Title: Making Oil And Gas UpstreamMidstream Investment Decisions
1Making Oil And Gas Upstream/Midstream Investment
Decisions
Presentation To Senate Resources
Committee Legislative Budget Audit
Committee Hearings Alaska Natural Gas Pipeline
Issues
- Presentation By
- Ken Thompson, President CEO
- Pacific Star Energy LLC
2Agenda
- Importance of capital budgeting and allocation in
a corporation to decide what projects to approve - Framework of the capital budgeting process
- Capital projects portfolio
- Investment criteria
- Sensitivity
- Risks and risk mitigation
- Commercial vs. competitive rates-of-return
- Conclusions
3My Experience With Capital Portfolio Budgeting
Decisions
- Currently a Director on Board of Directors,
Alaska Air Group, and has helped set and approved
capital portfolio guidelines - Currently a Director on BOD, Coeur dAlene Mines
Corporation and has helped set and approved
capital portfolio guidelines - Was an Executive VP of ARCO in L.A. (1998-2000)
and sat in on ARCO BOD meetings helped set and
solicited approval of capital portfolio
guidelines and mix of projects in the portfolio - Past President of ARCO Alaska, Inc. (1994-98) and
argued the case for Alaska project requests to be
included in ARCOs approved capital portfolio - Past Manager of ARCO Corporate Planning to review
and solicit approval for upstream, midstream and
downstream investments
4The Importance Of Capital Budgeting And
Allocation
- One of the most significant financial activities
of a firm - Determines the core activities of the firm over
a long term future - Confirms which projects receive capital to
proceed timely and which projects do not receive
capital - Not all projects that are commercial or even
competitive are approved internally when capital
is constrained - Capital constraints force an allocation process
that selects a project mix that maximizes
shareholder wealth - Decisions must be made carefully and rationally
with owners, i.e. shareholders, in mind
5How Capital Budgeting Fits Into The Financial
Planning Of A Corporation
6Broad Framework For Capital Budgeting
- Identify company strategy overall and how the
strategy works to maximize shareholder wealth - Establish system for evaluating projects,
preparing capital allocation requests consistent
with strategy - Idea phase
- Preliminary evaluation phase
- Business evaluation phase
- Go-ahead or reject phase
- To be approved, a project must pass all these
phases - Develop a culture consistent with the strategy
and the capital evaluation system
7Capital Projects Portfolio
- Safety or environmental project outlays required
by law or company policy - Maintenance or cost reduction projects
- Expansion in existing businesses Major Oil
Co. Capital - Upstream Exploration (10 of
capital) - Upstream Development and production
(50-60 of capital) - Midstream Pipelines, natural gas processing
(10 of capital) - Downstream Oil refining and retail marketing
(20 of capital) - Chemical manufacturing
(10 of capital) - Investment for new products or ventures
- Discretionary or non-discretionary
8Decision Criteria For A Capital Project To Even
Be Considered For The Portfolio
- Internal rate-of-return (IRR)
- Commercial, i.e. exceed cost of capital plus
premium (e.g. 12) - Competitive, i.e. create the best mix of future
cash flows when multiple projects can be selected
from (e.g., 15) - Discounted cash flow net present value (NPV)
- Payback period
- Profitability index
- Sensitivity analysis
- Risk assessment
- Discretionary or non-discretionary
9Decision Criteria Definitions
- Net present value (NPV) indicates the expected
impact of the project on the value of the firm.
The NPV is the present value of all expected cash
flows including the investment dollars both
positive and negative cash flows are considered.
A discount rate is chosen to get discounted net
present value. The NPV decision rule specifies
that all independent projects with a positive NPV
should be accepted. When choosing among mutually
exclusive projects and when capital is
constrained, the projects with the largest
positive NPV combination should be selected. - Internal rate-of-return (IRR) is the discount
rate at which the net present value (NPV) of a
project equals zero. The IRR decision rule
specifies that all independent projects with an
IRR greater than the cost of capital should be
accepted when there are no capital constraints.
