Title: Project Close-Out Planning, Critical Path, Contingency Planning and Risk Analysis
1Project Close-Out Planning, Critical Path,
Contingency Planning and Risk Analysis
- John N. Galayda Director, LCLS Construction
- May 13, 2009
2Project Closeout
- Plan laid out 12/2008
- Based on DOE M 413.3-1 (3-28-03)
- This manual was cancelled, 1/13/2009
- DOE N 251.75
- Project Transition/Closeout (CD-4)
- DOE G 413.3-16 (9-24-2008)
3(No Transcript)
4Table of Contents
- Tailoring
- Project Performance and Completion Criteria
- Readiness Assessment/Operational Readiness Review
- Commissioning Plan
- Transition to Operations Plan
- Quality Assurance
- Environmental Management System Revision
- Safeguards, Security and Safety Plan
- Post CD-4 Approval Requirements (related to
transition/closeout)
5Project Performance and Completion Criteria
- Defined in the Critical Decision approvals,
refined in - Global Requirements Document
- Defined minimum goals for each stage of
commissioning, prerequisite to starting next
stage - http//www-ssrl.slac.stanford.edu/lcls/PRD/1.1-001
-r0.pdf - LCLS Start-up Test Plan
- Defined criteria for completion of commissioning
stages - Injector
- Linac
- Linac-to-Undulator
- Undulator Beam Dump
- Front-End Enclosure
- Near Experiment Hall
- X-Ray Tunnel Far Experiment Hall
- Key Performance Parameters Prerequisite to the
Approval of CD-4, Start of Operations - http//www-ssrl.slac.stanford.edu/lcls/prd/1.1-002
-r1.pdf
6Project Performance and Completion Criteria
7Project Performance and Completion Criteria
- For Closeout Verify Performance Criteria Have
Been Met
7
8Commissioning Plan
- Equipment checkout integrated with staged
accelerator readiness sequence - Safety readiness and technical readiness have
been integrated - Injector
- linac
- Linac-to-Undulator,Beam Dump, Front-End
- Near Hall
- X-Ray Tunnel, Far Experiment Hall
- Photon Beam Systems will follow this path
- Technical/scientific accelerator commissioning
plans are also in good shape - Conventional Facilities commissioning agent
(contract work) results
8
9Readiness Assessment/Operational Readiness Review
- Safety Assessment Document has been developed and
expanded in stages, latest at - https//www-internal.slac.stanford.edu/ad/addo/SAD
/sadindex.html
System Lead Deliverable Date
Injector Schultz/Hislop/ Scharfenstein. Injector SAD 3/2007
Linac Schultz/Hislop/ Scharfenstein Injector/Linac SAD 12/2007
Linac-to-Undulator-to-Dump, Front-End Enclosure Schultz/Hislop/ Scharfenstein Accel Sys SAD 8/2008
Near Experiment Hall Arthur SAD extension 8/2009
X-Ray Tunnel, Far Experiment Hall Arthur SAD extension 1/2010
9
10Readiness Assessment/Operational Readiness Review
- Not governed by the Accelerator Safety Order
(except for radiation shielding) - SLAC Building Inspection Office assesses building
readiness for handover - BIO determination will be included in the
closeout package
System Lead Deliverable Date
CF Saenz (for LCLS) Test results, cleared punchist LTU-NEH 9/2009 FEH, Hutches 3/2010
10
11Quality Assurance, Safeguards/Security
- Guidance to keep the QA plan current
- SLAC Quality Assurance Program-
- https//www-internal.slac.stanford.edu/oa/document
s/assurance.pdf - June 2008
- Governing document
- Safeguards/Security
- Existing SLAC program
12Transition to Operations Plan
- SLAC Linac operations staffing, policies and
procedures are mature - Criteria for transition to operations of new
systems were well-established - Criteria were met at each stage as part of the
Accelerator Readiness Review Process - Criteria for transition-to-operations of Photon
Beam Systems will be patterned after SLAC SOP - XFD operations organization is in growth spurt
- Handover from Project to Directorate/XFD
commissioning organization will be part of ARR
for the Near Hall and subsequent SLAC instrument
readiness reviews - Handover deliverables will ensure safe operation
sophistication will grow as operations and
organization mature - SLAC Guidelines for Operations will be amended to
include XFD operations, and offered as part of
Project Closeout
12
13Project Closeout Report
- Target date 10/2010
- Technical, scope, cost and schedule baseline
accomplishments - Financial closeout, including a final cost report
- Deactivation, decontamination and decommissioning
planning (if required) - Closeout approvals
- Permits, licenses, and/or environmental
documentation - Contract closeout status
- Adjustments to obligations and costs
- Photographic documentation
- Baseline change control log
14Critical Path
- Detection of X-Rays in Far Hall after
January-March 2010 shutdown for K-10 substation
replacement - Accelerator, Undulator-to-AMO maintenance only
- Completion/testing of Personnel Protection for
XRT and FEH.
