Title: Third Workstream meeting re Baseline Reconsultation and Substitution
1Third Workstream meeting re Baseline
Re-consultation and Substitution
2Recap of previous two workstream meetings (1)
- Outlined the basis for Ofgems TPCR baselines
- National Grid provided network analysis following
Ofgems prescribed methodology - Based on 2008 network, average of three TBE
scenarios (Auctions , Transit UK and Global LNG)
using supply substitution - Using least favourable node as supply balance
- TPCR baselines were set based on
- Baseflow under each scenario as starting point,
then split remaining unallocated entry capacity
on 10YS forecast flows for 2008
3Recap of previous two workstream meetings (2)
- Resulted in aggregate baselines of 8814 GWh/d
- Discussed alternative methods for splitting the
unallocated capacity within Ofgems spreadsheet - National Grid asked for input from workstream
members, in particular on - Views on re-cutting of the cake (i.e. aggregate
the same, i.e. 8814 GWh/d) - Vs setting higher baselines (aggregate greater)
4Summary of responses
5Where do we go from here?
- No real consensus view from the industry
- No particular comments on a methodology to apply
- Consider the two alternative approaches
- re-cutting of the cake (i.e. aggregate the
same, i.e. 8814 GWh/d) - Vs setting higher baselines (aggregate greater)
6Re-cutting the cake how do you allocate the
8814 GWh/d? (1)
- Start with current level of capacity obligations
(take maximum booked for April 2008 onwards from
August 2007 report on website) (8210 GWh/d) - Take off the Incremental Obligated (IO) which has
been sold in Sept 2006 QSEC auction (1310 GWh/d) - This leads to 6900 GWh/d having been allocated
- If previously sold out at an ASEP, add back 20
previously reserved for S-T (based on old TPCR
baseline) - This affects Cheshire, Easington, Hornsea and
Isle of Grain (359 GWh/d) - This leads to 7259 GWh/d which would be allocated
- this then leaves 1554 GWh/d of entry capacity
unallocated
7How do you allocate the 1554 GWh/d?
- Believe need to take account of physical
capability - New baselines should be constrained to not exceed
previous obligations - Needs to be broadly commensurate with the
buy-back target - Therefore, based on the above, need to preserve
the zonal limits - Applied above logic and used four different ways
of splitting the 1554 GWh/d - On existing obligated level
- 2005 TYS
- 2006 TYS
- Max flow seen over 2 winters, 2005/6 and 2006/7.
8Possible sets of baselines (1)
Obligated Allocation based on sold 20 old TPCR
baseline where sold out
9Re-cutting the cake how do you allocate the
8814 GWh/d? (2)
- Start with the current level of capacity
obligations (take maximum booked for April 2008
onwards from August 2007 report on website less
Incremental Obligated) (6900 GWh/d) - Add back 20 previously reserved for S-T (based
on old TPCR baseline) at all ASEPs (but cap
resultant figure at the old TPCR baseline) - This leads to 8400 GWh/d being allocated
- this then leaves 414 GWh/d of entry capacity
unallocated
10Possible sets of baselines (2)
11Zonal analysis of possible baselines (2)
12Re-cutting the cake how do you allocate the
8814 GWh/d? (3)
- Alternative starting position - could use
historical flow over the last two winters
(subject to the old TPCR baseline) - Then adjust for the current level of capacity
obligations - This leads to 7802 GWh/d being allocated
- this then leaves 1012 GWh/d of entry capacity
unallocated
13Alternative re-cutting of cake possible
baselines (3)
14Zonal analysis of possible baselines (3)
15Alternative of higher baselines Capex
requirement
- Can Use the TPCR agreed revenue drivers as proxy
for capital expenditure - If baselines increased back to pre 2007 TPCR
levels - Around 275m extra capex needed to provide the
increased baselines
16Alternative of higher baselines Buyback
modelling
- Alternatively, can examine the incremental
buyback risk. Preliminary results indicate that - Just at Teesside, increasing the baseline back up
to 70 mscm/d could lead to around 90m
incremental buyback risk (mean level of 20m) per
year (assuming that the incremental flow at
Teesside is off-set by reduction of flow at
Milford Haven) - Similar level of risk at Barrow of increasing
baseline back to 66 mscm/d
17Summary
- Discussed how baselines were set
- Presented feedback received from industry
- Proposed alternative ways of cutting the cake
- Demonstrated that going back to higher baselines
means either - significant capex needed
- or that buy-back risk is likely to be high
- Will provide a summary report to Ofgem in the
next two weeks - Ofgem to commence their consultation