr
10l/hr
10l/hr
0.8g/s0.3x
0.9g/s0.2x
1.0g/s0.8x
50l/hr
51Cooldown Flows (96-101hrs) Refill CM4
1.6g/s
0.0g/s.4x
0.0g/s0.4x
0.0g/s0.4x
0.1g/s
0.1g/s
0.1g/s
0.1g/s
CM6
CM1
CM4
CM7
CM5
CM3
CM2
2
3
3
3
2
10l/hr
30l/hr
80l/hr
20l/hr
30l/hr
10l/hr
10l/hr
0.8g/s0.3x
0.8g/s0.3x
1.0g/s0.8x
0.8g/s0.2x
50l/hr
52Cooldown Flows (101-106hrs) Refill CM3
1.3g/s
0.0g/s0.4x
0.0g/s0.4x
0.1g/s
0.1g/s
0.1g/s
0.1g/s
0.1g/s
CM6
CM1
CM4
CM7
CM5
CM3
CM2
3
3
3
3
2
10l/hr
40l/hr
20l/hr
20l/hr
30l/hr
10l/hr
80l/hr
0.8g/s0.4x
0.8g/s0.3x
1.0g/s0.8x
0.7g/s0.2x
0.8g/s0.2x
50l/hr
53Cooldown Flows (106-111hrs) Refill CM2
1.0g/s
0.0g/s0.4x
0.1g/s
0.1g/s
0.1g/s
0.1g/s
0.1g/s
0.1g/s
CM2
CM6
CM1
CM4
CM7
CM5
CM3
3
3
3
3
3
80l/hr
40l/hr
20l/hr
30l/hr
40l/hr
10l/hr
20l/hr
0.8g/s0.4x
0.8g/s0.4x
1.0g/s0.8x
0.7g/s0.3x
0.7g/s0.2x
0.8g/s0.2x
50l/hr
54Cooldown Flows (111-116hrs) Refill CM1
0.7g/s
0.1g/s
0.1g/s
0.1g/s
0.1g/s
0.1g/s
0.1g/s
0.1g/s
CM2
CM6
CM1
CM4
CM7
CM5
CM3
3
3
3
3
3
20l/hr
40l/hr
30l/hr
30l/hr
40l/hr
80l/hr
30l/hr
0.8g/s0.4x
0.8g/s0.4x
1.0g/s0.8x
0.7g/s0.3x
0.7g/s0.3x
0.7g/s0.3x
0.8g/s0.2x
50l/hr
55Cooldown Flows (116-121hrs) Fill and Regulate
Level
0.7g/s
0.1g/s
0.1g/s
0.1g/s
0.1g/s
0.1g/s
0.1g/s
0.1g/s
CM2
CM6
CM1
CM4
CM7
CM5
CM3
3
3
3
3
3
3
3
36l/hr
50l/hr
36l/hr
36l/hr
50l/hr
36l/hr
36l/hr
0.8g/s0.5x
0.8g/s0.5x
0.8g/s0.3x
0.7g/s0.3x
0.7g/s0.3x
0.7g/s0.3x
0.7g/s0.3x
50l/hr
56Cooldown Flows
57- Conclusion
- A 500W class refrigerator will be installed and
commissioned at ISAC-II before year end - Full commissioning of the cold distribution and
first stage of the accelerator will be completed
in 2005 - A second 500W class refrigerator will be
installed 2007