Staffing - PowerPoint PPT Presentation

1 / 7
About This Presentation
Title:

Staffing

Description:

... levels of Civil Service staffing, especially in Engineering and Mission Assurance) ... Systems Engineer not assigned to EO-1 Project until mid-1997. NMP / EO-1 ... – PowerPoint PPT presentation

Number of Views:31
Avg rating:3.0/5.0
Slides: 8
Provided by: timk1
Category:

less

Transcript and Presenter's Notes

Title: Staffing


1
Section 6 Staffing and Experience
. . . Timothy A. Klein New Millennium Program
Business Manager
2
Staffing and Experience - History
  • EO-1 approved in March 1996 with only the ALI
    Instrument
  • MIT/LL and subcontractor team well-experienced in
    instrument systems development and spectroscopy
  • Swales/Litton spacecraft team selected through
    in-house Engineering Directorate contract strong
    subsystem experience, but first time building and
    integrating a complete spacecraft
  • Complement of Eight NMP Technologies Selected
    Through NMP Process in July 1996
  • Technologies at different stages of maturation
  • Varying degrees of expertise amongst the
    technology provider teams
  • Early definition specifically noted three
    technologies which needed to be stretched to
    meet technology validation goals (WARP, GPS and
    Precision Pointing)

3
Staffing and Experience - Management
  • Despite clear technology challenges, EO-1 was
    originally envisioned as a light touch mission
  • Management approach comparable to a small science
    mission
  • Emphasis on instruments, not on spacecraft or
    ground systems
  • Technologies viewed as payload, not as integral
    components
  • Light touch relative to contractor
    insight/oversight (with resulting initial low
    levels of Civil Service staffing, especially in
    Engineering and Mission Assurance)
  • Systems Management and Risk Management limited by
    low staffing and availability of experienced
    personnel
  • Risk management well beyond what we thought in
    the beginning
  • Systems Engineer not assigned to EO-1 Project
    until mid-1997

4
Staffing and Experience - Technologies
  • Technologies specifically required more staffing
    than originally thought
  • Found we needed to be ready to assist contractors
    with science, engineering and management to help
    them meet cost, schedule and technical targets
  • Much more technical staffing than we originally
    thought required to stay on top of technologies
  • Found it difficult to obtain the needed
    experienced engineers to assist with advanced
    technologies
  • Best move EO-1 made creating the Mission
    Technologist position

5
Staffing and Experience - Changes
  • Hyperion Instrument Added December 1998
  • TRW and subcontractor team well-experienced in
    instrument systems development and spectroscopy
  • Additional instrument requirements in turn
    required additional staffing across all mission
    elements
  • Ground System and Flight Software
  • Ongoing additional requirements laid against
    original ground system architecture has driven
    FOT and other staffing
  • Need for flight software maintenance has also
    increased staffing levels above original plan
  • EO-1 met the challenge of these and other changes

6
Staffing - IT Augmentation
  • Became clear as EO-1 was moving through IT that
    staffing was insufficient for work remaining to
    meet the 12/15/99 LRD
  • GSFC management worked with Swales/Litton team
    and other GSFC contractors to sharply increase
    staffing in August 1999
  • Augmenting IT staffing late in the project did
    not enable completion of the work on schedule or
    correction of discovered deficiencies
  • Upside additional deficiencies and gaps,
    especially in flight software and ground
    processing, were identified. Able to take many
    risk mitigating activities and add key
    experienced personnel
  • Resulted in an outstanding Thermal/Vacuum (T/V)
    test and a more robust system
  • We now have the experienced core team to take us
    through the remainder of IT, launch campaign and
    early operations

7
Staffing and Experience - FTE History
Write a Comment
User Comments (0)
About PowerShow.com