Title: LADOTD CONSTRUCTION COST ESTIMATING
1LADOTD CONSTRUCTIONCOST ESTIMATING
Charles Nickel, P.E. Cost Estimate Value
Engineering Director
Office (225) 379-1078 E-mail
Charles.Nickel_at_la.gov
2Cost Estimating Process
- GOAL
- To provide guidance in developing and
maintaining accurate, consistent, and reliable
project cost estimates.
3Project Management Body of Knowledge (PMBOK)
- Cost Management Involves 3 Processes
- Cost Estimating
- Cost Budgeting
- Cost Control
4Project Management Body of Knowledge (PMBOK)
- Cost Management Involves 3 Processes
- Cost Estimating
- Cost Budgeting
- Cost Control
5Cost Estimating Process
- Types of Project Cost Estimates
- 1.) Engineering
- 2.) Construction
- 3.) Right-of-Way
- 4.) Utilities
- 5.) Mitigation (Permits, Approvals, etc.)
6Cost Estimating Process
- Types of Project Cost Estimates
- 1.) Engineering
- 2.) Construction
- 3.) Right-of-Way
- 4.) Utilities
- 5.) Mitigation (Permits, Approvals, etc.)
7Cost Estimating Process
- Some common methods of Cost Estimating
- Historical Bid Based
- Cost Based
- Parametric
- Risk Based
8Cost Estimating Process
- Some common methods of Cost Estimating
- Historical Bid Based
- Cost Based
- Parametric
- Risk Based
9Historical Bid Based Estimating
- Uses previous bid data as a basis for cost
estimating. - Items with little or no bid history are much more
difficult to estimate with this method, if not
impossible.
10Historical Bid Based Estimating
- Long Range Estimates
- Detailed Estimates
11Historical Bid BasedLong Range Estimating
Estimating UsingMajor Item Cost Groups
12Historical Bid BasedLong Range Estimating
Cost groups are based on line items classified
into major item categories such as
- Asphalt
- Base
- Concrete
- Drainage
- Earthwork
- Erosion Control
- Gates Fences
- Guiderail
- Landscaping
- Mobilization
- Pavement marking
- etc.
13Historical Bid BasedLong Range Estimating
Item Group Cost XX Project Cost Project Cost
Item Group Cost / XX
14Historical Bid BasedLong Range Estimating
For example, for a particular type of roadway
project, historically Asphalt Items 58 of
Project Cost Base Items 12 of Project
Cost Mobilization 10 of Project Cost Other
Items 20 of Project Cost
15Historical Bid BasedLong Range Estimating
Item Group Cost Quantity Unit Price
16Historical Bid BasedLong Range Estimating
- Quantities for cost groups can be estimated based
on early project measurements such as - Length of roadway
- Width of roadway
- Depth of pavement
- Number of intersections
- Etc.
17Historical Bid BasedLong Range Estimating
Once the quantities are estimated, Unit Prices
can be determined based on historical bid data.
18Historical Bid BasedLong Range Estimating
Estimate of Asphalt Group 1.5 M Estimate of
Base Group 1.2 M 2.7 M 2.7 M / (58
12) 3.8 M Construction Cost 3.8 M
contingencies
19Detailed Estimates
20Historical Bid BasedDetail Estimating
Involves past item level relationships between
the unit price and other measurable parameters of
the item such as
- Quantity
- Letting Date
- Number of Bidders
- Location
- Size
- Type of Work
21Historical Bid BasedDetail Estimating
- Modeling Unit Price relationships
- Simple Linear Regressions
- Not so Simple Linear Regressions
22Historical Bid BasedDetail Estimating
- Simple Linear Regression Models
- For example
- Unit Price b0 b1 (Bid Date)
- Log(Unit Price) b0 b1 Log(Quantity)
23(No Transcript)
24(No Transcript)
25(No Transcript)
26(No Transcript)
27(No Transcript)
28(No Transcript)
29(No Transcript)
30(No Transcript)
31(No Transcript)
32Historical Bid BasedDetail Estimating
- More Complex Linear Regression Models
- For example
- Log(Unit Price)
- b0 b1 Log(Quantity) b2 (Bid Date)
33(No Transcript)
34Historical Bid BasedDetail Estimating
Adjust the bid points to reflect only one
relationship at a time.
35(No Transcript)
36(No Transcript)
37(No Transcript)
38(No Transcript)
39(No Transcript)
40Historical Bid BasedDetail Estimating
- The more relationships that can be identified and
modeled, the closer the adjusted bid points will
be to the trend lines. - The amount of time and resources spent
identifying and modeling these relationships will
determine the level of accuracy achievable.
41(No Transcript)
42Estimating Tools
- Excel Spreadsheets
- Access Database Applications
- Trnsport CES
- All these tools rely on the EXPERIENCE of the
ESTIMATOR to use them wisely to develop the
Construction Cost Estimate.