Title: Anatomy of the TSA High Speed Operational Connectivity Program
1- Anatomy of the TSA High Speed Operational
Connectivity Program
Strong Business Need, Disciplined Teamwork,
Success
2(No Transcript)
3Over 400 Federalized Airports
4Hi-SOC Airport FunctionalityThe Definition of
Success
- Connectivity to All TSA Controlled Space (LAN)
- Networked Check Points, Baggage Areas
- Networked Training Rooms, Office Space
- WAN Connectivity to TSA Hosting Center
- VoIP Intelligent Phones
- Migration to XP and Email
- Security and Remote Access VPN
5Hi-SOC Component Efforts Projects as of
February 2005
Sept
Oct
Nov
Dec
Jan
Feb
Mar
Apr
JFK Complete
FSD Deployment
Phase I 16 Sites
9/10ContractAward
12/3112 SitesComplete
10/4First Site Prep Proposal Receipt
11/18DCA Complete
10/11SiteSurveyComplete
Pago Pago, SaipanComplete
Guam Complete
Phase II Additional SitesSite prep funds
from AvOps
2/9AvOps PR received
Myrtle Beach Complete
HQ User Migration
3/3175 Migrations Complete
2/725 Migrations Complete
9/10Phase IContractAward
Closeout
10/29Phase IIContractAward
12/15PilotStart
1/10MigrationStart
1,900 Pentagon City, Veridian, Crystal Gateway
Users
2/93 Pilot Sites Complete
11/17ContractAward
215 Sites
7/1TransitionComplete
MPLS Enterprise
1/17Hosting Center Standup Complete
11/19Contract Award
1/25Hosting Center Standup Complete
11/15Deployments Complete
11 FSDsComplete
VoIP Field Deployment
11 FSD sites20 AvOps Priority Sites
Airport Deployment
Site Survey Requirements Transmitted
10 Airports
Hi-SOC Milestone Chart v13.0
6Hi-SOC Program Status
- FSD Deployment (Tom D.)
- Five week delay due to DSL installation barriers
- Funds continuing to arrive for additional sites
- HQ User Migration (Al P.)
- 60 of migrations completed, over 1,100 users to
date - Deployment on schedule to complete April 2005
- MPLS Enterprise Deployment (Mark K.)
- Nearly 40 of sites finished
- Completion on target for June 2005
- VoIP Enterprise Deployment (Ray P.)
- Deployments complete to initial sites
- Resolution of small site issue underway
- Airport Deployment (Bill Z.)
- LAX site kickoff teleconference this week
- Critical path shortened by five weeks via survey
sequencing
7Hi-SOC Precedence Diagram
9 9
68 68
Start Leasing MOAAgreements
Accept Leasing MOA Agreements
0 0
0 6
7 8
19 33
34 43
54 68
44 53
9 18
Questionnaire
Requirements Teleconference
Kick Off Meeting Site Walk
Statement of Work
General Contractor Bids
Unisys Cost ProposalGeneration
TSA Cost Proposal Approval
START
34 53
19 33
9 18
54 54
Order/Conduct VoIP Survey
Out of Box Solution? Security
Develop Security Processes
Begin
Certification Process Three artifacts
69 70
71 110
111 116
SOW Requirements
Installation
Security
Permitting
Schedule Alignment withAirport
WOS Order Generation
Acquisition
Infrastructure
147 151
166 170
152 166
117 146
71 86
116 116
DD250
Site Installation
Cable Plant Circuitry Installation
Deliver Artifacts
Security Certifications Complete
Final Security Certification
152 155
156 156
Migration
Migration DD250
170 170
71 115
156 156
152 155
Order/Procure VoIP
VoIP DD250
Install VoIP
FINISH
8Listening Points
- Program Management Topics?
- Managing benefits, stakeholders, governance
- Embracing change to optimize benefits
- Project Management Topics?
- Triple constraints
- Resisting change to protect the baseline
- PM Tools?
