EIS Progress Report - PowerPoint PPT Presentation

About This Presentation
Title:

EIS Progress Report

Description:

Expected results. HR/Payroll 2nd parallel payroll run. 10/1/09. Full parallel run of the end of month payroll process; test of leave hours. ... – PowerPoint PPT presentation

Number of Views:25
Avg rating:3.0/5.0
Slides: 12
Provided by: foot3
Category:
Tags: eis | progress | report | testing

less

Transcript and Presenter's Notes

Title: EIS Progress Report


1
EIS Progress Report
  • Executive Steering Committee Meeting
  • September 23, 2009

2
Issues Report
  • Banner Finance
  • Additional self service trainings are scheduled
    for both campuses
  • Approval queue will be turn on by October 15.
  • Banner HR/Payroll
  • Status and analysis report

3
Project calendar review
4
Major Tasks AchievedAugust/September 2009
Planned activities Dates Expected results
HR first parallel payroll run 9/1/09 Be able to compare the paychecks of 3600 employees between Banner and IAplus.
Major Banner modification decisions 9/1/09 3 digit vs. 4 digit faculty load factor modification decision point, 10-11 month tax withholding.
CCCApply contract ready for signature 9/1/09 Move to the next phase of the project.
Conversion of Catalogue and Schedule from IAplus to Banner (Summer and Fall quarter) 9/3/09 A test Banner platform for the schedulers to clone the future Banner schedules.
HR go Live readiness review 9/11/09 First assessment of HR go live readiness for January 2010.
Mid-month payroll parallel run 9/17/09 Mid-month payroll parallel run against IAplus.
Production data replication to DR site 9/22/09 Live data replication established for finance module to Carlsbad DR site.
5
Major Milestone Ahead October 2009
Planned activities Dates Expected results
HR/Payroll 2nd parallel payroll run 10/1/09 Full parallel run of the end of month payroll process test of leave hours.
Luminis requirements definition for HR and Student 10/1/09 Luminis channel setup within Banner system for HR and Student access.
CCCApply implementation kick off 10/6/09 Technical team kick off meeting with College of Sequoia.
3CBG Conference 10/8/09 3CBG Banner user conference
Academic History conversion starts 10/12/09 Student conversion task
2nd Mid month pay roll/Direct deposit testing 10/18/09 Payroll direct deposit testing.
ECMS/C3MS integration testing starts 10/30/09 Course management system interface testing starts.
3/12/2014
5
6
Project Progression Chart
7
Project budgetCurrent budget vs expenditure as
of 07/29/2009
Project Item Budget amount Expenditure Balance
Banner/Oracle Implementation 3 years 6.6M 6.3M 0.3M
EIS Hardware 1.0M 1.1M -0.1M
Backfill 1.7M 0.3M 1.4M
Start up cost year 2/3 1.3M 0.56M 0.74M
Project Contingency 1.2M 0 1.2M
Total 11.8M 8.26M 3.54M
8
Percent of budget used as of August 31, 2009
9
Completion vs. Budget detail AnalysisAs of
August 31, 2009
10
Project Calendarhttp//www.fhda.edu/eis/eis_plan

Dates with underlines indicate multiple events
occurring at the same time. Hold Control button
down while clicking underlined events to follow
links to agendas.
11
Questions