Entergy Mississippi, Inc. Proposed Transmission Reliability Projects - PowerPoint PPT Presentation

1 / 34
About This Presentation
Title:

Entergy Mississippi, Inc. Proposed Transmission Reliability Projects

Description:

Construct the Rankin to S. Jackson 230kV line. This will also allow for additional S. Jackson area load on the 115kV system to ... – PowerPoint PPT presentation

Number of Views:56
Avg rating:3.0/5.0
Slides: 35
Provided by: brian569
Category:

less

Transcript and Presenter's Notes

Title: Entergy Mississippi, Inc. Proposed Transmission Reliability Projects


1
Entergy Mississippi, Inc.Proposed Transmission
Reliability Projects
  • Entergy Transmission Planning Summit
  • New Orleans, LA
  • July 10, 2003

2
2004/2005 EMI Transmission Reliability Projects
Capacitor Banks 2004
Andrus-Greenville Upgrade Line Carryover 2003-04
Tillatoba Auto 2005-06
Livingston Rd. Ridgeland Convert to 230kV
2005-06
Rankin-S. Jackson New 230kV Line Carryover
2003-2005
Franklin-Brookhaven Upgrade Line 2004-05
Georgetown-Hazelhurst New Line 2005-06
Franklin Auto 2003-04 Carryover
Amite-Fernwood Upgrade Line 2005-06
3
Andrus to GreenvilleBuild New 115 kV Line
  • Scenario
  • The 115kV Gerald Andrus to Greenville loop is
    located in North Mississippi. It consists of
    two lines, 5.3 miles each. These lines serve the
    city of Greenville.
  • The single contingency loss of either side of the
    loop overloads the remaining section by 30.
  • Recommended Solution
  • To relieve the overloading condition described
    above, reconductor the existing, 954 ACSR
    conductors to 954 ACSS to obtain a line rating of
    359 MVA on the two lines from Gerald Andrus to
    Greenville. The new ACSS conductor provides a
    higher ampacity than a comparable size ACSR
    conductor due to its metallurgical properties.
    This will allow most of the existing structures
    to be re-used providing a lower cost solution
    than the original proposal to build a third line
    from Gerald Andrus to Greenville.
  • Estimated Cost 2,700,000

4
(No Transcript)
5
Franklin 500/115 kV SubstationAdd Second
500/115 kV Autotransformer
  • Scenario
  • Franklin substation has three single-phase
    autotransformers, 500 MVA total, 500/115kV with a
    single-phase spare in place.
  • Loss of one phase causes overloads on 115kV
    system and widespread undervoltages within the
    entire south Mississippi and north of Lake
    Pontchartrain area in ELIs service territory.
  • As an interim solution, an undervoltage loadshed
    scheme has been installed for the loss of the
    transformer.
  • Recommended Solution
  • Install a parallel three phase autotransformer
    with breakers relaying
  • Estimated Cost 8,800,000

6
(No Transcript)
7
Jackson Improvement Plan Phase IRankin to S.
Jackson Build New 230 kV Line
  • Scenario
  • The 115kV system serving the Jackson area is
    heavily loaded. Single contingencies in the North
    and South Jackson area will cause overloads as
    high as 33 on the 115kV transmission system. The
    solution is to shift load off of the 115 kV
    system to the 230 kV system by converting
    Livingston Rd. 115 kV and Ridgeland 115 kV to 230
    kV. The completion of the 230kV loop around
    Jackson will allow for shifting load to the 230
    kV system. The line is currently scheduled for
    an ISD of 2005. The Livingston Rd. and Ridgeland
    230 kV conversions are proposed to be in service
    in 2005 and 2006.
  • Recommended Solution
  • Construct the Rankin to S. Jackson 230kV line.
    This will also allow for additional S. Jackson
    area load on the 115kV system to be moved to the
    230kV system.
  • The proposed Rankin to S.Jackson 230kV line will
    be approximately 20 miles long.
  • Estimated Cost 10,200,000

