Title: Trevor Buggins MAS Project
1Trevor BugginsMAS Project
Operational Leadership Business Benefits/Personal
Benefits
2Content
- Project brief
- Approach to project
- Process
- Improvement
- Outcomes
3OPERATIONAL LEADERSHIP PROJECT
Company
Project Title
Project Sponsor
Project Leader
- Outputs/Deliverables (What When)
- Specific description/list of what I need to
manage/do and by when, to ensure project success. - Machining plan matched to capacity capability
- Greater interaction Production v Customer
Services -
- Visibility of plan/workflow
- Defined process, with schedule of activities.
Purpose Statement What is the current
situation/problem. ? (Use specific facts
/measures if possible) What would happen if
project not completed? To improve the
consistency of output for Bipolar implant product
range ,
Benefits (Why) Why solve the problem / improve
the situation? What does success look like - 2/3
measurable results expected. Reduction in
manufacturing lead-time (50) On time
completion of w/o to be improved (gt70). Achieve
daily flow of work through successive
processes. Stock reduction
4(No Transcript)
5Current State Map
6Key issues
- Poor lead-time
- Large raw material stock (buffer stock because
of suppliers) - No product flow
- Late customer deliveries (Japan 66)
7Future State Map
8Bipolar Cell
9Outcomes
- Introduce Bipolar cell
- Introduce flow tools within the new process
- 28 weeks reduced to 6 saving 170k
- Improvement in customer delivery
10Personal benefits
- Key tools
- Plan, Do, Check and Action
- Behaviour change
- Self
- Others
- Learned how to implement!
11Summary
- OL course has enabled me to
- Reflect where I am currently,
- Identify the areas I need to address for myself,
- Discuss the tools with my supervisory team
-
-