Western Renewable Energy Zone WREZ Concept as of 112707 - PowerPoint PPT Presentation

1 / 11
About This Presentation
Title:

Western Renewable Energy Zone WREZ Concept as of 112707

Description:

How the Western Interconnection-wide REZ idea evolved. Status of efforts to brainstorm a work plan ... Using 3Tier data to map and characterize NW wind areas ... – PowerPoint PPT presentation

Number of Views:25
Avg rating:3.0/5.0

less

Transcript and Presenter's Notes

Title: Western Renewable Energy Zone WREZ Concept as of 112707


1
Western Renewable Energy Zone (WREZ) Concept(as
of 11/27/07)
2
Outline of Presentation
  • How the Western Interconnection-wide REZ idea
    evolved
  • Status of efforts to brainstorm a work plan
  • Rough outline of the work plan
  • Larsons observations on
  • Applicability of WREZ work to Action 4, 5, 10
  • Connection with yesterdays idea on
  • Using 3Tier data to map and characterize NW wind
    areas
  • Compare areas with transmission expansion plans

3
How Idea Evolved
  • Several individual states undertaking analysis of
    renewable resources and transmission needed to
    move power to loads
  • Texas pioneering concept under name of
    Competitive Renewable Energy Zones (CREZ)
  • Colorado identifying zones as required by state
    law
  • California launched RETI
  • Arizona utilities contracted for study
  • Nevada Governor established committee
  • Sub-regional work such as the NW wind integration
    work
  • September 28-29 WGA renewables/transmission
    summit in Ft. Collins
  • WREZ idea recommended as a next step
  • Small team formed to explore feasibility of a
    WREZ project
  • October 19 WGA meeting with DOE Asst Secretary
    Karsner and DOE Office of Electricity
  • November 5 briefing and review by WIEB/CREPC
  • November 7 briefing and review by WGA Staff
    Council
  • November 7 to today developing a rough work
    plan to be more broadly vetted

4
1. Why do we need a Western REZ initiative?
  • Supplement state-by-state assessments to provide
    a picture of potentially lower cost regional
    renewable generation alternatives
  • Identification of WREZs will enable all parties
    to make more informed decisions about
  • The cost of renewable power
  • Optimal transmission to move renewables
  • Potential partners in developing transmission
  • Where developers should site generation to access
    transmission and minimize environmental impacts

5
2. What are the other benefits of a Western REZ
initiative?
  • WREZ process would lay factual foundation for
    interstate collaboration on
  • Transmission and generation planning
  • Regulatory reviews of proposed transmission
    facilities
  • Cost allocation
  • Needs assessments

6
Outline of Rough Work Plan
  • Phase 1
  • Identify commercial potential, aggregate into
    zones, estimate bus bar price and delivered price
    of power
  • Maximize consistency with state and sub-regional
    work
  • Ground truth data through a stakeholder process
    complete 9/07
  • Phase 2
  • Have sub-regional planning groups and WECC
    develop conceptual transmission plans to deliver
    power from highest ranking REZs
  • Phase 3
  • Report to Governors on remaining obstacles to
    transmission to move renewables
  • Investigate reasons for LSEs not procuring
    renewables
  • Phase 4
  • Identify institutional options for coordinated
    permitting and cost recovery

7
Organization of Effort
  • Steering Committee (Govs, PUCs, CEOs of LSE,
    renewable generators and environmental groups)
  • Technical Committee
  • Diverse geography, diverse organizations
    (states/provinces, generation developers,
    transmission developers, environmental groups,
    etc.)
  • Executive Committee for day-to-day management

8
Potential Organization of WREZ Effort
Steering Committee (Govs, LSE CEOs, Env group
CEOs)
Technical Committee (Geographically and
organizationally diverse)
Executive Committee (to manage day-to-day
activities)
Work groups
Work groups
Work groups
Project support staff WGA/WIEB
secretariat Outreach coordinator/
facilitators National labs
9
Proposed Approach
  • Zone development
  • Update resource assessment data (wind, solar,
    geothermal, biomass)
  • Input from stakeholders on promising resource
    areas (based on production value, exclusion
    areas, land ownership, etc)
  • Define preliminary zones
  • Develop supply cost curves
  • Transmission corridor development
  • Develop crayon-level transmission corridors that
    connects zones and load centers
  • Input from stakeholders on promising transmission
    corridors (based on resources, exclusion areas,
    land, etc)
  • Optimization of transmission corridors to zones

10
Larsons Observations (1)
  • Connections to NWIAP items 4, 5, 10
  • 4. NTAC work on a methodology would be helpful
    and if completed by Sept 08 can provide a
    template for other areas
  • 5. Columbia Grid and NTTG work on applying a
    methodology would be helpful.
  • WREZs should be identified by 9/08
  • TEPPC 2007 modeling should be complete before
    9/08
  • 10. NTAC/Columbia Grid/NTTG work on upgrades to
    deliver wind from MT
  • This would be useful work

11
Larsons Observations (2)
  • 3Tier data to map/characterize NW wind resource
    areas and compare with transmission proposals
  • Seems to be exactly in line with WREZ game plan
  • Needs to be coordinated with WREZ work
Write a Comment
User Comments (0)
About PowerShow.com