Title: ELECTRICITY SUPPLY SECURITY Challenges for Poland
1ELECTRICITY SUPPLY SECURITYChallenges for
Poland
Hanna Trojanowska International Affairs and New
Technologies Department PSE SA Vilnius, 26-27
January 2006.
2AGENDA
- Challenges for the Polish Power Sector
- Development of the Polish Transmission System
(PTS) including interconnections up to 2012 - Restructuring of the Polish Power Sector
3POWER SECTOR IN POLAND
TRANSMISSION PSE-Operator SA Transmission System
Operator - balancing market
- GENERATION
- over 30 PP including
- two large groups of
- producers BOT, PKE
-
- - 34 673 MW
- installed capacity,
- - 156,023 TWh
- annual production
- - 144,8 TWh
- annual consumption
- - 23 477 MW
- Peak load
- on 21 Dec. 2005
- 11,184 TWh
- net export of electricity
- DISTRIBUTION
- 9 distributing
- companies
- providing
- services
- for 15 million
- customers
-
POLISH Electricity Markets
TRADE suppliers, traders,
4Challenges for the Polish Power Sector
- 95 of electricity is generated from coal (hard
and brown) - Implications for environmental standards
necessary investments - Geographical location of the Polish Transmission
System specific conditions for co-operation
with neighbouring countries - Electricity demand forecasts
- RD focus on new technology in generation
- Nuclear option is on the table
5SYSTEM ADEQUACY
- Long term security of electricity supply
according to UCTE requirements - Investments in the new infrastructure -
generation transmission - Forecasts of UCTE System Adequacy
- Competitiveness of electricity markets vs
security of electricity supply
6Benefits of nuclear energy in Poland
- Meeting the increased electricity demand
- Low costs of power generation
- No CO2 emissions
- Diversification of fuel sources supply
- Increase of independence and readiness in case of
energy crisis
7AGENDA
- Challenges for the Polish Power Sector
- Developments of the Polish Transmission System
(PTS) including interconnections - Restructuring of the Polish Power Sector
8PTS - CONGESTED AREAS
9PTS - INTERCONNECTIONS
PTS-NORDEL INTERCONNECTIONDC cable link the
transfer capacities reach 600 MW in both
directions and are determined by the cable
parameters
PTS-UPS/IPS INTERCONNECTIONthe transfer
capacities reach 400 MW (only imports of power
possible) and are determined by the current
operation
KSP-UCTE INTERCONNECTIONthe export capacities
are 2000 MW
10PTS IN 2008
2007
2006
2007
2006
11PTS IN 2012
2012
2010
12SCOPE OF GRID INVESTMENTS REQUIRED FOR POLAND AND
LITHUANIA TO PARTICIPATE IN THE IEM
- Grid investments in Lithuania
- 400 kV Alytus Polish border double-circuit line
- back-to-back substation 2?500 MW in Alytus
- 330 kV Alytus Kruonis double-circuit line
13SCOPE OF GRID INVESTMENTS REQUIRED FOR POLAND AND
LITHUANIA TO PARTICIPATE IN THE IEM
- Grid investments in Poland
- 400 kV Elk Lithuanian border double-circuit
line - 400 kV Narew-Elk line
- 400 kV Elk Olsztyn Matki line
- upgrade of substation Elk to 400 kV
- 400 kV Patnów Sochaczew Milosna
double-circuit link - 400 kV Plewiska German border double-circuit
line (third Poland-Germany line)
14SCOPE OF GRID INVESTMENTS REQUIRED FOR POLAND AND
LITHUANIA TO PARTICIPATE IN THE IEM
- Grid investments in Germany
- 400 kV double-circuit line to Poland (third
Poland Germany line) - voltage level switch over from 220 to 400 kV
Krajnik Vierraden - 380 kV Vierraden Neuenhagen double-circut line
15SCOPE OF GRID INVESTMENTS REQUIRED FOR POLAND AND
LITHUANIA TO PARTICIPATE IN THE IEM
- All the investment projects mentioned have been
submitted under the TENs project
16REQUIRED CONDITION OF GRID IN 2012
Kaliningrad(back-to-back)
Alytus(back-to-back)
Elblag
Elk
Olsztyn Matki
BIA
Ross(back-to-back)
Narew
Plewiska
Patnow
Milosna
Sochaczew
17CONCLUSIONS FROM THE STUDIES
-
- Reliability analyses of the interconnected
systems, which take into account the needs of the
IEM, define the necessary scope of system
expansion in the Baltic countries, Poland and
Germany for the purposes of the Lithuania-Poland
interconnections - All analyses have shown that the project is not
cost-effective - The results have been unacceptable to the TSOs,
mainly to the Polish TSO due to effects on
transmission tariff - The outstanding funds required to achieve
financial closing for the project exceeded 60 of
the planned expenditure
18SINCE OUR NEGOTIATIONS ARE STILL ONGOING, A
SATISFACTORY SOLUTIONMAY STILL BE FOUND
19AGENDA
- Challenges for the Polish Power Sector
- Developments of the Polish Transmission System
(PTS) including interconnections - Restructuring of the Polish Power Sector
20CONSOLIDATION OF THE POLISH POWER SECTOR
- Opportunities and advantages on the electricity
market in the context of economic power balance
on the market - Optimization of number of players capable of
competing on electricity market - Restructuring of LTC
- Electricity market concentration
- effectiveness versus competitions barriers
21Advantages of Power Sector Restructuring
- Fulfilling Energy law requirements regarding
the TSOs activity - Establishment of fully independent TSO with
transmission asset - Creation of a strong integrated company
capable of competition on the domestic and
European electricity market and able to invest
in the development of infrastructure
22Thank you for your attention !