9Hi-SOC Anatomy At-A-Glance
- Strong Business Need
- Understood the stake holders
- Communicated the consequence of inaction
- Clearly articulated the program benefits
- Disciplined Team Work
- Practices grounded in PM Standards
- Built repeatable processes
- Worked together effectively
- Success
- Understood the desired goal
- Communicated the desired goal
- Delivered the desired goal
10The Backbone of Success
- Developing the Project Requirements
- WBS Modeling and Schedule Development
- Staffing Plan (Team Building)
- Communications Planning
- Working with Acquisitions and Budgeting
- Deployment
- Quality and Close Out
- Documentation, including the Hi-SOC Case Study
11Functional Requirements
- General requirements had to be singularly defined
at each airport - If you have been to one airport you have been to
one airport - Implementation of Hi-SOC restricted by
constraints of each airport
12WBS and Modeling
- Built the WBS and Implementation Model
- Modeling Risk comprised of Airport differences
and individual constraints - Developed a loose scheduling model, impacting
ability to baseline project schedule
13Milestone Development
- The September 20, 2006 Milestones
- 70 Category X and I Hi-SOC (Major)
- 100 Category II, III, IV High Speed Data
Connectivity to Administration and Training Areas
(Smaller) - 100 High Speed Data Connectivity to all TSA
computers No Computer Left Behind
14The Pilot
- Ten large and complex airports
- Assisted with original requirements and schedule
modeling - Provided risk forecasting
-
-
-
15Airport Workbooks
- Communications And Discovery Tool To
- Work with airports
- Standardize approach to performing kick off
meetings - Schedule site walks with airports, government,
and contractors - Provided
- Detailed scope discovery for each site
- The communications process
- An information sheet on Hi-SOC
- Schedule Development Tool
- Contact List
- Airport Risk Register
16Hi-SOC Staffing
- Concept
- Team Building What was needed to efficiently
complete all project requirements (Staffing) - Worked in a Matrix Environment (Dispersed
Authority) - Fixed Roles and Responsibility (Clearly Defined
Ownership) - Team Elements
- Project Management Office
- Security
- Legal
- Real Estate
- Acquisitions
- Finance
17(No Transcript)
18The Hi-SOC War Room (PMO)
- Streamlined Communications
- Enabled Daily Team Building
- Accentuated Fixed Roles and Responsibilities
- Institutionalized Project Area Ownership
- Co-located Individual Regional Teams
- Deputy Project Lead (Contractor)
- Regional Engineer
- Regional Information System Security Officer
(ISSO)
19Program Communications Infrastructure
- Effective Communications A critical success
factor for the Hi-SOC Program - It was better to over communicate when there was
doubt than not communicate and have
misinformation - Standardized meeting processes were invaluable
- Published meetings notes every time
- Kept individuals accountable for action
20Communications (Continued)
- Daily meetings 0900
- Weekly IPT meetings
- Internal
- With contractors
- Standardized meeting and reporting processes
- Open communications
- Understood the inter workings of other offices
- Understood roles and responsibilities
- Managed Change Control through sound
communications - One Team, One Goal, One Message
21You Know What They Say About Assumptions
- The money is not always there starting October
1st - The contract is not always available on October
1st - Our acquisition year ended July 1st for contracts
- Our acquisition year ended June 1st for Purchase
Requests -
- ALWAYS Keep A Good Working Relationship With
Acquisitions and Finance Instant Risk
Mitigation
22 Calling in Re-Enforcements The Army
- The US Army Information System Engineering
Command Experiment (ISEC) - The Bridge Contract (Unisys) not available until
January 26, 2006 - Needed an instrument to begin project
implementations to meet Sept 30th Goals - Assigned ISEC 12 airports to begin initial Hi-SOC
work
23Managing the Budget
- Managed gt100 million budget
- Full-time finance manager a MUST
- Conducted multiple briefings for Deputy CIO to
validate budget requirements - Managed and tracked all purchase requests
- Managed and tracked all procurement activities
- Committed and obligated all funding in a timely
manner
24Quality and Close Out
- Airport Project Acceptance (Check List)
- Managing Fiber Leases into the Future
- Multiple Vouchers
- Data Repository Captured Airport-Specific
Information
25Documenting and Archiving the Project and
Processes
- Conducted lessons learned session after major
milestones - Celebrated success with team gatherings,
promotional stories - Built extensive library of all program
documentation - Created the Hi-SOC Case Study and Archival
Document
26Hi-SOC Results to Date
- Major Airports
- 90 received Hi-SOC
- 100 scheduled to be achieved 4/30/08
-
- Medium To Small Airports
- 87 have Hi-SOC
- 100 scheduled to be achieved 11/30/07
- Over 99 of TSA computers have network
connectivity - Hi-SOC infrastructure is now ready and will
maximize the ROI for numerous, mission critical
software applications
TSA now has a proven example for how to use
repeatable, disciplined PM techniques for IT
endeavors
27In Closing
- Ask yourself Is this program management or
project management? - Effective use of PM techniques can improve any
effort at any time. - PM discipline from within is possible in any
organization. - One size cannot fit all.
27
28Keep Sharing Promising Practices
- Bill Ziegler, PMP
- William.Ziegler_at_dhs.gov, 571-227-3868
- Kriste M. Jordan, PMP
- Kriste.Jordan_at_dhs.gov, 571-227-1453
Federal PM Case Studies
28