Title: May 5, 2004
1ISO New England State of the Market Report 2003
Robert G. Ethier, Ph.D. Director, Market
Monitoring
2Fuel Prices and Energy Prices
- Electricity prices were driven to high levels by
fuel prices, which are the largest component of
generators marginal costs, and to a lesser
extent by load levels. - The next figure shows that monthly energy prices
for 2002 and 2003 have been driven by fuel price
trends. - Natural gas prices were 74 percent higher than
2002 on average. - Nearly half of New England capacity is gas-fired
or gas capable. - Electricity prices peaked in February and March
as natural gas prices rose to unprecedented
levels. - The July Peak Summer Load was much lower.
3Fuel Prices and Energy Prices (Continued)
- Electricity prices increased less than gas prices
because economic dispatch substituted other,
cheaper fuels. - Gas-only units were on the margin 52 of the time
in 2003 versus 55 in 2002, despite approximately
6,000 MW of new gas capacity added over the two
years. - Gas-capable units were on the margin 67 of the
time in 2003.
4New England Electricity Natural Gas Prices
2001 - 2003
SMD Implementation
5Energy Prices in 2003
- The next figure shows real-time price duration
curves for 2001 to 2003. - These curves show the percentage of hours when
the load-weighted price for New England is
greater than each given price level. - Price levels were generally higher in 2003 than
in the previous two years due to higher fuel
prices. - In 2003, there were fewer price spikes than the
two previous years - In 2003, real-time prices exceeded 500 for 1
hour, compared to 4 hours in 2002 and 15 hours in
2001. - The lower quantity of price spikes was primarily
due to milder weather in New England combined
with relatively robust capacity margins. - Scarcity pricing provisions were implemented, but
were not triggered in 2003.
6(No Transcript)
7Load Profile
- The next figure shows annual load duration curves
for New England. - These curves show the percentage of hours in
which the load is greater than the level
indicated on the vertical axis. - In 2003, peak days had far less impact on average
prices than in 2002. The absence of severe price
spikes was due to mild summer loads. - There were only 19 hours in 2003 when actual
loads exceeded 24,000 MW, compared to 34 hours in
2002. - In 2003 there were 200 hours when load exceeded
21,000 MW compared to 263 hours in 2002.
8(No Transcript)
9All-in Energy Prices
- The following figure calculates an all-in price
that includes the cost of energy, ancillary
services, capacity, and other costs. - The all-in energy price is a weighted average of
various locations within New England, since
energy prices vary by location. - Ancillary services includes reserves and
regulation prior to SMD, and regulation after SMD
implementation. - This figure shows that all-in prices rose in
2003. - The all-in price rise is primarily caused by
increased energy prices in 2003, which rose 41
in 2003 due to higher fuel prices. (from
41.65/MWh to 55.36/MWh) - The capacity component fell in 2003 due primarily
to increases in installed capacity. - While the energy component increased in 2003, the
fuel adjusted energy price fell relative to 2002.
10All-In Price Metric 2001 - 2003 (/MWh)Total per
MWh Energy, Uplift, Capacity, and Ancillary
CostsIncludes Energy and Fuel Adjusted Energy
Energy Costs
Fuel Adjusted Energy Costs
Total Energy
Fuel Adjusted Total Energy
Uplift
Capacity
Ancillary Services
Note Energy Interim Market Period ECP System
Load SMD Period RT Load Obligation RT LMP
11Economic Incentives for New Investment
- In long-run equilibrium, the market should
support the entry of new generation by providing
sufficient net revenues (revenue in excess of
production costs) to finance new entry. - We calculated the net revenue the markets would
have provided to different types of units in
2003. - A gas-fired combined-cycle (heat rate 7,000).
- A gas-fired combustion turbine (heat rate10,500)
.
12Economic Incentives for New Investment (Continued)
- Even though energy and all-in prices were higher
in 2003, the net revenue for gas-fired units was
lower in 2003 than 2002 due to gas price
increases. - New capacity added in 2002 and 2003 also reduced
net revenues. - These results indicate that the market in 2003
did not produce sufficient net revenue to support
investment in a new gas turbine (GT) or a new
combined-cycle (CC) unit. - A new GT would only recover 16 - 21 of its
estimated annual fixed costs for 2003. - A new CC would only recover 64 -73 of its
estimated annual fixed costs for 2003.
