Project Close-Out Planning, Critical Path, Contingency Planning and Risk Analysis

About This Presentation
Title:

Project Close-Out Planning, Critical Path, Contingency Planning and Risk Analysis

Description:

Criteria for transition to operations of new systems were well-established ... Accelerator, Undulator-to-AMO: maintenance only ... –

Number of Views:194
Avg rating:3.0/5.0
Slides: 30
Provided by: wwwssrlSl3
Category:

less

Transcript and Presenter's Notes

Title: Project Close-Out Planning, Critical Path, Contingency Planning and Risk Analysis


1
Project Close-Out Planning, Critical Path,
Contingency Planning and Risk Analysis
  • John N. Galayda Director, LCLS Construction
  • May 13, 2009

2
Project Closeout
  • Plan laid out 12/2008
  • Based on DOE M 413.3-1 (3-28-03)
  • This manual was cancelled, 1/13/2009
  • DOE N 251.75
  • Project Transition/Closeout (CD-4)
  • DOE G 413.3-16 (9-24-2008)

3
(No Transcript)
4
Table of Contents
  1. Tailoring
  2. Project Performance and Completion Criteria
  3. Readiness Assessment/Operational Readiness Review
  4. Commissioning Plan
  5. Transition to Operations Plan
  6. Quality Assurance
  7. Environmental Management System Revision
  8. Safeguards, Security and Safety Plan
  9. Post CD-4 Approval Requirements (related to
    transition/closeout)

5
Project Performance and Completion Criteria
  • Defined in the Critical Decision approvals,
    refined in
  • Global Requirements Document
  • Defined minimum goals for each stage of
    commissioning, prerequisite to starting next
    stage
  • http//www-ssrl.slac.stanford.edu/lcls/PRD/1.1-001
    -r0.pdf
  • LCLS Start-up Test Plan
  • Defined criteria for completion of commissioning
    stages
  • Injector
  • Linac
  • Linac-to-Undulator
  • Undulator Beam Dump
  • Front-End Enclosure
  • Near Experiment Hall
  • X-Ray Tunnel Far Experiment Hall
  • Key Performance Parameters Prerequisite to the
    Approval of CD-4, Start of Operations
  • http//www-ssrl.slac.stanford.edu/lcls/prd/1.1-002
    -r1.pdf

6
Project Performance and Completion Criteria
7
Project Performance and Completion Criteria
  • For Closeout Verify Performance Criteria Have
    Been Met

7
8
Commissioning Plan
  • Equipment checkout integrated with staged
    accelerator readiness sequence
  • Safety readiness and technical readiness have
    been integrated
  • Injector
  • linac
  • Linac-to-Undulator,Beam Dump, Front-End
  • Near Hall
  • X-Ray Tunnel, Far Experiment Hall
  • Photon Beam Systems will follow this path
  • Technical/scientific accelerator commissioning
    plans are also in good shape
  • Conventional Facilities commissioning agent
    (contract work) results

8
9
Readiness Assessment/Operational Readiness Review
  • Safety Assessment Document has been developed and
    expanded in stages, latest at
  • https//www-internal.slac.stanford.edu/ad/addo/SAD
    /sadindex.html

System Lead Deliverable Date
Injector Schultz/Hislop/ Scharfenstein. Injector SAD 3/2007
Linac Schultz/Hislop/ Scharfenstein Injector/Linac SAD 12/2007
Linac-to-Undulator-to-Dump, Front-End Enclosure Schultz/Hislop/ Scharfenstein Accel Sys SAD 8/2008
Near Experiment Hall Arthur SAD extension 8/2009
X-Ray Tunnel, Far Experiment Hall Arthur SAD extension 1/2010
9
10
Readiness Assessment/Operational Readiness Review
  • Not governed by the Accelerator Safety Order
    (except for radiation shielding)
  • SLAC Building Inspection Office assesses building
    readiness for handover
  • BIO determination will be included in the
    closeout package

System Lead Deliverable Date
CF Saenz (for LCLS) Test results, cleared punchist LTU-NEH 9/2009 FEH, Hutches 3/2010
10
11
Quality Assurance, Safeguards/Security
  • Guidance to keep the QA plan current
  • SLAC Quality Assurance Program-
  • https//www-internal.slac.stanford.edu/oa/document
    s/assurance.pdf
  • June 2008
  • Governing document
  • Safeguards/Security
  • Existing SLAC program