When choosing mutually exclusive projects and
when capital is constrained, the projects with
the highest IRRs should be selected. - Payback period represents the amount of time it
takes for a project to recover its initial cost.
The payback period decision rule specifies that
all independent projects with a payback period
less than a specified number of years should be
accepted. When choosing among mutually exclusive
projects and during certain times of tight
capital constraint, the projects with the
quickest paybacks are preferred. - Profitability index (PI) is the ratio of the
present value of change in operating cash inflows
to the present value of investment cash outflows.
A project that increases owners wealth has a PI
greater than one. If PI is less than 1, a
project should be rejected.
10Example Portfolio No Capital Constraints
-
- Cash Flows
- _______Millions of Dollars________
NPV at 12 - Project Inv. C1 C2 C3 C4
C5 _Millions of Dollars _IRR, - A -50 30 20 10 8
5 8
21 - B -50 5 20 20 20
10 3
14 - C -30 5 15 20 5
2 5
19 - -130
- The firm has had a phenomenal year with oil
prices above 40/bbl and has no capital
constraints. Which projects should be approved?
Answer all of them because all have positive NPV
at 12, all have a good IRR, and the company can
afford 130MM capital.
11Example Portfolio Capital Constraints
- Cash Flows
- _______Millions of Dollars________
NPV at 12 - Project Inv. C1 C2 C3 C4
C5 _Millions of Dollars _IRR, - A -50 30 20 10 8
5 8
21 - B -50 5 20 20 20
10 3
14 - C -30 5 15 20 5
2 5
19 - -130 but company budget now
constrained to only 80MM in capital - The firm has seen oil prices fall to 30/bbl and
has instituted a capital constraint of 80MM/year
capital. Which projects should be approved?
Answer You would do Projects A and C for a
combined 80MM investment as those two have the
best IRRs and the best NPV combined total of
13MM versus the combined NPV of 11MM for
Projects A and B. - Dilemma Project B is still commercial with a
positive NPV and acceptable IRR but cannot be
funded due to the investment portfolio capital
constraint of 80MM. Selection of A and C has a
higher combined NPV, thus maximizing shareholder
wealth for the fixed amount of capital to invest.
Project B is not competitive enough to add to
the portfolio and will be re-considered in future
years.
12Discretionary Versus Non-Discretionary Projects
13How Does The Gas Pipeline Project Equity Capital
Fit In Majors Capital Portfolios?
- Project is 18-20B to Chicago there will be
project financing of 70 of this amount, or 14B
debt secured by the line assets equity capital
needed is 6B - Assuming 6B equity that is needed, and assuming
ownership of 1/3-1/3-1/3, BP,CP and EM would each
need to allocate 2B in their capital portfolio - The project will be constructed over 4 years, so
the equity capital needed each year from each
company is 0.5B when the project carries the
debt -
- Capital Equity Capital Of
If - Spending Needed For Line
Annual 100 2003 - __Company 2003, B Per Year,
B Budget Equity
ROCE, - ExxonMobil 15.5 0.5
3.3 1.67B/11
18 - BP 12.4
0.5 4.0 1.67B/14
16 - ConocoPhillips 6.2
0.5 8.1 1.67B/27
16 - Totals 34.1
1.5 4.0 5.0B/15 17 -
(Times 4 years 6.0B equity - Debt will be 14.0B)
14What About The Level Of Debt For The Alaska Gas
Pipeline?
