Software Support for Industrial Controls Contract Organization

Description:

preventive. system & database administration. user support & documentation production ... Quality Assurance Plan. Maintenance Management System. C168/ST ... – PowerPoint PPT presentation

Number of Views:14
Avg rating:3.0/5.0
Slides: 12
Provided by: NIN46
Category:

less

Transcript and Presenter's Notes

Title: Software Support for Industrial Controls Contract Organization


1
Software Support for Industrial Controls
ContractOrganization
  • IT-2711 C168/ST
  • STTC Meeting 25/9/2000
  • Eva Sanchez-Corral


2
Scope of the contract
  • To OUTSOURCE the OPERARTION MAINTENANCE and the
    DEVELOPMENT of monitoring and control systems on
    a RESULT-oriented basis.

3
Target
  • Start-up 15 October 2000
  • Duration 3 years 2 renewals of 1 year
  • Volume ? 1 to 1.5 MCHF/year

4
Scope of Services
  • Projects
  • small medium size
  • according to ESA Software Engineering standards
    PSS-05 and CERN standards
  • Operation and Maintenance
  • corrective
  • preventive
  • system database administration
  • user support documentation production

5
Contract Organization (1)
  • Strategy
  • OM and Projects activities follow-up
  • Tools (MP5, EDMS, Project follow-up)
  • Active participation of CERN staff
  • Regular meetings (with Contractor, CERN C168
    users)
  • Performance evaluation
  • Project Milestone plans
  • Training
  • CERN staff and Contractor

6
Contract Execution (1)
  • OM Service
  • Transition period of 6 months, Learning period
  • The Contractor should take over of the systems
    with CERNs collaboration.
  • Maintenance Management System MP5
  • Definition of
  • systems to be maintained and
  • maintenance tasks to be performed
  • Interventions follow-up
  • Unplanned OM tasks maximum intervention times
    required
  • Volume of activities revised twice a year
  • Maintenance Plan and Quality Assurance Plan
  • To be provided by Contractor at the latest
    February 2000

7
Contract Execution (2)
  • Projects
  • 1) User Requirements Document Project
    Management Plan by Project Leader
  • Review by C168 Review team
  • Sent to Contractor
  • 2) Contractors offer (financial and technical)
  • According to Tender Reference projects
  • CERN will approve/reject Contractors proposal
  • 3) Follow-up
  • Project life cycle and Milestones
  • 4) After successful Provisional Acceptance
    Testing -gt 2 years guarantee
  • OM repair all non-conformance with the
    specification done by Contractor
  • 5) Final Acceptance

8
Contract Organization (2)
  • CERN C168 Team responsibility chart

9
Contract Organization (3)
  • OM activities (2) systems to be maintained

10
Conclusions
  • The contract should
  • improve the quality of OM and of the new systems
  • partially compensate the decrease of staff
  • Outsourcing a complex activity
  • Give the responsibility to the contractor
  • Control its monopoly situation
  • Manage our loss of know-how (keep doing
    computing)
  • Change our habits
  • Methods, Standards
  • Promote collaboration within ST

11