NSTX TF Joint Failure - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

NSTX TF Joint Failure

Description:

NSTX TF Joint Failure – PowerPoint PPT presentation

Number of Views:17
Avg rating:3.0/5.0
Slides: 17
Provided by: michaeld48
Learn more at: http://nstx.pppl.gov
Category:
Tags: nstx | failure | joint | moed

less

Transcript and Presenter's Notes

Title: NSTX TF Joint Failure


1
NSTX TF Joint Failure
  • OFES Presentation
  • March 14, 2003
  • Mike Williams

2
NSTX TF Joint Failure
  • What happened?
  • Why did the joint fail?
  • What is our plan?

3
February 14, 2003 Following our morning test
shots, the first plasma attempt of the day
resulted in a loud bang (heard on the control
room audio monitors) accompanied by a plume of
smoke (visible on the control room video
monitors).
Power Supply Current Waveforms
4
Several protective devices tripped TF power
supply fault detector section overcurrent, TF
Analog Coil Protection (ACP) overcurrent, TF
Rochester Instrument System (RIS) overcurrent,
TF ground fault current relay. The target level
for the TF during this shot was 53.4kA which
produces Bt4.5kG. The fault occurred just prior
to reaching flat top as the current passed the
50kA level.
5
Initial inspection revealed that one of the TF
flags had been displaced by about 1 inch.
TF Flags
6
The TF flags are used to connect the outer leg
turns (red) to the inner leg turns (copper
bundle).
Hub Assembly
Umbrella Structure
TF Flags
7
TF flag schematic
EM Load
Hub Assembly
TF Bundle
TF Flag
Preload (bolts)
Hub Assembly
Shim
Keenserttm
8
Subsequent inspection (including removal of the
TF bundle) revealed the extent of the damage.
9
What happened?
  • An open circuit fault (the flag joint opening up)
    led to turn-to-turn (inner and outer legs) and
    turn-to-ground faults (to the hub and umbrella
    assemblies) at or near the high-voltage terminals
    of the TF circuit.
  • This fault condition led to a spike of fault
    current from the power supply which shunted the
    coil inner/outer leg assembly.
  • Once the power supply tripped, the current spike
    decayed.
  • This was followed by an L/R decay of the coil
    current as the coil released its stored energy.
    (Although the L/R decay was not typical, it has
    been modeled by an arc across the open flag
    joint.)
  • The energy dissipated in the arc was of order
    1.4MJ.

10
Why did the joint fail?
  • Subsequent analysis has revealed that the present
    design was unable to maintain the required joint
    pressure
  • Bolts alone could not adequately withstand the
    additional electromagnetic load in addition to
    the initial preload,
  • Shims did not adequately transfer load to the hub
    assembly.

11
Prior to this run period, we were concerned about
these joints.
  • During the past outage (after two weeks of 6 kG
    operation) we identified systemic issues of
    loosened bolts, mushrooming copper around bolt
    holes and increased joint resistance.
  • We delayed completing the outage to address these
    concerns
  • Resurfaced flag faces, which were not perfectly
    aligned, and chamfered bolt holes (bottom),
  • Improved bolt washers and bolt retention (top and
    bottom),
  • Retorqued bolts (top and bottom) and replaced 4
    keensertstm with tap-loktm inserts
    (bottom),
  • Replaced G-10 flag shims with inflatable epoxy
    shim design (top and bottom).
  • We derated the TF and instituted an accelerated
    inspection program during maintenance weeks for
    the FY03 campaign.

12
After 3 run-weeks in FY03, we inspected the
joints.
  • Plan was to inspect 4-6 joints on the top of the
    machine plus the leaking coolant path (6A),
  • Found several loose bolts so we inspected (and
    retorqued when necessary) all of the upper
    joints,
  • Found one joint resistance out of spec and broke
    one Keenserttm while tightening bolt,
  • The new epoxy shims were tight,
  • The 6A coolant path was still leaking (as well as
    a smaller internal leak in 8A),
  • We planned to continue inspections during
    maintenance weeks while limiting operation to 4.5
    kG.
  • Design of a new TF bundle/flag joint was underway.

13
We have now accelerated the redesign effort.
  • We understand the weaknesses in the present
    design
  • We have analyzed the fault data and inspected the
    damaged components,
  • We have refined our models of the joint design
    and performed more analyses.

14
There are significant design issues
  • Maintaining contact on the joint face
  • Bolt design needs to accommodate preload as well
    as electromagnetic and thermal loads,
  • Design needs to accommodate shear on the joint
    face while minimizing electrical resistance.
  • Transferring the mechanical loads (via the hub
    assembly) to the torque collar
  • Shims were a weakness in current design.
  • Determine whether the current hub assembly/torque
    collar is adequate for the additional loads.
  • More robust cooling channel
  • New design will incorporate rigid, thicker-walled
    piping
  • Eliminate external bends.

15
We plan to complete our design activity in the
next few weeks.
  • Presently testing prototype joint design
    concepts,
  • Complete joint/bundle design by early-April,
  • Final Design Review (inviting participants from
    C-MOD, MAST, DIII-D, UW and FFOC) on April 10,
  • FDR will incorporate findings from Laboratory
    review committee.

16
We are developing a plan which should have us
back in operation this Fall.
  • Vacuum vessel pumpdown mid-June followed by
    bakeout,
  • Complete machine clean-up and preassembly testing
    by July,
  • Complete manufacture of new TF bundle by August
  • The bulk of the machining will be done by an
    outside vendor,
  • We plan to assemble the new TF bundle in-house,
  • Complete machine reassembly by October,
  • Begin power testing October 20,
  • Begin plasma operations November 3.
Write a Comment
User Comments (0)
About PowerShow.com