- Project is 18-20B to Chicago there will be
project financing of 70 of this amount, or 14B
debt secured by the line assets equity capital
needed is 6B - Assuming 14B debt that is needed, and assuming
ownership of 1/3-1/3-1/3, BP,CP and EM would each
need to assess impact of 4.67B in debt -
- Debt Debt/
Debt 2003
At Year-end Equity Needed For Line
Net - __Company 2003, B Ratio
B_____ Income, B
- ExxonMobil 9.8
0.105 4.7
21.5 - BP 19.9
0.273 4.7
10.3 - ConocoPhillips 15.6
0.413 4.7
4.6 - Totals 45.3
14.1 36.4 -
-
15Sensitivity Analysis
- Low-side oil and gas price cases
- Some oil companies test all projects at 20/bbl
or 3.50/MCF and must meet hurdle criteria at
low-side pricing - Different mix of projects within the capital
budgeting portfolio - Effect upon cash flows
- Effect upon total company value
- Effect upon debt/equity mix
- Best cash flow and earnings profile
- Shareholder wealth
- Final portfolio decided by executive management
and BOD
16Risk Assessment
- Forecasting risks
- Production
- Costs
- Taxes
- Other
- Exploration geologic risks
- Political risks
- Permitting risks
- Capital cost prediction risks
- Non-recourse project financing and debt
assumptions - Effect on supply/demand balance and pricing risk
- Projects must be resilient to risks
17Risk Mitigation
- Sufficient front-end engineering and assessment
- Right technologies or new technologies
- Tighter control of capital and operating costs
- Government assurances and/or incentives
- Permitting
- Loan guarantees to allow better project financing
interest rates - Tax credits
- Low-side price risk protection
- Contract risk sharing mechanisms
- Taking on partners to spread the risks
- Different companies have different investment
hurdle rate criteria and could be considered as
partners
18Commercial Versus Competitive IRRs
- Commercial
- IRR exceeds the cost of capital
- Competitive
- IRR and other criteria exceed the hurdle that
creates the best mix of projects worldwide that
maximizes shareholder wealth - Comparison of performance between states and
countries and between competitor companies - Project IRRs may be commercial but not be
competitive - Corporations differ in IRR hurdle rates
- Financial performance
- Capital structure
- Segment of business and its available returns for
projects -
19Conclusions
- Getting the Alaska Gas Pipeline Project into
major oil companies approved capital portfolios
is challenging - The project may be commercial but is not
competitive - The project is discretionary vs.
non-discretionary so has to meet tougher criteria
than some projects - Investors who desire a commercial
rate-of-return are important to consider as
investment partners, sponsors - Multiple partners can mitigate risk on any one
firm - Government assurances of fiscal certainty and/or
incentives can greatly reduce risks and ensure
the project is competitive - Sharing of risks by government is essential,
including debt guarantees, low interest rate bond
financing, low-price protection - Local ownership adds incremental valuea possible
key to bridging the gap between commercial
and competitive
20Sources And Exciting Reading
- Richard A. Brealey (London Business School) and
Stewart C. Myers (MIT Sloan School of
Management), Principles Of Corporate Finance,
New York McGraw-Hill, Inc., 1991. - Don Dayananda, Steve Harrison, Patrick Rowland,
John Herbohn, and Ricard Irons, Capital
Budgeting Financial Appraisal Of Investment
Projects, Cambridge, England, UK Cambridge
University Press, 2002. - John Graham and Campbell Harvey (Duke
University), Article How Do CFOs Make Capital
Budgeting And Capital Structure Decisions?, New
York Journal of Applied Corporate Finance, 2001. - John A. Boquist, Todd T. Milbourn and Anjan V.
Thakor, Article How Do You Win The Capital
Allocation Game?, Cambridge, MA MIT Sloan
School of Management, 1998. - Bill Young, Article BP Amoco Policy Statement
On The Use Of Project Finance, Waterton, MA
Harvard Business School Publishing, 2003. - Pamela Peterson, Internet Article Capital
Budgeting Techniques, http//garnet.acns.fsu.edu,
2004. - Rick Mathis, Internet Article Corporate Finance
Live, www.prenhall.com, 2004. - Corporate Annual Reports, Analyst Presentations,
and press releases for various companies.