Title: TANESCO SCHEMES FOR NEW GRID CONNECTIONS


1
TREESPA OPEN WORKSHOP
  • TANESCO SCHEMES FOR NEW GRID CONNECTIONS
  • By Eng. Sophia S. Mgonja
  • SENIOR MANAGER DISTRIBUTION


2
Distribution Key Statistics (As on 30th October
2009)
3
CUSTOMER BASE INCREMENT
  • Target is to connect 100,000 customers annually
    from 2007
  • Specific actions
  • Extension of Medium voltage and low voltage lines
    by TANESCO
  • Outsource MV LV distribution construction works
    in six regions
  • Outsource construction of service lines in one
    region as pilot project.

4
PERFORMANCE
5
CONNECTION BARRIERS
  • Low purchasing power of customers
  • Long procurement process leading to
    unavailability of some construction materials
  • Un-surveyed areas

6
CONNECTION WAY FORWARD
  • Customers are now allowed to pay in part for
    service line connections
  • Outsource construction projects
  • Ensure availability of construction materials,
    transport and skilled manpower
  • For REA funded projects, the first 100 customers
    to pay for application form VAT only, and will
    be provided with four energy saver bulbs

7
RURAL ELCTRIFICATION PROJECTS
  • The first priority is to connect all district
    headquarters and surrounding villages.
  • To date only 12 district headquarters have not
    yet been connected with electricity out of 114
    districts.
  • However 4 out of the 12 districts will be
    connected by end of this year or early next year.

8
REA FUNDED PROJECTS
  • Projects in progress
  • Kilindi District Headquarters in Tanga Project
    expected to be completed in December 2009
  • Electrification of Bahi District headquarters in
    Dodoma Project expected to be completed in
    December 2009
  • Electrification of Kilolo District Headquarters
    in Iringa Project expected to be completed in
    December 2009
  • Uyui District Headquarters in Tabora Project
    expected to be completed in December 2009.

9
REA FUNDED PROJECTS
  • NEW APPROVED RURAL ELECTRIFICATION PROJECTS
  • Total number of projects is 42.
  • Total expected new customers 19,453
  • Estimated total cost TShs. ..
  • Total route length
  • Medium voltage lines 1,646km
  • LV lines 946km
  • Distribution substation 369
  • Total expected new customers 19,453

10
GENERAL CONDITIONS OF SUPPLY FOR ENERGY EFFICIENT
UTILIZATION
  • POWER FACTOR-
  • shall be 0.95 for lighting and 0.9 for other
    loads. A surcharge of 2.9 times consumed kWh is
    imposed for low P.F
  • Three phase supplies shall be balanced
  • Consumers should comply with methods of starting
    motors

11
CONCLUDING REMARKS
  • Rehabilitation of deteriorated Distribution
    Network infrastructure and expansion of
    distribution network to capture more customers
    are the critical challenges that face TANESCO.
  • Establishment of REA and formation of REF has
    assist in addressing expansion challenge
    especially in rural areas.
  • It is expected that more rural areas will be
    electrified following willingness of financiers
    to finance the RE projects including the
    Government.

12
  • THANK YOU FOR YOUR KIND ATTENTION