1
Preparation for Production
  • Material Approval from CERN
  • All material documented for flammability
    characteristics and approved by CERN.

2
Preparation for Production
  • Manpower
  • Additions since Dec 99
  • 1 additional tech in MP9 factory (baseline
    workforce7 technicians)
  • CO approved on Jan 00
  • 1 additional tech for QA/QC FNAL/IHEP/PNPI kit
    preparation
  • 1 FTE additional inspector for Frame Inspection
  • 1.2 FTE additional procurement support for Frame
    Procurements
  • CO under approval

3
Preparation for Production
  • Production Readiness Review II
  • All issues from PRR I considered adequately
    addressed and resolved
  • OK for FNAL production of CSC chambers.

4
FNAL Activity
PNPI Site
parts and critical tooling (smaller chambers)
smaller CSCsElectronics, tested installation/comm
issioning
UC Site
large CSCs
large CSCsElectronics, tested installation/commis
sioning
Fermilab Site - panel production - large CSC
assembly
CERN
large CSCsElectronics, tested installation/commis
sioning
large CSCs
UF Site
Procurement
parts and critical tooling (smaller chambers)
smaller CSCsElectronics, tested installation/comm
issioning
Wire
Panels
IHEP Site
Guard strips
Gap bars (UF)
Wire fix bars
Frames (FNAL) HV Connector (UW)
Frames/HV Connector (UW)
Etc.
5
FNAL ActivityMilestones _at_ FNAL-FY99
6
FNAL ActivityMilestones _at_ FNAL-FY00
7
Prototyping Production Sign-off
  • Prototyping Schedule
  • ME1/2 Assembled by Jan. 00
  • ME2/1 Assembled by May 00
  • ME3/1 Assembled by Jun. 00
  • ME1/3 Assembled by Jun. 00 Aug. 00
  • 4 ME234/2 Pre-production chambers
  • Production Sign-off
  • Production to be agreed upon by
  • all L2-L3 Managers through the
  • Configuration Control Process
  • ME234/2 Jul. 00
  • ME1/2 Aug. 00
  • ME2/1 Sep. 00
  • ME3/1 Dec. 00
  • ME1/3 Sep. 00

8
FNAL Factories - Lab 8
90 ME2324/2 Chamber(60) 15/553 Rejected
Panels (2.7)
9
Manpower Experience
10
Manpower Experience
11
Foreign Factory Setup
  • Setting up a Factory implies placing many
    activities/items under control
  • 10 Chamber kits shipped to Russia/China by
    Jan.-Feb. 01
  • Tooling
  • Assembly, Commissioning Shipment
  • Operating Procedures
  • Parts Control
  • Parts Inspection Shipment
  • Parts Accounting
  • Parts Storage and Flow to the Production Floor
  • Chamber Assembly Activities
  • Assembly Procedures Personnel Training
  • Definition/tooling for QA/QC Activities
  • Discrepancy Report Scenarios
  • Travelers and Measurements Data-basing
  • Underlined Fermilab Responsibilities

12
Conclusions
  • CSC Production at FNAL is underway
  • First CSC production rates in agreement with
    expectations
  • Chamber Integration effort on track for
    China/Russia Chambers
  • Manpower usage cost in line with expectations
  • Preparation for China/Russia Production sites
    weel under way.