Title: BTeV Spools (WBS 2.1.2.3)
1BTeV Spools (WBS 2.1.2.3)
2Topics
- Scope of work
- Spool design parameters
- Spool design
- Cost and schedule
- Key milestones
- Critical path analysis
- Risk analysis
- Summary
3Organization (or You are here)
2.1.3 Project Management
WBS 2.1 Magnet Fabrication Test
2.1.2 New Spools
2.1.1Q1 to Q5 Quadrupoles
2.1.2.3Spool Assembly
2.1.2.2Corrector Magnets
2.1.1.4 Q1 to Q5 Fabrication
2.1.2.1 HTS Leads
2.1.1.1Cold Mass
2.1.1.2Cryostat
2.1.1.3 MTF Test Stand
4Scope of Work
- Design and oversee production of two sets of
spools. - Each set consists of 5 spools (X1H, X1V, (2) X2,
X3) for a total of 10 spools (installed). - The current plan is to have an outside company
fabricate and build the spool assemblies based on
our design. - The major components would be supplied to the
vendor. - HTS Leads, correctors, other leads, bus work,
etc. - The completed spools will be tested at FNAL.
5Initial Design Criteria
- Designed in accordance with ASME Boiler and
Pressure Vessel Code - Design pressure, MAWP
- Single phase 200 psig
- Two phase 50 psig
- LN2 system 100 psig
- Heat load to 4K 5 W per device (spool, quad,
etc.) - Corrector envelopes
- X1 spools 200 mm OD x 1200 mm long
- X2 spools 200 mm OD x 550 mm long
- X3 spools 200 mm OD x 800 mm long
- BPM length 10 inches
MAWP is Maximum Allowable Working Pressure
6Spool Pieces
Q1Q2X3Q3 (mirror image about IP not shown for
space)
- Spools are located between other components,
either new quads or existing Tev equipment (not
shown here) - X1 (not shown) variations driven by H/V Dipole
corrector requirement
7Spool Internal Components
- Spool component list
- Corrector magnets
- Power leads
- 10 kA HTS leads, 2 per power spool (1 pair)
- Corrector leads
- 200A leads
- Instrumentation leads
- Beam position monitors
- Relief valves 3 per spool
- Cryogenic pipe interfaces as needed
- Through bus as needed
- Quench stoppers
- Vacuum Break
8Spool Information
(Details)
(Interfaces)
9X2 Spool
Corrector Leads
Relief valves
HTS Leads
10X2 Spool Cross Section
Support Post (same as quad)
Liquid Nitrogen volume
Vacuum break
BPM
Helium vessel
Corrector
Vacuum vessel
11X2 Lead Stack Helium Pipe
HTS Leads
Corrector Leads
Safety Leads (for Tev bus)
12X2 Lead Stack Cross Section
Quench Stopper (for Tev bus)
13X2 Vacuum Vessel
ASME BPV Code VIII-1 Appendix 13 Sketch 3
14Spool Cost and Schedule Summary
- Engineering and design manpower
- Engineers 1.5 FTEs (FY05 FY06)
- Designer/drafters 2 FTEs (FY05 FY06)
- 1.5 years of detailed design October 2005
March 2006 - Bidding, fabrication, assembly and test
- April 2006 October 2008
- Production oversight 1 FTE
Summary of spool cost (Based on LHC DFBX and
preliminary fabrication study) Base cost 5.284M
(Material 3.712M, Labor 1.572M)
15Spool Schedule
16Spool Cost
FY05 k No Contingency No Escalation GA
Included Construction Costs
17Spool Labor
18Key Milestones
- Start of detailed design October, 2004 (FY05)
- Bidding process April, 2006
- 1st Spool fabrication begins October, 2006
- Series production begins November, 2007
- Production and test complete October, 2008
19Critical Path Analysis
- Design of internal components
- The Corrector and BPM designs need to be complete
in time so that integration into the spool can
begin. - Detailed design complete
- The spool detail design needs to be completed in
time so that the bidding process may start. - Vendor production schedule
- Timely delivery of components to vendor.
- Production oversight is critical to keep the
vendor on schedule.
20Risk Analysis
21Summary
- The spool design is based on the stated corrector
envelopes, BPM length and (2) HTS leads per power
spool. - The remaining components are well understood and
the conceptual design is under way. - Cost estimates for assembly by an outside vendor
are based on the LHC DFBX (feedbox) which is
similar is size and function to the new spools
and a preliminary fabrication study that was
completed in August, 2004 by potential vendors.