Third Workstream meeting re Baseline Reconsultation and Substitution - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

Third Workstream meeting re Baseline Reconsultation and Substitution

Description:

Take off the Incremental Obligated (IO) which has been sold in Sept 2006 QSEC ... Demonstrated that going back to higher baselines means either: significant ... – PowerPoint PPT presentation

Number of Views:221
Avg rating:3.0/5.0
Slides: 18
Provided by: elainec7
Category:

less

Transcript and Presenter's Notes

Title: Third Workstream meeting re Baseline Reconsultation and Substitution


1
Third Workstream meeting re Baseline
Re-consultation and Substitution
  • 12 September 2007

2
Recap of previous two workstream meetings (1)
  • Outlined the basis for Ofgems TPCR baselines
  • National Grid provided network analysis following
    Ofgems prescribed methodology
  • Based on 2008 network, average of three TBE
    scenarios (Auctions , Transit UK and Global LNG)
    using supply substitution
  • Using least favourable node as supply balance
  • TPCR baselines were set based on
  • Baseflow under each scenario as starting point,
    then split remaining unallocated entry capacity
    on 10YS forecast flows for 2008

3
Recap of previous two workstream meetings (2)
  • Resulted in aggregate baselines of 8814 GWh/d
  • Discussed alternative methods for splitting the
    unallocated capacity within Ofgems spreadsheet
  • National Grid asked for input from workstream
    members, in particular on
  • Views on re-cutting of the cake (i.e. aggregate
    the same, i.e. 8814 GWh/d)
  • Vs setting higher baselines (aggregate greater)

4
Summary of responses
5
Where do we go from here?
  • No real consensus view from the industry
  • No particular comments on a methodology to apply
  • Consider the two alternative approaches
  • re-cutting of the cake (i.e. aggregate the
    same, i.e. 8814 GWh/d)
  • Vs setting higher baselines (aggregate greater)

6
Re-cutting the cake how do you allocate the
8814 GWh/d? (1)
  • Start with current level of capacity obligations
    (take maximum booked for April 2008 onwards from
    August 2007 report on website) (8210 GWh/d)
  • Take off the Incremental Obligated (IO) which has
    been sold in Sept 2006 QSEC auction (1310 GWh/d)
  • This leads to 6900 GWh/d having been allocated
  • If previously sold out at an ASEP, add back 20
    previously reserved for S-T (based on old TPCR
    baseline)
  • This affects Cheshire, Easington, Hornsea and
    Isle of Grain (359 GWh/d)
  • This leads to 7259 GWh/d which would be allocated
  • this then leaves 1554 GWh/d of entry capacity
    unallocated

7
How do you allocate the 1554 GWh/d?
  • Believe need to take account of physical
    capability
  • New baselines should be constrained to not exceed
    previous obligations
  • Needs to be broadly commensurate with the
    buy-back target
  • Therefore, based on the above, need to preserve
    the zonal limits
  • Applied above logic and used four different ways
    of splitting the 1554 GWh/d
  • On existing obligated level
  • 2005 TYS
  • 2006 TYS
  • Max flow seen over 2 winters, 2005/6 and 2006/7.

8
Possible sets of baselines (1)
Obligated Allocation based on sold 20 old TPCR
baseline where sold out
9
Re-cutting the cake how do you allocate the
8814 GWh/d? (2)
  • Start with the current level of capacity
    obligations (take maximum booked for April 2008
    onwards from August 2007 report on website less
    Incremental Obligated) (6900 GWh/d)
  • Add back 20 previously reserved for S-T (based
    on old TPCR baseline) at all ASEPs (but cap
    resultant figure at the old TPCR baseline)
  • This leads to 8400 GWh/d being allocated
  • this then leaves 414 GWh/d of entry capacity
    unallocated

10
Possible sets of baselines (2)
11
Zonal analysis of possible baselines (2)
12
Re-cutting the cake how do you allocate the
8814 GWh/d? (3)
  • Alternative starting position - could use
    historical flow over the last two winters
    (subject to the old TPCR baseline)
  • Then adjust for the current level of capacity
    obligations
  • This leads to 7802 GWh/d being allocated
  • this then leaves 1012 GWh/d of entry capacity
    unallocated

13
Alternative re-cutting of cake possible
baselines (3)
14
Zonal analysis of possible baselines (3)
15
Alternative of higher baselines Capex
requirement
  • Can Use the TPCR agreed revenue drivers as proxy
    for capital expenditure
  • If baselines increased back to pre 2007 TPCR
    levels
  • Around 275m extra capex needed to provide the
    increased baselines

16
Alternative of higher baselines Buyback
modelling
  • Alternatively, can examine the incremental
    buyback risk. Preliminary results indicate that
  • Just at Teesside, increasing the baseline back up
    to 70 mscm/d could lead to around 90m
    incremental buyback risk (mean level of 20m) per
    year (assuming that the incremental flow at
    Teesside is off-set by reduction of flow at
    Milford Haven)
  • Similar level of risk at Barrow of increasing
    baseline back to 66 mscm/d

17
Summary
  • Discussed how baselines were set
  • Presented feedback received from industry
  • Proposed alternative ways of cutting the cake
  • Demonstrated that going back to higher baselines
    means either
  • significant capex needed
  • or that buy-back risk is likely to be high
  • Will provide a summary report to Ofgem in the
    next two weeks
  • Ofgem to commence their consultation
Write a Comment
User Comments (0)
About PowerShow.com