15(No Transcript)
16Level 2 Milestones
17- SXR instrument
- LCLS Project has no obligation to
install/integrate SXR hardware after 3/2010
18Project Contingency
- Major scope additions since last review
- SXR Instrument installation/integration 1.5M
- Adds scientific capability to LCLS in 2010
- Leverages a 5M hardware contribution by
consortium - 3 instruments (AMO, XPP, SXR) by end of 2010
- Far Hall Hutch 6 and Mezzanine 800K
- Adds workspace to Far Experiment Hall
- Completes originally envisioned count of hutches
- Mezzanine installation would be disruptive later
in operation - Building 28 office area increase 2.15M
- Additional technical/safety oversight of work
- Refined basis of estimate (A/E design)
- Expansion to area previously envisioned for SSRL
- Permits co-location of XFD personnel (albeit far
from LCLS)
19Estimate at Complete
- LCLS EAC for TEC 345.0M
- Remaining Work (ETC) 29.4M
- Remaining Contingency 7.0M
- Contingency (Cost to Go) 23.9
- Contingency (Comm to Go) 27.5
- Adding scope to optimize science. Reserve
adequate contingency to address remaining risks
to project. - LCLS EAC for OPC 62.0M
- Remaining Work (ETC) 16.7M
- Remaining Mgmt Reserve 6.0M
- Mgmt Reserve (Cost to Go) 36.0
- Increasing Mgmt Reserve due to lower than
anticipated commissioning costs, so far
20Bottoms-up Contingency Assessment
- Assessment is a bottoms-up, risk-based estimate
of potential need by each CAM - Historically conservative
21(No Transcript)
22(No Transcript)
23Top-Down Contingency Assessment
- Correct cost-to-go for Pending BCRs
- 800K in allowances
- Assume all schedule variances are real
- Remaining work, assuming all schedule variances
will be realized as cost 32M - Remaining contingency 8M
- Contingency allocation, top down 11 avg
- 20 to civil construction not yet awarded
- 5 to civil construction already contracted
- 5 to SLAC effort-to-go
- 10 on other MS not yet awarded
- 4.5M unassigned contingency
24Contingency Wish List
25Alternative for Office Space
- Tilt-up building
- Fast construction
- LEEDS Gold
- 18,500GSF
- More convenient access to LCLS Halls
- Proposals under evaluation
- Will wait for award of hutches and April (maybe
May) actuals to decide
26Other Project Costs
- Allocated 2M for ramp-up of x-ray commissioning
effort in 2009 not fully committed - 6M cumulative management reserve
- Wish list
- 1.77M reserve in 2009
- Commit 1M soon
- 2010
- must reserve 2M
- for risk mitigation
- 3M to go
27Risk Assessment
- Happily, many technical risks to the project may
be retired - Civil construction generic risks are pretty
invariant right up to the end of the project. - While less cost-to-go means less schedule risk,
the approach of CD-4 milestone means schedule
risk becomes more significant
28Risk Assessment (contd)
- Major risk is civil construction claims
- appropriate accrual was put in baseline TEC
- Major schedule risk is civil construction
schedule - As noted in Risk Registry
29End of Presentation
29