Title: SPS Smoke Removal Control System Reengineering
1SPS Smoke Removal Control System Re-engineering
2Outline
- Introduction
- Workshop conclusions
- Functional Safety Study
- Architecture Proposal
- Action Plan
- Conclusions
3Introduction
Responsibilities
Owner DSO
TIS
FB
ST
CV
AA
4Workshop Conclusions
- Fire Brigade mission defined
- Current system
- Objective Improve ventilation and facilitate FB
job - Goal Oriented to protect the machine
- (machine closed, electric fire)
- It is not a real smoke removal system
- It is not a safety system
- Assure a reliable control system at least in such
a conditions - Functional Safety Study
5Functional Safety Analysis
Architectures
TDS
ACS
EC GTD
EC Landis
Concentrateurs
Concentrateurs
Air Injection
Air Extraction
6External Functional Analysis
7Internal Functional Analysis
Safety Function 1 Fire alarms to SCR
Detection Equipment BAx E1
8Internal Functional Analysis
Safety Function 2 Smoke Removal Commands
9Internal Functional Analysis
Safety Function 3 Interlock
Smoke Removal Synoptics Industrial PC BAs - E3
10Dysfunctional Analysis
Safety Functions
11Functional Safety Analysis
Critical components
12Dysfunctional Analysis
Critical Environments
13Recommendations
- Based on the simplified architecture
- Redundant path for smoke removal and Interlock
commands - CSAM safety network
- Supervision of critical components
- Autotest / test
- Performance measure
- Audit software of critical components
- Special care when modifying critical components
- Procedures
- Maintenance coordination
- Redundant power supply
- Not cut by Emergency stop
- Update documentation for operation and
maintenance - EDMS
- Avoid smoke removal commands from SCR and TCR
- Improve when CSAM safety network available
14Architecture Proposal
TCR
SCR
spstds1 EC GTD
srvtds1 TDS
stdlog Logging
PLC Concentrator
BA Synoptic
PLC Extraction
Power supply - Redundant power supply - Review
?t Performance measure Modifications
procedures Maintenance coordination Documentation,
EDMS
PLC Injection
PLC CDIN
15Action Plan
16Conclusions
- Implementation phase
- ? weekly follow-up
- ? System ready for March 2000
- People safety improvement when machine is open
- ? NEW PROJECT (This request being under the
responsibility of SL/DSO and TIS)