Title: Superfluid Helium Tank Status
1Superfluid Helium Tank Status
- Technical Interchange Meeting
- January 30 February 03, 2006
- Prepared by Dan Rybicki (281) 244-5181
- Presented by Trent Martin (281) 483-3296
2Sub Contract - Jacobs Sverdrup
- Carry-over contract was needed to complete tank
- Jacobs Sverdrup prime
- Sole source Hans Bieri Engineering, Winterthur,
CH - Contract signed November 23, 2005
- Firm Fixed Price type of contract
- 5 major work milestones identified to full
completion
3Sub Contract - Jacobs Sverdrup
- Meetings with Hans Bieri Engineering GmbH (HBE)
- in Winterthur in early December, mid-December,
and - late January
- Rybicki, Tutt, Martin and Porter
-
- HBE operation is well underway and nearly all
- sub components are in-house from vendors
4Super-Fluid Helium Tank
5Super-Fluid Helium Tank Weld Nomenclature
Miscellaneous port welds
Close out weld (central ring to upper
inner shell)
Thru-Tube to Inner shell weld
Nozzle to end cap weld
Central Ring to lower vessel half weld
(inner weld)
Close out weld (central ring to upper
outer shell)
Cryo valve port weld
Central Ring to lower vessel half weld
(outer weld)
6Super-Fluid Helium Tank - Weld Nomenclature
Tube end butt welds Serpentine HX
7Sub Component Status Thru-Tube Bodies
- 8 flight tubes complete and delivered in
November 8 nozzles - Final 8 flight tubes complete and delivered in
December 8 nozzles - 8 flight spares currently in fabrication
mid March delivery date
8Sub Component Status Outer Shells
- Upper outer shell complete and in-house at HBE
- Lower outer shell complete and in-house at HBE
9Sub Component Status Inner Shells
- Upper inner shell complete at HBE
- Lower inner shell complete at HBE
10Sub Component Status Shell Final Machining
- Precision grinding of inner shell wall thickness
11Sub Component Status Vessel End Caps
- All end caps (including spare) complete and
in-house at HBE - complete less nozzle holes cut
12Lower Half Assembly Status
- Lower Inner Shell welded to Lower End Cap
- Currently preparing Lower End Cap to weld Lower
Outer Shell
13Sub Component Status Central Ring
- Central Ring complete and in-house at HBE
- No finished spares available
14Sub Component Status Serpentine HX Tube
- Tube segments complete and in-house at HBE
- Welding procedure (tube end to tube end)
complete (pending review by Rybicki)
15Sub Component Integration Method Vessel Half
- Full scale mock up sections produced
- Nozzle to end cap and Thru-Tube to inner shell
holes practiced
16Sub Component Integration Method Vessel Half
- Thru-Tube hole alignment tooling developed and
checked out
17Sub Component Integration End Caps
- Mock up simulating nozzle to end cap welds
18Sub Component Integration End Caps
- Early development weld on full scale end cap
- Weld to be fully robotic applied
- Weld joint alignment accomplished with internal
back up tooling - tooling not shown
19Schedule
Date can be improved if Lower Half Integration
at SCL takes less than 12 weeks.