Title: Preparation for Production
1Preparation for Production
- Material Approval from CERN
- All material documented for flammability
characteristics and approved by CERN.
2Preparation for Production
- Manpower
- Additions since Dec 99
- 1 additional tech in MP9 factory (baseline
workforce7 technicians) - CO approved on Jan 00
- 1 additional tech for QA/QC FNAL/IHEP/PNPI kit
preparation - 1 FTE additional inspector for Frame Inspection
- 1.2 FTE additional procurement support for Frame
Procurements - CO under approval
3Preparation for Production
- Production Readiness Review II
- All issues from PRR I considered adequately
addressed and resolved - OK for FNAL production of CSC chambers.
4FNAL Activity
PNPI Site
parts and critical tooling (smaller chambers)
smaller CSCsElectronics, tested installation/comm
issioning
UC Site
large CSCs
large CSCsElectronics, tested installation/commis
sioning
Fermilab Site - panel production - large CSC
assembly
CERN
large CSCsElectronics, tested installation/commis
sioning
large CSCs
UF Site
Procurement
parts and critical tooling (smaller chambers)
smaller CSCsElectronics, tested installation/comm
issioning
Wire
Panels
IHEP Site
Guard strips
Gap bars (UF)
Wire fix bars
Frames (FNAL) HV Connector (UW)
Frames/HV Connector (UW)
Etc.
5FNAL ActivityMilestones _at_ FNAL-FY99
6FNAL ActivityMilestones _at_ FNAL-FY00
7Prototyping Production Sign-off
- Prototyping Schedule
- ME1/2 Assembled by Jan. 00
- ME2/1 Assembled by May 00
- ME3/1 Assembled by Jun. 00
- ME1/3 Assembled by Jun. 00 Aug. 00
- 4 ME234/2 Pre-production chambers
- Production Sign-off
- Production to be agreed upon by
- all L2-L3 Managers through the
- Configuration Control Process
- ME234/2 Jul. 00
- ME1/2 Aug. 00
- ME2/1 Sep. 00
- ME3/1 Dec. 00
- ME1/3 Sep. 00
8FNAL Factories - Lab 8
90 ME2324/2 Chamber(60) 15/553 Rejected
Panels (2.7)
9Manpower Experience
10Manpower Experience
11Foreign Factory Setup
- Setting up a Factory implies placing many
activities/items under control - 10 Chamber kits shipped to Russia/China by
Jan.-Feb. 01 - Tooling
- Assembly, Commissioning Shipment
- Operating Procedures
- Parts Control
- Parts Inspection Shipment
- Parts Accounting
- Parts Storage and Flow to the Production Floor
- Chamber Assembly Activities
- Assembly Procedures Personnel Training
- Definition/tooling for QA/QC Activities
- Discrepancy Report Scenarios
- Travelers and Measurements Data-basing
- Underlined Fermilab Responsibilities
12Conclusions
- CSC Production at FNAL is underway
- First CSC production rates in agreement with
expectations - Chamber Integration effort on track for
China/Russia Chambers - Manpower usage cost in line with expectations
- Preparation for China/Russia Production sites
weel under way.