Title: RISK ASSESSMENT CONCEPTS AND PRACTICE
1RISK ASSESSMENT CONCEPTS AND PRACTICE
- Presentation to University of South Australia
- Environmental Engineering
- 23 March 2004
- Richard McDonough
- Manager Pipeline Operations
- Petroleum Group
2The Author
- Chemical Engineering graduate
- Mines Energy / PIRSA - 19 years!!!
- Reservoir engineering
- Economic analysis for gas pricing, royalty
review, gas production - Gas reserves advice / computer modelling
simulation - Environmental approvals monitoring
- Petroleum Act 2000
- Pipelines
- AS 2885 (pipelines standards) committees
- Responsible for review of risk assessment for
pipelines in AS 2885
3Overview
- Risk concepts
- what is risk?
- risk perception
- acceptable risk
- ALARP
- Risk assessment methodology
- AS 3931, AS 2885, AS 4360
- Example high pressure gas pipelines
4What would you do?
5What would you do?
5 Caramello Koalas
6What would you do?
5 Caramello Koalas, 5 Snakes
7What would you do?
9 Caramello Koalas, 1 Snake
8What would you do?
9 Caramello Koalas, 1 Taipan
9What would you do?
What would STEVE IRWIN do??
9 Caramello Koalas, 1 Taipan 99 Caramello Koalas,
1 Taipan etc
10What would you do?
9 Caramello Koalas, 1 Python
11What would you do?
9 Caramello Koalas, 1 Jelly Snake
12What is risk?
13Risk Concepts
- Frequency
- Consequences
- Perception
- Risk Acceptance
14Risk Definitions
- AS 3931
- combination of the frequency, or probability, of
occurrence and the consequence of a specified
hazardous event - Note the concept of risk always has two
elements, the frequency or probability with which
a hazardous event occurs and the consequences of
the hazardous event
15What is risk?
- Risk combines FREQUENCY and CONSEQUENCE
- Risk estimation requires us to be SPECIFIC about
the consequence
16Risk Definitions
- AS 4360
- the chance of something happening that will have
an impact upon objectives. It is measured in
terms of consequences and likelihood. - I would suggest that this is a poor definition,
because - it uses imprecise language and
- it is misleading (risk can only be expressed for
a single consequence, NOT consequences - eg.
death risk is different to injury risk).
17Frequency Consequence
- Consequences
- positive
- negative
- hierarchy of consequences
- Frequency
- frequency of CONSEQUENCE
- NOT frequency of initiating event
18PIPELINE THREAT OCCURS
19Risk Perception
- A problem for engineers
- (rational, numerate beings!!!)
- Perception is reality
- Behaviour is driven by perception and not cold
hard facts. - Risk communication is an issue
20Acceptable Risk
- Individual Risk
- eg 1 in a million per year
- Societal Risk
- It is more acceptable to have 1000 incidents each
resulting in single fatalities than 1 incident
resulting in 1000 fatalities - Accepted risk will reflect either or both of
these - Refer to HIPAP4
21(No Transcript)
22ALARP
- As Low As Reasonably Practical
- In the range 10-4 to 10-6
- No single definitive definition
- Ultimately determined by courts
- A working definition
- where the cost of mitigating the risk exceeds the
costs of the risk consequences
23Comparison of AS4360, AS3931, AS2885
- Different objectives, audiences and emphases
- AS 4360
- generic
- AS 3931
- technological systems
- AS 2885
- pipelines
24Risk Assessment Process
25AS 2885 RISK ASSESSMENT PROCESS (proposed
revision)
PROBLEM DEFINITION
Describe Design and Operation Parameters
Determine Safety Review Methodologies
Location Analysis
THREAT ANALYSIS / MITIGATION BY DESIGN
Identify and Specify Threats
Classify Threats
Non-credible threats
External Interference Threats
Design Threats
Eliminate or Minimise Threats by Design
Identify Residual Threats
Identify Loss of Integrity Events
RISK EVALUATION LOSS OF INTEGRITY EVENTS
Risk consequence frequency
RISK MANAGEMENT
Risk Management Actions as Required
26Key Aspects of AS 2885
- Concentrates effort at Initial Evaluation and
Control stage - highlights importance of consequence analysis
- not obvious in AS3931 and AS4360
- If risk can be eliminated it MUST be eliminated
- not a feature of AS3931 and AS4360
27Key Aspects of AS 2885 (2)
- Minimizes risk-based decision-making
- minimizes decisions based on uncertainty
- Maximizes pipeline safety
- ALL threats must be addressed
28Pipeline Example
- High pressure gas pipeline traversing a number of
different land use areas - Concentrate on external interference protection
(the most common cause of pipeline incidents in
Australia). - Pipeline Risk Assessment focuses on specific
incidents on a specific pipeline at a specific
location (NOT generic)
29(No Transcript)
30Step 1 - Scope Definition(1)
- Pipeline Properties
- mechanical properties, operating parameters
- under what circumstances can a hole be put in the
pipe? - if a hole is put in the pipe, what can occur?
- All this is known, or can be calculated
- Pipeline-specific information (not generic
information) - Real information for decision-making
31Step 1 - Scope Definition(2)
- Location analysis
- land use, environment, crossings, population
density determined on a metre by metre basis - Threats and consequences are dependent on the
location - Generic guesses are not good enough
- Can only design against real threats which are
properly defined
32Step 2a - Threat ID
- The elimination of threats by external
interference protection and engineering design
must be based on quantifiable data.
Consequently, the threats analysis must generate
sufficient information about each threat to allow
such design to take place. (HB105)
33Step 2a - Threat ID
- For each location, identify all activities which
occur on the pipeline easement - Develop specific information for each threat
- what happens?
- what equipment?
- who is responsible?
- how deep?
34Step 2b - Eliminate threats where possible
- AS 2885 mandates physical and procedural measures
- Physical measures
- eg. wall thickness, depth of burial, slabs,
barriers - Procedural measures
- eg. signs, liaison, patrols, dial-before-you-dig
35Bobcat Bob
- 2 physical protection
- Digs 50 cm holes (pipe buried at 1m)
- Bobcat is not powerful enough to penetrate pipe
- 2 effective procedural protection
- signs on Bobs fences
- liaison with Bob once a year
- Threat eliminated
- No risk evaluation required (it is not meaningful)
36Water Company
- Water main below gas pipe
- Excavator powerful enough to penetrate pipe
- No physical protection
- Risk evaluation must be carried out
37Step 3 - Water Company Risk Evaluation
- Consequence analysis shows that an ignited gas
release may result in multiple fatalities - Frequency analysis suggests this is an unlikely
occurrence (ie. might occur once every hundred
years)
38Water Company Risk Evaluation
39Step 4 - Risk Management - Water Company
- High risk category demands risk management
action - Examples include
- increase pipe wall thickness at this location
- bury gas pipe below water pipe
- raise water pipe above gas pipe
- concrete slabs around pipe at this location
40Conclusions
- Risk analysis is not rocket science
- However, brain needs to be switched on
- Be specific
- Be highly critical of any numbers, assumptions
and conclusions (always ask hard questions) - Minimise risk-based decisions by eliminating
threats where possible - In general, the process is more important than
any numbers generated because it has forced
people to think about the problem
41(No Transcript)