8
(No Transcript)
9
Franklin to BrookhavenIncrease Line Capacity
  • Scenario
  • The Franklin to Brookhaven transmission path
    consist of two 115kV transmission lines. The
    Franklin to Brookhaven lines are critical sources
    into the south Mississippi area. It provides
    power from the 500kV system at Franklin. The
    north line ( Franklin-Vaughn-W.
    Brookhaven-Brookhaven) is constructed of 666
    ACSR.
  • The loss of the south line ( Franklin-Brookhaven
    S.-Brookhaven) will overload the north line by
    23. Load will have to be shed during the peak
    season to reduce the overload to 100. There are
    no operating procedures to mitigate this
    circumstance. This overload will increase when a
    second autotransformer is added to Franklin.
  • Recommended Solution
  • Upgrade the line from Franklin to Vaughn to West
    Brookhaven to Brookhaven (18.26 miles) with 1590
    ACSR. Upgrade all appropriate switches, bus work
    and other devices as necessary.
  • Estimated Cost 4,940,000

10
(No Transcript)
11
Jackson Improvement Plan Phase IIConvert
Livingston Road Ridgeland to 230 kV
  • Scenario
  • The 115kV line from Lakeover-NE Jackson-Rex Brown
    is 25 miles long.
  • The loss of the Lakeover - Livingston Rd. 115 kV,
    Livingston Rd. Ridgeland 115 kV, Rex Brown N.
    Jackson 115 kV or N. Jackson - Canton Rd. 115 kV
    in 2004 causes overloads on 4 lines by as much
    as 33. By 2007, 5 lines would overload by as
    much as 35.
  • Recommended Solution
  • Convert the Livingston Rd 115kV substation to
    230kV in 2005 and convert the Ridgeland 115kV
    Substation to 230kV in 2006 on the Lakeover to
    Luckney to Rankin 230kV line.
  • Estimated Cost 1,700,000

12
(No Transcript)
13
Tillatoba 230/115 kV SubstationAdd Second
230/115 kV Autotransformer
  • Scenario
  • Tillatoba substation has three single-phase
    autotransformers, 392 MVA total, 230/115kV with
    one single-phase spare in place.
  • The loss of the Tillatoba 230/115kV
    autotransformer causes low voltages and numerous
    overloads throughout the northern Mississippi
    area. This contingency causes 18 buses to fall
    below 92 voltage and 9 line overloads.
  • Recommended Solution
  • Install a parallel single-phase autotransformer
    with Breakers Relaying
  • Estimated Cost 4,800,000

14
(No Transcript)
15
Georgetown to HazelhurstBuild New 115 kV Line
  • Scenario
  • The SW Jackson to Byram to Brookhaven line is 53
    miles long with 234MWs of load.
  • The loss of SW Jackson - Elton 115 kV or Elton -
    Byram 115kV lines will overload the segments from
    Brookhaven to Hazlehurst by as much as 43 in
    2004. Voltages as low as 78 would be caused on
    16 buses from Terry to Brookhaven to McComb to
    Tylertown . By 2007, the voltages would decrease
    to as low as 62 on 29 buses, and the loss of
    Wesson - Brookhaven 115 kV or Wesson to James Rd.
    will cause overloads by 15 on SW Jackson - Elton
    - Byram 115kV line. This project will also delay
    the need to upgrade Ray Braswell West Jackson
    115 kV and Ray Braswell Forest Hill 115 kV
    lines.
  • Recommended Solution
  • Build a new 115kV line from Georgetown to
    Hazelhurst using 1272 conductor to obtain a line
    rating of 261 MVA.
  • Estimated Cost 9,300,000

16
(No Transcript)
17
Amite to FernwoodIncrease Line Capacity
  • Scenario
  • The Amite to Fernwood 115kV line, located in
    south Louisiana, north of Lake Pontchartrain,
    extending north into southern Mississippi is 32
    miles long. Amite is approximately 17 miles from
    the Mississippi state line and Fernwood is
    approximately 15 miles from the state line. This
    115kV line, constructed with 4/0 ACSR conductor,
    is part of the Amite to McComb tie between MPL
    and LPL.
  • Single contingencies in Mississippi of Brookhaven
    to Mallalieu, Mallalieu to Norfield, Norfield to
    McComb or Franklin Auto in 2004 will cause
    overloads up to 70 on the Amite-Kentwood-Colonial
    Pipeline-Fernwood line segments.
  • Recommended Solution
  • Reconductor the existing, 4/0 ACSR (68MVA)
    conductors to 1272 to obtain a line rating of 261
    MVA on the line from Amite to Fernwood line.
  • Estimated Total Cost 14.4M for ELI EMI
  • EMIs portion 7,000,000