12
Transition to Operations Plan
  • SLAC Linac operations staffing, policies and
    procedures are mature
  • Criteria for transition to operations of new
    systems were well-established
  • Criteria were met at each stage as part of the
    Accelerator Readiness Review Process
  • Criteria for transition-to-operations of Photon
    Beam Systems will be patterned after SLAC SOP
  • XFD operations organization is in growth spurt
  • Handover from Project to Directorate/XFD
    commissioning organization will be part of ARR
    for the Near Hall and subsequent SLAC instrument
    readiness reviews
  • Handover deliverables will ensure safe operation
    sophistication will grow as operations and
    organization mature
  • SLAC Guidelines for Operations will be amended to
    include XFD operations, and offered as part of
    Project Closeout

12
13
Project Closeout Report
  • Target date 10/2010
  • Technical, scope, cost and schedule baseline
    accomplishments
  • Financial closeout, including a final cost report
  • Deactivation, decontamination and decommissioning
    planning (if required)
  • Closeout approvals
  • Permits, licenses, and/or environmental
    documentation
  • Contract closeout status
  • Adjustments to obligations and costs
  • Photographic documentation
  • Baseline change control log

14
Critical Path
  • Detection of X-Rays in Far Hall after
    January-March 2010 shutdown for K-10 substation
    replacement
  • Accelerator, Undulator-to-AMO maintenance only
  • Completion/testing of Personnel Protection for
    XRT and FEH.

15
(No Transcript)
16
Level 2 Milestones
17
  • SXR instrument
  • LCLS Project has no obligation to
    install/integrate SXR hardware after 3/2010

18
Project Contingency
  • Major scope additions since last review
  • SXR Instrument installation/integration 1.5M
  • Adds scientific capability to LCLS in 2010
  • Leverages a 5M hardware contribution by
    consortium
  • 3 instruments (AMO, XPP, SXR) by end of 2010
  • Far Hall Hutch 6 and Mezzanine 800K
  • Adds workspace to Far Experiment Hall
  • Completes originally envisioned count of hutches
  • Mezzanine installation would be disruptive later
    in operation
  • Building 28 office area increase 2.15M
  • Additional technical/safety oversight of work
  • Refined basis of estimate (A/E design)
  • Expansion to area previously envisioned for SSRL
  • Permits co-location of XFD personnel (albeit far
    from LCLS)

19
Estimate at Complete
  • LCLS EAC for TEC 345.0M
  • Remaining Work (ETC) 29.4M
  • Remaining Contingency 7.0M
  • Contingency (Cost to Go) 23.9
  • Contingency (Comm to Go) 27.5
  • Adding scope to optimize science. Reserve
    adequate contingency to address remaining risks
    to project.
  • LCLS EAC for OPC 62.0M
  • Remaining Work (ETC) 16.7M
  • Remaining Mgmt Reserve 6.0M
  • Mgmt Reserve (Cost to Go) 36.0
  • Increasing Mgmt Reserve due to lower than
    anticipated commissioning costs, so far

20
Bottoms-up Contingency Assessment
  • Assessment is a bottoms-up, risk-based estimate
    of potential need by each CAM
  • Historically conservative

21
(No Transcript)
22
(No Transcript)
23
Top-Down Contingency Assessment
  • Correct cost-to-go for Pending BCRs
  • 800K in allowances
  • Assume all schedule variances are real
  • Remaining work, assuming all schedule variances
    will be realized as cost 32M
  • Remaining contingency 8M
  • Contingency allocation, top down 11 avg
  • 20 to civil construction not yet awarded
  • 5 to civil construction already contracted
  • 5 to SLAC effort-to-go
  • 10 on other MS not yet awarded
  • 4.5M unassigned contingency

24
Contingency Wish List
  • Technical

25
Alternative for Office Space
  • Tilt-up building
  • Fast construction
  • LEEDS Gold
  • 18,500GSF
  • More convenient access to LCLS Halls
  • Proposals under evaluation
  • Will wait for award of hutches and April (maybe
    May) actuals to decide

26
Other Project Costs
  • Allocated 2M for ramp-up of x-ray commissioning
    effort in 2009 not fully committed
  • 6M cumulative management reserve
  • Wish list
  • 1.77M reserve in 2009
  • Commit 1M soon
  • 2010
  • must reserve 2M
  • for risk mitigation
  • 3M to go

27
Risk Assessment
  • Happily, many technical risks to the project may
    be retired
  • Civil construction generic risks are pretty
    invariant right up to the end of the project.
  • While less cost-to-go means less schedule risk,
    the approach of CD-4 milestone means schedule
    risk becomes more significant

28
Risk Assessment (contd)
  • Major risk is civil construction claims
  • appropriate accrual was put in baseline TEC
  • Major schedule risk is civil construction
    schedule
  • As noted in Risk Registry

29
End of Presentation
29
Write a Comment
User Comments (0)
About PowerShow.com