13Economic Incentives for New Investment (Continued)
- This was done pool-wide because LMPs existed for
only a portion of the year - A unit in Connecticut, for example, would have
earned additional revenue.
14Net Revenue Metric 2003
All Values in /MWh Combustion Turbine Unit Combined Cycle Unit
Energy revenues 1 58,773 315,239
Energy marginal costs 2 47,907 241,792
Net Revenue Energy 10,867 73,447
Revenue Capacity 3 1,972 1,972
Revenue Ancillary Services 4 - 1,492
Total Net Revenue 12,839 76,912
Estimated Annual Fixed Costs 60,000-80,000 105,000-120,000
- Energy revenues are calculated as the revenue per
MW of a hypothetical unit assumed to be
dispatched during each hour when the market
clearing price equals or exceeds the unit's
marginal cost, adjusted for a 5 forced outage
rate. Revenues are calculated based on the
system wide energy clearing price prior to SMD
(March 1, 2003), and based on the real-time Hub
LMP from March 1, 2003 onward. - Energy marginal costs are calculated as the
average Massachusetts natural gas daily spot
price multiplied by the unit's respective heat
rate the unit's respective variable OM. These
marginal costs are then adjusted for a 5 forced
outage rate. - Capacity revenues for year ending 12/31/2003 are
the UCAP revenues derated by the 5 forced outage
rate. - Ancillary service revenues are calculated only
for Regulation.
15Forced Outages
- The next figure presents the trend in the forced
outage rates from the beginning of the operation
of the New England Markets. - The forced outage rate is the percentage of time
capacity is unavailable due to full or partial
forced outages. - Total outage rates have declined substantially
following the implementation of markets in New
England. - This is consistent with the incentives the
deregulated markets provide to maximize
availability, particularly during high load
(on-peak) conditions. - Previous analysis suggests that new
combined-cycle units initially have high outage
rates. New England has many new combined-cycle
units. Improvements in outage rates may be
expected as these units mature.
16(No Transcript)
17Congestion Costs
- The following figure shows the monthly average
congestion components of LMPs in the day-ahead
and real-time markets for March through December
2003. - Maine had significant negative congestion as
generation was periodically constrained down due
to export constraints. - Connecticut had significant positive congestion
as it was periodically import constrained. - Northeastern Massachusetts/Boston experienced
less congestion than expected based on historical
data due to significant generation additions and
transmission upgrades. - Note that these numbers understate congestion
costs, as they exclude significant out-of-merit
local operating reserve costs, which dont affect
LMPs.
18On-Peak Average Day-Ahead Congestion March -
December 2003
19On-Peak Average Real-Time Congestion March -
December 2003
20Competitive Benchmark Analysis
- Evaluated actual energy clearing price and actual
cumulative bid-in capacity sorted by ascending
price (aggregate bid-intercept) versus marginal
cost-based simulated dispatch. - Simulated dispatch designed to produce an
estimate of the perfectly competitive market
outcome. - Caution that the estimate is subject to an
unknown error. - Metric is increase over perfect market
outcome (Quantity-weighted Lerner Index). - Results in 2003 show market continues to function
well, with modest differences from competitive
baseline.
21Competitive Benchmark Results 2003 vs. 2002
Note Energy Clearing Price is the ECP prior to
March 1, 2003 the Real-Time Hub Price as of
March 1, 2003
22Other Conclusions
- The New England markets continued to perform
competitively in 2003 with no evidence of
significant economic or physical withholding. - Day-ahead and real-time energy prices exhibit
good convergence. - Average day-ahead/real-time spread was 1.10 MWh
during first year of SMD - Virtual trading volumes were reasonable in 2003,
contributing to the convergence between the
day-ahead and real-time prices.
23Other Conclusions (Continued)
- Real-time prices in adjacent regions continue to
be inefficiently arbitraged. - The ISO-NE Demand Response Program provides a
modest real-time reduction when necessary. - Mild conditions in 2003 limited the
implementation of such reductions. - Regulation was only ancillary service market in
2003. - A market flaw was identified in 2003 and
corrected in early 2004.
24Other Conclusions (Continued)
- Out-of-merit operation an on-going issue.
- Primarily in import-constrained areas.
- Would be helped by increase in quick-start
capacity. - Continuing to investigate unit commitment and
software resolutions. - New Forward Reserve Market should help incent
this capacity. - Resource Adequacy in constrained areas in an
on-going issue. - Clear market deficiency when large numbers of
units required for reliability do not cover
going-forward costs.