18
(No Transcript)
19
2006 - 2008 EMI Planned Carryovers
Tillatoba Auto Carryover 2005-06
Livingston Rd. Ridgeland Convert to 230kV
Carryover 2005-06
Georgetown-Hazelhurst New Line Carryover 2004-06
Amite-Fernwood Upgrade Line Carryover 2005-06
20
2006 - 2008 EMI Transmission Reliability Projects
Capacitor Banks 2005-08
Tillatoba to S. Grenada Build New Line 2007-08
Hollandale 230/115 kV Auto 2006-07
Ray Braswell Add Second 500/230kV Auto 2006-2007
Franklin to Brookhaven S. to Brookhaven Upgrade
Line 2007-08
21
Ray BraswellAdd Second 500/230 kV
Autotransformer
  • Scenario
  • Ray Braswell has one 560 MVA, 500/230kV
    autotransformer and one 560MVA, 500/115kV
    autotransformer.
  • The loss of the Ray Braswell to Lakeover 500kV
    line will overload both the Ray Braswell
    500/230kV and the Ray Braswell 500/115 kV
    autotransformers by 11 in 2007.
  • Recommended Solution
  • Install a parallel 560MVA 500/230MVA
    autotransformer with breakers relaying at Ray
    Braswell.
  • Estimated Cost 15,000,000

22
(No Transcript)
23
Franklin to Brookhaven South to
BrookhavenIncrease Line Capacity
  • Scenario
  • The Franklin to Brookhaven transmission path
    consists of two 115kV transmission lines. The
    Franklin to Brookhaven lines are a critical
    source into the south Mississippi area. It
    provides power from the 500kV system at Franklin.
    The south line ( Franklin - Brookhaven S. -
    Brookhaven) is constructed of 954 ACSR conductor.
  • With the addition of a parallel 500/115
    autotransformer at Franklin, the loss of the
    north line (Franklin to Vaughn to Brookhaven)
    will overload the south line by 13 in 2007.
    Load will have to be shed during the peak season
    to reduce the loading on the line to 100. There
    are no operating procedures to mitigate this
    circumstance.
  • Recommended Solution
  • Upgrade the line from Franklin to Brookhaven S.
    to Brookhaven with 1780 ACSR. Upgrade all
    appropriate switches, bus work and other devices
    as necessary.
  • Estimated Cost 5,000,000

24
(No Transcript)
25
Hollandale SubstationInstall 230/115 kV
Autotransformer
  • Scenario
  • The Greenville to Hollandale 115kV line, located
    in northwest Mississippi, is 23.5 miles long and
    the Hollandale to North Vicksburg 115kV line is
    59 miles long.
  • The loss of any section of line from Greenville
    to Hollandale will cause all the line sections
    from Vicksburg to Hollandale to overload by as
    much as 61 in 2007. This will also cause
    voltages as low as 51 from Redwood to
    Hollandale.
  • Recommended Solution
  • Connect Gerald Andrus - Ray Braswell 230 kV line
    into Hollandale and install a 230/115kV
    autotransformer. Before the transformer is
    installed, the Hollandale Greenville TCEPA SS
    S.E. Greenville 115 kV line must be upgraded to
    1272 ACSR (20 miles long).
  • Estimated Cost 12,000,000 (Includes line
    upgrade)

26
(No Transcript)
27
Tillatoba to South GrenadaBuild New 115 kV Line
  • Scenario
  • The 115kV line from Tillatoba to S. Grenada is 19
    miles long and part of a 43-mile line to Winona.
  • The loss of the Tillatoba to Grenada line in 2004
    causes voltages as low as 81 on five buses, and
    overloads on three lines by as much as 34. In
    2007, there are 11 buses with voltages between
    92 to 62, and overloads on 7 115kV lines by 7
    to 93.
  • Recommended Solution
  • Build a single separate line from Tillatoba to S.
    Grenada with 1272 ACSR (or equivalent conductor).
    The line should be built for 230kV and operated
    at 115kV.
  • Estimated Cost 6,000,000

28
(No Transcript)
29
2009-2013 EMI Transmission Reliability Target
Areas
Batesville to Getwell Build 230kV line
Jackson 230kV Improvement Plan
Natchez Area
Franklin to McComb Build New 115kV line
30
(No Transcript)
31
(No Transcript)
32
(No Transcript)
33
(No Transcript)
34
  • Questions
Write a Comment
User Comments (0)
About PowerShow.com